Observations

PRL HSEQ Portal
Printed: 22 Jul 2026 · 16:25
Report:Observations
Period:All dates
Generated:2026-07-22 16:25:50
Records:1473
DateTypeCategoryDescriptionAreaExact LocationDepartmentCompanyContractor NameRoutine / ShutdownAction TakenLocationAssigned ToStatusTarget DateClosed Date
2025-07-01Unsafe ConditionEquipmentPumps rotation were found reversed. (Skid Pump, Circulation motor, Foam Filling Pump, Boundary Wall Pump)Foam Skid PumpFoam Skid PumpRotaryPRLRoutineKemari TerminalteamClosed2025-07-02
2025-07-01Unsafe ActPPEAt tank #05, a worker was observed carrying out excavation work without wearing face mask and gloves. Informed the site supervisor.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-02
2025-07-01Unsafe ActProcedureDuring round at tank #56 (KT), a fitter was observed changing a grander disk without unplugging the grander.Tank FarmTank#56CivilCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-02
2025-07-01Unsafe ActPPEAt tank #56 (KT), civil Foreman Mr. Tanveer was observed not using the safety goggles within the tank foundation.Tank FarmTank#56CivilCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-02
2025-07-01Unsafe ActProcedureAt tank #13, a worker was observed shifting materials while using the stairs. As both of his hands were occupied, he failed to maintain three points of contact. The worker was counseled.Tank FarmTank#13CivilCONTRACTORWMSRoutineKorangi RefineryteamClosed2025-07-02
2025-07-03Unsafe ActProcedureAt tank #13, a worker was observed holding the rope of the suspended platform from ground level instead of securing it to a fixed point. The worker was counseled.Tank FarmTank#13CivilCONTRACTORWMSRoutineKorangi RefineryteamClosed2025-07-04
2025-07-03Unsafe ConditionLack of SupervisionAt tank #11, a damaged rope was being used for lifting activity. Informed the site supervisor.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-04
2025-07-03Unsafe ActWork at HeightAt tank #11, a worker was observed using a hammer at height with a damaged tool tie. The worker was counseled.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-04
2025-07-03Unsafe ActWork at HeightAt tank #11, a worker was observed using a hammer at height without fastening it with a tool tie. The worker was counseled.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-04
2025-07-11Unsafe ConditionElectricalAt tank #11, the main electrical supply line was observed exposed. Informed the site supervisor.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-12
2025-07-11Unsafe ConditionLack of SupervisionAt tank #05, an energized fresh air compressor was observed on site which was not in use. Informed to the site supervisor.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-12
2025-07-10Unsafe ConditionEnvironmentAt tank #05, seepage was observed form the engine side of the air compressor. Informed the site supervisor.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-11
2025-07-10Unsafe ConditionLack of SupervisionAt tank #05, air compressor that was being used for sandblasting activity, its hose was not tied with a whip. Informed the site supervisor.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-11
2025-07-10Unsafe ConditionHealthInside tank #11, loose material (channels and wedges) was observed on scaffolding platform. Informed the site supervisor.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-11
2025-07-10Unsafe ActPPEAt tank #05, 3 ATL staff members were observed climbing the monkey ladder without wearing gloves and chin strap. Counseling was done.Tank FarmTank#05 , 03ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-11
2025-07-10Unsafe ActPPEAt tank #05, multiple workers were observed performing vacuum test with folded sleeves and were not wearing rubber gloves. Workers were counseled.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-11
2025-07-08Unsafe ConditionProcedureFoam skid pump water discharge line spot damage needs replacement.Foam Skid PumpFoam Skid PumpCivilPRLRoutineKorangi RefineryteamClosed2025-07-09
2025-07-08Unsafe ConditionProcedureJetty line 4’’ butterfly valve not proper working. (Valve was later changed)Tank FarmJetty lineStationaryPRLRoutineKemari TerminalteamClosed2025-07-11
2025-07-07Unsafe ActPPEAt Fire water pump house, M/s RE worker was observed operating a grinder without wearing earplugs, worker was counseled.Fire Water Pump HouseFire Water Pump HouseStationaryCONTRACTORRERoutineKorangi RefineryteamClosed2025-07-08
2025-07-07Unsafe ActEquipmentAt Fire water pump house, an energized grinder was found unattended at site, informed the site supervisor.Fire Water Pump HouseFire Water Pump HouseStationaryCONTRACTORRERoutineKorangi RefineryteamClosed2025-07-09
2025-07-07Unsafe ActPPEAt Fire water pump house, 3 M/s RE riggers were observed shifting a 12-inch pipeline during installation of pump, wearing normal gloves instead of rigging impact gloves. The site supervisor was informed.Fire water pump houseFire Water Pump HouseStationaryCONTRACTORRERoutineKorangi RefineryteamClosed2025-07-08
2025-07-07Unsafe ActPPEAt road #12, a worker was observed using a hammer without wearing the safety gloves, the worker was counseled.Road# 12Road# 12CivilCONTRACTORWMSRoutineKorangi RefineryteamClosed2025-07-08
2025-07-19Unsafe ActPPEAt API separator, three M/s Q.K Builders workers were performing sand backfilling activity without wearing safety goggles, safety gloves, and face masks. Informed to site supervisor and counseling done.API SeparatorAPI SeparatorCivilCONTRACTORQK BuildersRoutineKorangi RefineryteamClosed2025-07-20
2025-07-19Unsafe ActWork at HeightAt 105C8, two M/s WMS workers were working at height without wearing chinstraps. Counseling was done.Plant Area105C8StationaryCONTRACTORWMSRoutineKorangi RefineryteamClosed2025-07-19
2025-07-19Unsafe ActPPEAt WWTP pit, four M/s Afzal Contractor workers were carrying out stonework inside a 10-ft deep pit without wearing gloves and without proper ladder access. Informed to Mr. Afzal Chaudhry and WMS representative.WWTPWWTP PitCivilCONTRACTORAfzalRoutineKorangi RefineryteamClosed2025-07-20
2025-07-18Unsafe ConditionLack of SupervisionAt tank #5, the lifting rope was becoming loose. Site supervisor was informed and instructions to replace the rope were given.Tank FarmTank# 05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-19
2025-07-18Unsafe ConditionWork at HeightAt road no#3 (ISOM), scaffolding material was lying in the ISOM are without any barricading. Informed to site supervisor (M/s AKS Brothers).Tank FarmRoad #3CivilCONTRACTORAKSRoutineKorangi RefineryteamClosed2025-07-19
2025-07-18Unsafe ConditionPPEAt tank #56, an electrical D.B receptacle got overheated and melted due to adjoining of internal wires. The observation was spotted by Stationary Mr. Furrukh and reported by Wasif Ali Fireman. The matter was immediately investigated by PRL electrical team, fire and stationary safety personnel and sorted out the same.Tank FarmTank# 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-19
2025-07-17Unsafe ActPPEDuring the diesel fuel filling activity at excavator at around 15:00 hrs, the operator switched on the ignition and operated the Excavator without completing the filling job. PRL Safety personnel at site immediately stopped the operator and a counseling was done.Tank FarmAt ExcavatorStationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-18
2025-07-17Unsafe ActPPEDuring civil work on foundation, at tank #56, workers were observed without safety goggles.Tank FarmTank# 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-18
2025-07-17Unsafe ActProcedureDuring Gas Cutting activity, at tank #56, the fitter helper was observed without face shield.  Tank FarmTank# 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2025-07-18
2025-07-25Unsafe ActVehicleDuring the safety round at Tank #11, it was observed that an iron beam was loaded onto a Shehroz truck, but it was extending beyond the truck’s body, posing a risk of striking objects or causing accidents while in transit. This is for your information and necessary corrective actions.Tank FarmTank# 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-26
2025-07-25Unsafe ActHousekeepingAt storm pit, M/s RE workers were carrying the hot work activity inside the crane barricaded area with the canopy for hot work placed within the barricade. Counseling was provided.Storm PitStorm PitStationaryCONTRACTORRERoutineKorangi RefineryteamClosed2025-07-26
2025-07-25Unsafe ConditionFalling ObjectAt tank #11, a hammer with a damaged tool tie was observed. Informed to the HSEQ and site supervisor.Tank FarmTank# 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-26
2025-07-25Unsafe ConditionEnvironmentAt tank #5, during sandblasting activity, oil leakage was observed from the engine side of the air compressor (M/s ATL). Informed to HSEQ supervisor.Tank FarmTank# 05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-26
2025-07-25Unsafe ConditionLack of SupervisionAt tank #5, during inspection prior to the crane lifting operation, leakage and dripping from crane was observed. Activity has been put on hold and informed to rigging supervisor.Tank FarmTank# 05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-25
2025-09-01Unsafe ConditionEnvironmentAt back side of HSEQ caravan, filled garbage bags needs to be removed.HSEQ caravanHSEQ caravanA&SPRLShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ConditionEnvironmentAt access to furnace area, near road 10 and around WBL. leftover scaffolding materials need to be removed. Informed to Civil departmentPlant AreaFurnace areaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ActPPEAt road # 14, activity was about to start on the furnace oil line of Tank #1 under the permit issued for Tank #2. The fireman stopped the work and instructed the team to obtain a separate permit for this job, as it was not covered under the existing permit.  Road # 14Road # 14StationaryCONTRACTORREShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ActPPEAt 201-DN, during flange tightening work, WMS workers were hammering without wearing safety gloves. The supervisor was informedAt 201-DNAt 201-DNStationaryCONTRACTORWMSShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ConditionWork at HeightScaffolding materials were present at the back side of the control room without any barricading.Plant AreaBackside of Control RoomCivilCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ActLine of FireDuring crane operations at the Descon yard, two storekeepers were observed crossing the barricaded line of fire. The incident was reported to the Descon HSE supervisor, and counseling was conducted.DEL YardDEL YardConstructionCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ActVehicleAt road # 10, the forklift operator was heading toward the DEL yard with material loaded on the forks, but he had no visibility ahead.Road # 10Road # 10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ConditionWork at HeightAt below area of main stack, access to furnace area, near control room, WBL & below area of AFC. leftover scaffolding materials need to be removed. Informed to Civil department.Plant AreaBelowAarea of Main StackCivilPRLShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ConditionLack of SupervisionAt road #10 and near Stationary caravan, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Road# 10Road# 10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ConditionLack of SupervisionAt road #10 and near Stationary caravan, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Road# 10Road# 10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-09-01Unsafe ActPPEAt Road #14, during de-spading work, workers of M/s RE were found working in the dark without wearing safety goggles and stud bolts were placed on the road. The team was counseled at site and instructed to arrange proper lighting.Road #14Road #14StationaryCONTRACTORUEShutdownKorangi RefineryteamClosed2025-09-02
2025-09-01Unsafe ActPPEAt below area of 105-Cs, safety helmet was found on HP streamline. Informed to stationary supervisor for removal.Plant AreaBelow Area of 105-CsStationaryCONTRACTORUEShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ConditionLack of SupervisionAt desalter area. Unattended pressurized gas cylinder was found on walkway. informed to M/s HSE supervisor.Plant AreaDesalter AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-31
2025-08-30Unsafe ConditionLack of SupervisionAt road #10 and Stationary caravan, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Road #10Road #10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-31
2025-08-30Unsafe ConditionWork at HeightAt below area of 103-B, near control room & at AFC platform, leftover scaffolding materials need to be removed. Informed to Civil department.Plant AreaBelow Area of 103-BCivilPRLShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ActPPEAt DEL yard, during crane operation worker was found crossing the barricaded area and crane operator cleaning the diesel tank outside the cabin while the load was suspended. Also, trailer driver find was without PPEs like safety helmet and gloves.DEL YardDEL YardStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ActPPEAt DEL yard, during crane operation worker was found crossing the barricaded area and crane operator cleaning the diesel tank outside the cabin while the load was suspended. Also, trailer driver find was without PPEs like safety helmet and gloves.DEL YardDEL YardStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ConditionHousekeeping  Near Crude pump pit, poor housekeeping was observed in the area after the maintenance activity.Crude pumpCrude Pump PitStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ConditionWork at HeightAt below area of 205-F, near main stack, near furnace area & at 123-C platform, scaffolding materials were found on walkway without barrication. Informed to Civil department.Plant AreaBelow Area of 205-F,CivilCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ConditionWork at HeightAt furnace area, scaffolding material trolley was found parked without wheel chowks. Informed to safety supervisor.Plant AreaFurnace AreaCivilCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ActWork at HeightAt heat exchanger area, during erection of scaffolding M/s DEL scaffolders were not using tool tether. Counseling donePlant AreaHeat Exchanger AreaCivilCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ConditionProcedureAt 123-C platform & below area of 101-B furnace, leftover materials (welding blankets, stud bolts, spool pieces, lifting belt, tool trays etc.) need to be removed from platform.Plant Area123-C PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-31
2025-08-30Unsafe ConditionLack of SupervisionAt road #10 and near heat exchanger area, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Plant AreaNear Heat ExchangerStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-30Unsafe ActWork at HeightAt 185C, during fit-up activities, an untagged scaffolding platform was being used by DEL team.Plant AreaAt 185CStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-09-01
2025-08-29Unsafe ActProcedureAt 185C, two Descon workers were observed crossing the barricaded area during lifting operations.Plant AreaAt 185CStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ActWork at HeightAt 106-J and 105-JA, scaffolding dismantling was in progress while the rotary team was simultaneously working below in the same area.Plant AreaAt 106-J and 105-JAStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ConditionWork at HeightAt multiple locations loose material were found on scaffolding/ permanent platform that needs to be removed. (Open)Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-31
2025-08-29Unsafe ActFalling ObjectAt Boiler # 2, grinder spatters were observed falling onto the gas cutter cylinder's lead and a polythene bag.Plant AreaBoiler # 2StationaryPRLShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ActPPEAt boiler # 2, WMS worker found handling shar edge metallic piece without wearing safety gloves.Plant Areaboiler # 2StationaryPRLShutdownKorangi RefineryteamClosed2025-08-01
2025-08-29Unsafe ConditionLack of SupervisionAt road #10, near AFCs, at 123C platform and near heat exchanger area, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor. (Open) RepetitivePlant Area123C PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-29
2025-08-29Unsafe ConditionProcedureAt AFC 105-Cs, leftover materials (pressure gauges, stud bolts, etc.) need to be removed from platform.Plant AreaAFC 105-CsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ConditionProcedureAt AFC 105-Cs, leftover materials (pressure gauges, stud bolts, etc.) need to be removed from platform.Plant AreaAFC 105-CsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ConditionWork at HeightAt below area of 102-E & near Texas tower, scaffolding materials were found on walkway without barrication Informed to Civil department.Plant AreaBelow Area of 102-ECivilPRLShutdownKorangi RefineryteamClosed2025-08-30
2025-08-29Unsafe ConditionWork at HeightAt 123-C platform, scaffolding materials were observed on walkway, need to be removed.Plant Area123-C PlatformCivilPRLShutdownKorangi RefineryteamClosed2025-08-30
2025-08-28Unsafe ConditionProcedureAt 101-B, a piece of wood wedge fell from platform in the barricaded area.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-29
2025-08-28Unsafe ConditionSlip/Trip/FallAt ISOM near desalter drain pit grating found expanded and shuffle from its surface which is posing a tripping hazard.Plant AreaNear DesalterStationaryPRLShutdownKorangi RefineryteamClosed2025-08-29
2025-08-28Unsafe ActProcedureAt furnace area, crane was moving while its out rigger fully extended.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-29
2025-08-28Unsafe ConditionFalling ObjectAt furnace platform, loose material (wire brush) was found on edge posing a falling object.Plant AreaAt Furnace Platform,StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-29
2025-08-27Unsafe ConditionProcedureAt heat exchanger area. Unattended pressurized gas cylinder was found on walkway. Counseling done.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionProcedureAt multiple locations (below area of AFC, heat exchanger and pump gallery) loose materials (pipes, nut/ bolts, spool pieces, exchanger head, gasket, valves) were observed on the walkway without barrication.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActProcedureAt 105-Cs platform, stud bolts were found on walkway. Needs to be removed.Plant Area105-Cs PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActProcedureAt AFC 105-Cs, an unsafe act was observed where a fitter from M/s DEL was walking on the fin tube, which may result in tube deformation. Counseling of fitter was done at site and informed to Mr. Fahad Alvi.Plant AreaAFC 105-CsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActWork at HeightAt below area of AFC, unorganized scaffolding materials were observed, which could potentially fall into the drain channel. Informed to Civil department.Plant AreaBelow Area of AFCCivilPRLShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionWork at HeightAt 123-C platform, scaffolding materials were observed on walkway, need to be removed.Plant AreaAt 123-C PlatformCivilPRLShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionElectricalAt 123-C platform, electrical cable tray was found detached and posing falling hazard. Needs to be fixed.Plant AreaAt 123-C PlatformCivilPRLShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionProcedureAt multiple locations, oil-soaked cotton rags were found left on-site and on pipelines after maintenance activities. This poses a potential fire hazard during start-up operations.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionHousekeepingAt 105-C, poor housekeeping was observed on the platform.Plant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionHousekeepingAt 201-C, M/s AG's air compressor was found without wheel stoppers, and the area was not barricaded. The team was counseled.Plant AreaAt 201-CStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionProcedureAt furnace area, an expired 6 kg DCP fire extinguisher was found in a rusty and inadequate condition. Immediately it was removed from site.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActPPEAt 125-J, a forklift was observed lifting an exchanger flange using the fork edges, causing it to slip and nearly fall. The activity was stopped immediately and the operator was counseled.Plant AreaAt 125-JStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ConditionProcedureAt 101-B, the area was found not barricaded during a lifting operation. The team was counseled.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActHousekeepingAt 101-B, two paint buckets were found placed near ongoing hot work activity. The buckets were immediately removed from the site.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-27Unsafe ActPPEAt 101-B, M/s DEL’s welding lead was observed climbing the monkey ladder without wearing chin strap and safety gloves. Counseling done.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-26Unsafe ConditionProcedureAt multiple locations (below area of AFC, heat exchanger and crude pump) loose materials (pipes, nut/ bolts, spool pieces, exchanger head, gasket, valves) were observed on the walkway without barrication.Plant AreaAt Multiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionLack of SupervisionAt road #10, mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Plant AreaAt Road #10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionProcedureAt crude pump area, metallic ramp was observed on the walkway without barrication.Crude Pump AreaCrude Pump AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-26Unsafe ConditionProcedureAt crude pump area, metallic ramp was observed on the walkway without barrication.Crude Pump AreaCrude Pump AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-28
2025-08-26Unsafe ConditionProcedureAt heat exchanger area, M/s DEL’s compressor was observed parked without wheel chowk.Crude Pump AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionLack of SupervisionAt crude pump area, during hot work combustible material (tarpaulin) was observed within 7-meter radius of the activity. Informed to M/s DEL’s HSE supervisor.Crude Pump AreaCrude Pump AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionWork at HeightAt different locations of heat exchanger and crude pump area, leftover scaffolding materials were observed, need to be removed.Plant AreaDifferent LocationsCivilCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionHousekeepingAt 101-B, poor housekeeping was observed.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ConditionPPEAt 105-C2, UE worker was found wearing safety goggles while performing the paint job. Counseled the worker.Plant Area105-C2StationaryCONTRACTORUEShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ActVehicleAt Road # 10, a DEL truck (Mazda) was observed moving without a flagman. Counseled the driverRoad # 10Road # 10StationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-27
2025-08-26Unsafe ActEquipmentAt 101-B, a worker was found using a grinder with folded sleeves. Counseled the workerRoad # 10At 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-26Unsafe ConditionElectricalAt the 101-B platform, electrical board cabling was found laid across the walkway, posing a tripping hazard. Informed the supervisorPlant AreaAt 101-B PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-26Unsafe ConditionFalling ObjectAt the 101-B platform, a loose metal piece was found placed in a way that posed a falling object hazard. Informed the supervisorPlant AreaAt 101-B platformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionFalling ObjectAt different locations of pump gallery, leftover scaffolding materials were observed, need to be removed.Plant AreaDifferent LocationsCivilPRLShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionLack of SupervisionAt Desalter area, gas cylinder trolley was found on walkway, informed to M/s HSE supervisor.Plant AreaAt Desalter AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionProcedureAt 123-C Platform, leftover materials need to be removed.Plant AreaAt 123-C PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-08-26
2025-08-25Unsafe ConditionProcedureAt multiple locations (below area of AFC, utility, heat exchanger and pump gallery area) loose materials (pipes, nut/ bolts, spool pieces, exchanger head, gasket, valves ) were observed on the walkway without barrication.Plant AreaAt Multiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionLack of SupervisionAt multiple locations (furnace area, road 5, road 10, 123-C platform, heat exchanger area) mixed waste (hazardous and non- hazardous) were found, informed to M/s HSE supervisor.Plant AreaAt Multiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionSlip/Trip/FallAt the plant center, the steam pipe layout was found to be unorganized, causing a tripping hazard. (Closed)Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionSlip/Trip/FallAt the plant center, the steam pipe layout was found to be unorganized, causing a tripping hazard. (Closed)Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionPPEAt the Hydrogen/Nitrogen area, two workers from Pakistan Oxygen were performing a job without PPEs. The issue was reported to CR, and the workers immediately wore PPEs.Plant AreaAt Hydrogen/Nitrogen AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionHousekeepingAt 105-Cs platform, a Flame proof light found placed on the walkway.Plant AreaAt 105-Cs PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionHousekeepingAt 105-Cs platform, a Flame proof light found placed on the walkway.Plant AreaAt 105-Cs PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionHousekeepingNear Texas tower During Crane Operation the drain was not covered.Plant AreaAt 105-Cs PlatformStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ActFalling ObjectAt 105-Cs, it was observed that a tray was full of nuts posing a falling object hazard.Plant AreaAt 105-CsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionLack of SupervisionInside 101-B confined space, the compressor had been shut down, but a DESCON worker was still working inside. The supervisor was informed, and the worker was counseled.Plant AreaInside 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionLack of SupervisionInside 101-B confined space, the compressor had been shut down, but a DESCON worker was still working inside. The supervisor was informed, and the worker was counseled.Plant AreaInside 101-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ActProcedureWhile the Steam flashing at Boiler area, workers found inside the barricaded area. The worker was counseled.Plant AreaAt Boiler AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionEnvironmentAt plant area, all dustbins found full of garbage need to be removed from the area.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ConditionLack of SupervisionAt 704-C ISOM area, during hydro jetting work, one side of the hydro jetting canopy was not properly covered. The issue was reported to the Descon supervisor, and the area was immediately covered.Plant AreaAt 704-C ISOM AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-26
2025-08-25Unsafe ActPPEAt 101B, during civil refractory work inside the furnace (confined space), three workers were not wearing face masks. The issue was reported to the Descon SBM, and the workers were counseled. (Closed)Plant AreaAt 101BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ActPPEAt 101B, during civil refractory work inside the furnace (confined space), three workers were not wearing face masks. The issue was reported to the Descon SBM, and the workers were counseled.Plant AreaAt 101BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ActLine of FireAt 101B (outside), during painting work with a cherry picker, one Descon worker was in the line of fire. The supervisor was informed, and the worker was counseled.Plant AreaAt 101BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ActLine of FireAt 101B (outside), during painting work with a cherry picker, one Descon worker was in the line of fire. The supervisor was informed, and the worker was counseled.Plant AreaAt 101BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ActPPEAt 152-F during the main hole opening, one Descon fitter was performing the job without safety gloves. The supervisor was informed, and the worker was counseled.Plant AreaAt 152-FStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ConditionHousekeepingAt multiple locations (furnace area, road 5, heat exchanger area) mixed waste (hazardous and non- hazardous) was found, informed to M/s HSE supervisor.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-25Unsafe ConditionProcedureSince the start of the shutdown, the HSE lead for the night shift of M/s DEL has not reported.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-24Unsafe ActWork at HeightAt 2201-F, during work at height, DEL team was not using the tool tie.Plant AreaAt 2201-FStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2026-07-09
2025-08-24Unsafe ActPPEAt 105-C2, UE workers were observed performing job without wearing safety goggles.Plant AreaAt 105-C2StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-25
2025-08-24Unsafe ConditionSlip/Trip/FallAt 105-C7, material placed on platform posing a tripping hazard.Plant AreaAt 105-C7StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-26
2025-08-24Unsafe ConditionWork at HeightAt boiler & 3, during work at height, the area was not barricade.Plant AreaAt boiler 2 & 3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-25
2025-08-24Unsafe ActWork at HeightIn the furnace area, a scaffolder was observed lifting three (03) scaffolding pipes simultaneously.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-25
2025-08-24Unsafe ConditionHousekeepingAt 101-E, 102-C, exchanger head cover was placed without area barricade.Plant AreaAt 101-E, 102-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-25
2025-08-22Unsafe ConditionProcedureAt 118-C, during crane operation, area was not barricaded.Plant AreaAt 118-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionWork at HeightAt different locations in the process and utility area loose scaffolding pipes and planks were observed on the walkway without barrication.Plant AreaDifferent LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionElectricalAt the reactor area, a compressor was found in use without earthing. The operator was counseled on site and instructed to ensure earthing before operating the compressor.Plant AreaAt Reactor AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActEquipmentAt utility area, during hot job an energized grinder was observed on the floor. Counseling done.Plant AreaAt Utility AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-23Unsafe ActLine of FireAt the Utility and Pump Gallery, sparks were observed coming out of the welding canopy. The working team was immediately instructed to cover the area.Plant AreaAt Utility and Pump GalleryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-24
2025-08-23Unsafe ActWork at HeightAt 304-C, while working at height M/s DEL TE was found scaffolding platform without wearing safety harness. Counseling donePlant AreaAt 304-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-24
2025-08-23Unsafe ActWork at HeightAt 301-F while working at height, M/s DEL worker was using spanner without tie his tool with tool tether.Plant AreaAt 301-FStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-24
2025-08-23Unsafe ConditionProcedureAt multiple locations (below area of AFC, utility, heat exchanger and pump gallery area) loose materials (pipes, nut/ bolts, exchanger head, gasket, valves ) were observed on the walkway without barrication.Plant AreaAt Multiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-24
2025-08-23Unsafe ConditionProcedureA hot job was carried out in the Utility and Pump Gallery, but no fire watcher from M/s DEL were available.Plant AreaUtility and Pump GalleryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-24
2025-08-22Unsafe ConditionPPEAt 109-J, hot work activity started without fire watcher and taking precautions. Immediately stopped and instructed to take control measures.Plant AreaAt 109-JStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt 105-C, a DEL worker was found without chin guard at height.Plant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActPPEAt 106-C7, WMS workers were performing electrical related jobs without wearing safety gloves.Plant AreaAt 106-C7StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt 301-CN, DEL worker using the hammer without tied with the tool teether while working at height.Plant AreaAt 301-CNStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightNear the fitter room, scaffolding erection activity was in progress without the area being barricaded, and workers were drinking water from the cooler at the same location.Plant AreaNear the Fitter RoomStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionHousekeepingAt cooling tower, 105-C7 and humidifier, poor housekeeping was observed.Plant AreaAt Cooling TowerStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureAt humidifier, 105-C5 platform, 301-B, 311-B, and 302-B, miscellaneous materials were observed without barricaded.Plant AreaDifferent LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt 103-B, it was observed that a DEL worker stepped onto a ladder to access the scaffolding platform without wearing a safety harness. He was immediately stopped and reminded to wear safety harness.Plant AreaAt 103-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureIn utility area near 2403-J, drain channel grating was found missing and area not barricaded.Plant AreaUtility Area Near 2403-JStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActElectricalAt heat exchanger area, M/s DEL QC person was observed using non-intrinsically battery-operated flashlight without permit and electrical inspection tag. Counseling done.Plant AreaAt Heat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-23
2025-08-22Unsafe ActPPEStationary Dept‘s AP and multiple R.E workers were observed wearing black goggles at night. Counseling done.Plant AreaStationary Dept‘sStationaryCONTRACTORREShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureAt pump corridor and in front of 104-C spool pipes was observed on the floor without barrication.Plant AreaAt Pump CorridorStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionWork at HeightAt pump corridor area, a bag filled with rags was observed placed in front of the monkey ladder blocking the access. Removed later.Plant AreaPump CorridorStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActLack of SupervisionAt 123C And 124C leftover material was found. Informed to M/s DEL’s safety supervisor.Plant AreaAt 123C And 124CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActHousekeepingAt JP-1 gantry, during dinner time, M/s DEL workers were observed lying on the road. Counseling done.Plant AreaAt JP-1 gantryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt pump corridor area M/s AKS worker was observed working on the scaffolding without equipping his tool with tool tie. Counseling done.Plant AreaPump Corridor AreaCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2026-07-09Unsafe ConditionEnvironmentAt intersection of road 3 and 10, a tray loaded with oily rocks and sludge filled bags (pyrophoric material suspected) were observed, informed to Mr. Arsalan for removal.Plant AreaAt Intersection of Road 3 and 10CivilPRLShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureM/s DEL rigger in-charge was found wearing an unapproved coverall at plant side.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureNear control room loose material (flanges) was observed on the floor without barrication.Plant AreaNear control RoomStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActProcedureMultiple M/s DEL’s workers were observed in the plant area wearing unapproved coveralls having metallic buttons. Instructed to wear the approved coverall.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-22Unsafe ConditionVehicleAt roads #07 near boiler #04 a crane was observed parked with elevated boom, Informed the HSE supervisor of M/s DEL.Plant AreaRoads #07 Near Boiler #04StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionWork at HeightAt 123C And 124C, loose scaffolding materials were found on the platform.Plant AreaAt 123C And 124CCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2026-07-09Unsafe ConditionLack of SupervisionThe reverse alarm and spark arrestor of the DEL ambulance were missing, and a paramedic staff member was also absent todayPlant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionSlip/Trip/FallAt 303-CN, the hose pipe of the hydro jetting machine was laid on the floor in an unorganized manner, posing a tripping hazard.Plant AreaAt 303-CNStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActProcedureAt 105-C, during lifting operation WMS team working inside the barricaded area.Plant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActPPE  At 301-J, M/s DEL workers using sandpaper without wearing safety gloves.Plant Area  At 301-JStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureAt 109-J, M/s DEL contractor's fire extinguisher found rusty from the bottom.Plant AreaAt 109-JStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt 202-C, M/s DEL worker was found using a spanner at height, with the tool tied to a tool tether.Plant AreaAt 202-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureAt multiple locations like 101-B, 103-B & 104-F misc. material was observed in the area without barricade.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionHousekeepingAt multiple locations like near CR, 108-C, 202-C1, 106-C, 203-JA, 302-C2 & trim cooler poor housekeeping was observed.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-21Unsafe ConditionWork at Height  At 113-C, poor housekeeping was observed on the scaffolding platform.Plant AreaAt 113-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-21Unsafe ActWork at HeightIn the pump corridor, a long scaffolding pipe was being handled by a single DEL worker.Plant AreaPump CorridorStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActWork at HeightAt 105-C, a DEL worker was found on the scaffolding platform without wearing a safety harness.Plant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionLine of FireAt 105-JA, during hot work activity, sparks were coming out from the fire blanket canopy. Instructed to properly cover the area.Plant AreaAt 105-JAStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionProcedureAt Air Coolers 105-C, water from the cleaning activity was dropping without proper area barricading. Immediate intervention was carried out, and corrective actions were taken.Plant AreaAt Air Coolers 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionProcedureAt multiple locations (Heat exchanger area, near Stationary caravan, pump corridor area and AFC), loose material (nut/bolts, exchanger covers) was found without barrication .Plant AreaAt Multiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActWork at HeightAt pump corridor area, M/s DEL workers were found using scaffolding having expired inspection tag. Informed the site supervisor.Plant AreaPump Corridor AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionProcedureDuring the night shift, when hydro jetting and furnace activities commenced, no HSE representative from M/s DEL was present at the site. Several DEL members were instructed to immediately call their HSE team to the site; however, DEL’s HSE representatives arrived after approximately one hour.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActProcedureAt WWTP, a compressor was observed being used without attaching its hose pipe with a whip latch. Instructed the operator to attach the hose pipe with a whip latch.Plant AreaAt WWTPRotaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionWork at HeightLoose scaffolding material was found without barrication at air fan cooler area and Heat exchanger area.Plant AreaAir Fan Cooler AreaCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActWork at HeightAt 103-B, during a hot work activity, sparks were observed coming out from the fire blanket canopy. Additionally, the worker was not wearing required PPE such as a chin guard, ear plugs, and had not fastened his safety harness while working at height.Plant Area103-BStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-22
2025-08-21Unsafe ConditionWork at HeightAt the hydro air coolers, a pulley was being used for a lifting activity, however it was installed at the edge of a single, open-ended scaffolding pipe, posing a risk of slippage. Additionally, poor housekeeping was observed on the platform.Plant AreaHydro Air Coolers AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-21Unsafe ActWork at HeightAt above area of 204-C, M/S DEL scaffolders were observed modifying the scaffolding on green tag instead of replacing it with a red tag. Informed to site supervisor.Plant AreaAt Above Area of 204-CCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActProcedureAt Road # 8, air pressurized hose pipe of air compressor detached from the coupling.Plant AreaAt Road # 8StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActLack of SupervisionAt 105-C, UE workers were performing a lifting operation without using a tool bag and pulley, which resulted in the rope being damaged at multiple points. Supervisor immediately changes the rope. RepetitivePlant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionProcedureIn front of 108-C, a fire extinguisher trolley was blocked due to the placement of lifting gears around it. Informed to lifting in charge.Plant AreaIn Front of 108-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ConditionSlip/Trip/FallAt 124-C, 202-C and 106-C3, loose material was found on the platform. Informed M/s UE supervisor.Plant AreaAt 124-C, 202-C and 106-C3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ConditionWork at HeightAt furnace area, scaffolding pipes and metal plank was found on walkway. Informed to Mr. Arsalan of Civil departmentPlant AreaFurnace AreaCivilPRLShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActWork at HeightAt furnace area, M/s DEL scaffolder was throwing scaffolding clamps. Counseling done.Plant AreaAt 103-BCivilCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ConditionHousekeepingAt furnace and at heat exchanger area, GI sheet was placed on floor without securing it. Informed to DEL HSE representative for securing.Plant AreaAt 103-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActPPEAt furnace area, while working in confined space, M/s DEL workers were wearing dust masks, Counseling of team done and instructed their supervisor to provide N-95 mask.Plant AreaAt 103-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActProcedureAt heat exchanger area, M/s DEL worker was found wearing unapproved coverall (metallic button and with DEL name). Informed to DEL HSE representative.Plant AreaAt 103-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActWork at HeightAt AFC, M/s DEL worker was found on scaffolding platform with hooking his harness hooks. Counseling done.Plant AreaAt 103-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ConditionPPEAt the caustic yard, leakage of caustic was observed from the housing of pump 101-JA. The stationary team applied a spade on the line, but leakage has not stopped. Control Room has been informed. (Open)Plant AreaAt the Caustic YardOperationPRLShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ConditionSlip/Trip/FallAt 106-C, a channel was placed on walkway posing a tripping hazard. (Closed)Plant AreaAt 106-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActElectricalAt 201-D, during hot work activity, earthing wire connection was found partially detached.Plant AreaAt 201-DStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ActWork at HeightAt cooling tower, M/s AKS team was performing the scaffolding erection activity without any safety supervision. Action taken by the civil team.Plant AreaAt 103-BCivilCONTRACTORAKSShutdownKorangi RefineryClosed2026-07-09
2026-07-09Unsafe ConditionWork at HeightAt 202 air cooler, loose material was observed on scaffolding platform. Counseled the teamPlant AreaAt 202 Air CoolerStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-20Unsafe ConditionWork at HeightAt 202 air cooler, loose material was observed on scaffolding platform. Counseled the teamPlant AreaAt 202 Air CoolerStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-21
2025-08-20Unsafe ActProcedureAt the plant center, an operations team member was found crossing a barricaded area while a crane operation was in progress. Counseled the staff.Plant AreaAt the Plant CenterOperationPRLShutdownKorangi RefineryClosed2025-08-21
2025-08-20Unsafe ConditionPPEAt 201-C5, hydrocarbon and water mixture were draining while the crane and Woma machine are being used in the vicinity. Immediately activity stopped and instructed to plan the activity. (Closed)Plant AreaAt 201-C5OperationPRLShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ActEnvironmentAt the pump corridor, the operations team was transferring a Perchloroethylene drum by rolling it on the floor. Counseled the team.Plant AreaAt the Pump CorridorOperationPRLShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ActProcedureAt 301-CN, operations team taking drain hose pipe upside with help of rope however on connection of hose pipe its metal coupling bolts were missing. Immediately action was taken by ops team and resolve the obs. (closed)Plant AreaAt 301-CNOperationPRLShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ConditionLine of FireAt 201-B, during hot work on steam line, sparks were coming out from the canopy. Instructed the supervisor to cover the area properly.Plant AreaAt 201-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ActProcedureAt 118-C, during hydro jetting activity area was not barricaded and a DEL worker was found with sleeves folded. Counseled the workerPlant AreaAt 118-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ConditionProcedureIn front of 101-C, a fire extinguisher trolley was blocked due to the placement of lifting gears around it. Informed to lifting in charge.Plant AreaInfront of 101-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-19Unsafe ConditionProcedureIn front of AFC and at heat exchanger area, wooden blocks and heat exchanger cover were found on walkway without barrication.Plant AreaInfront of AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ConditionProcedureAt plant center, bundle puller was slightly hit with steam line below the 107-F while lifting by the crane and the DEL workers were standing below the suspended load. Counseled the team.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-21
2025-08-20Unsafe ActProcedureAfter lunch at the site, the DEL HSE representative was not available. Later, their HSE lead instructed the team to be present at the site for supervision.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-21
2025-12-30Unsafe ConditionWork at HeightAt tank # 05, scaffolding platform inspection tag found expired. Informed to Nazam sb.Tank FarmTank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-01-01
2025-12-30Unsafe ConditionWork at HeightAt tank # 36, inside tank yard an iron hammer was being used to straight the scaffolding pipe very close to adjacent flanges. Informed to IIW HSE person & project manager.Tank FarmTank # 05ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-01
2025-12-30Unsafe ConditionPPEAt tank # 11, during tank inside mechanical work workers found with wearing face mask and safety goggle. Informed to HSE person ATL.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-01-01
2025-12-30Unsafe ConditionElectricalAt tank # 11, during tank inside mechanical work found using LED lights with expire Electrical inspection tag. Informed to HSE person ATL.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-01-01
2025-12-30Unsafe ConditionElectricalAt tank # 04, M/s Al Hadeed HSE person was not available at site during sludge removal activity.Tank FarmTank # 04ConstructionCONTRACTORAL-HADEEDRoutineKorangi RefineryteamClosed2026-01-01
2025-12-30Unsafe ConditionProcedureA M/s Kundi worker was observed passing directly below the flare stack instead of using the designated proper passage or roadsPlant AreaFlareConstructionCONTRACTORAL-HADEEDRoutineKorangi RefineryteamClosed2026-01-01
2026-01-01Unsafe ConditionProcedureAt tank yard # 4, workers were observed climbing on the boundary wall and carrying out demolition work in an unsafe manner.Tank FarmTank Yard # 4ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-03
2026-01-01Unsafe ConditionProcedureAt tank# 35, M/s IIW excavator being used at site was not fitted with a swing alarm.  Tank FarmTank 35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-03
2026-01-02Unsafe ConditionProcedureAt tank# 35, M/s IIW excavator being used at site was not fitted with a swing alarm.  Tank FarmTank #35ConstructionCONTRACTORPRLRoutineKorangi RefineryteamClosed2026-01-03
2026-01-02Unsafe ConditionProcedureAt tank yard # 4, workers were observed climbing on the boundary wall and carrying out demolition work in an unsafe manner.Tank FarmTank #04 YardConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-03
2025-08-18Unsafe ConditionProcedureThe same worker of M/s AG, who was found yesterday at Gate 3 without having undergone medical and safety orientation and was handed over to Mr. Shahzad of M/s WMS, was again found today near the fire camp. Upon investigation, it was revealed that his medical and safety orientation has still not been conducted. He has now been handed over to Mr. Fahad Alvi.Plant AreaAt Gate 3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-05Unsafe ConditionPPEAt tank 04 yard, during civil work 2 IIW workers not warring safety goggles, informed to site supervisor and consoling done.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-06
2025-08-18Unsafe ConditionSlip/Trip/FallIn front of heat exchanger area, water accumulation was observed on the floor, creating slip/trip hazard.Plant AreaInfront of Heat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ConditionLack of SupervisionAt 185-C near compressor of M/s DEL a fire extinguisher of PRL was found. Informed and instructed the safety supervisor to replace it with DEL’s Fire extinguisher. (Closed)Plant AreaAt 185-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActLack of SupervisionIn front of AFC, a Fire extinguisher of M/s DEL without monthly inspection tag was found. Informed to safety supervisor.Plant AreaIn Front of AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-01-07Unsafe ConditionProcedureWalkway is required for easily access the foam header at road # 1.  Tank FarmRoad # 1CivilPRLRoutineKorangi RefineryteamClosed2026-01-08
2025-08-18Unsafe ActElectricalAt DEL yard, M/s DEL safety team is using amplifier speaker set having expired PRL’s electrical inspection tag.Plant AreaDEL YardStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-07Unsafe ConditionProcedurePermanent Chain pole need to be installed as barrication over underground pipelines at road # 1 near VFD Crude Pump.  Tank FarmRoad # 1CivilPRLRoutineKorangi RefineryteamClosed2026-01-08
2025-08-19Unsafe ConditionEnvironmentAt the heat exchanger area, filter cartridge of hydro jetting machine was found on floor. Informed to hydro jetting supervisor for removal.Plant AreaAt the Heat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2026-01-07Unsafe ConditionEquipmentHandrail installed at walkway need to be fixed located at road no. 2 opposite foam skid generator.  Tank FarmRoad # 1CivilPRLRoutineKorangi RefineryteamClosed2026-01-08
2025-08-19Unsafe ConditionLack of SupervisionAt 105-C, UE workers were performing a lifting operation without using a tool bag and pulley, which resulted in the rope being damaged at multiple points. Supervisor immediately change the rope.Plant AreaAt 105-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-19Unsafe ConditionHousekeepingAt furnace area, load chain was found on walkway, needs to be removed from the site or placed in barricaded area.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-20
2025-08-18Unsafe ConditionProcedureAt 118-CN DEL fire extinguisher -14 DCP 6KG found substandard fire extinguisher seal.Plant AreaAt 118-CNStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-18Unsafe ActProcedureAt heigh Noice furnace area WMS worker found without ear protection.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-20
2026-01-07Unsafe ActLack of SupervisionAt tank#35,during excavation work use one dumper move on rood.16 without flagman.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-08
2025-08-18Unsafe ConditionWork at HeightAt cooling Tower 2305-JE loose material scaffolding clamps are placed on planks at height. Informed to supervisor.Plant AreaCooling Tower 2305-JEStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActWork at HeightAt exchanger area two DEL workers climbed monkey ladder together at same time Counseled the team.Plant AreaAt Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActPPEDEL supervisor was not using proper PPE’s (without safety goggles and short sleave coverall). Counseled the team.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-06-19
2026-01-07Unsafe ActProcedureAt tank# 11 ATL,W/S, during crane operation involved riggers 3rd party certification missing. Informed HSE in charge .Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-01-08
2025-08-18Unsafe ConditionWork at HeightAt near furnace area, scaffolding material trolley was found without wheel chowks.Plant AreaFurnace AreaCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-19Unsafe ConditionSlip/Trip/FallAt the heat exchanger area, the towing jack of the hydro jetting machine was placed right next to the access ladder of 123-C, creating a tripping hazard for personnel coming down from the ladder. Informed to hydro jetting supervisor.Plant AreaHeat Exchanger AreaStationaryCONTRACTORAGShutdownKorangi RefineryClosed2025-08-19
2026-01-07Unsafe ActLack of SupervisionAt tank#04,during confined space activities, not present HSE person ,informed site supervisors.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-08
2026-01-07Unsafe ActLack of SupervisionAt tank#04 ,during removing IFR materials not barricaded informed site supervisor and immediately barricading area.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-08
2026-01-07Unsafe ActProcedureAt tank#35, during excavation work, found full  diesel dram were present at tank yard. Informed to HSE in charge immediately remove diesel dram.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-09
2026-01-07Unsafe ActLack of SupervisionAt tank#35,during excavation work, found some materials not barricaded at work site. Informed to HSE supervisor IIW using materials barricaded immediately.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-09
2026-01-07Unsafe ActLack of SupervisionDuring excavation work at Tank #35, the excavator being used by M/s IIW was found without a PRL-approved spark arrester and was reported to the HSE In-Charge.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-09
2026-01-08Unsafe ActLack of SupervisionAt ATL yard, during safety round , 1st half ambulance driver and paramedic does not present at site. Informed to HSE lead.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-07-10
2026-01-08Unsafe ConditionProcedureDuring crane operations at the ATL yard, two riggers were observed working without valid third-party certification and the matter was reported to the HSE LeadTank FarmRoad # 1ConstructionPRLRoutineKorangi RefineryteamClosed2026-01-10
2026-01-08Unsafe ActPPEAt tank #04, during sludge pits backfilling 2 workers without safety gloves working, informed to site supervisor.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-10
2026-01-08Unsafe ConditionProcedureAt Tank #35, during a safety round, it was observed that grounding and earthing of the IIW containers were missing. The issue was reported to the HSE Lead.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-10
2026-01-08Unsafe ConditionProcedureAt tank #35, during safety round found the IIW ambulance shade and battery terminal safety cover missing ,informed to HSE lead.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-10
2025-08-18Unsafe ConditionEquipmentAt plant center, whip latch on hose pipe of hydro jetting machine was found missing.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-08Unsafe ConditionProcedureAt tank #35, dDuring the civil work in progress, a tractor without a reverse alarm was found, and the driver did not have a valid DDC. The issue was reported to the HSE Lead.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-10
2025-08-18Unsafe ActProcedureAt 105-C3, damage plank was being used for the movement on tubes.Plant AreaAt 105-C3CivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-09Unsafe ConditionWork at HeightAt tank # 62, reflective tape was missing on scaffolding installed along the roadside, posing a risk of vehicle colliding with the scaffolding (AKS).Tank FarmTank # 62CivilCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2025-08-18Unsafe ActWork at HeightAt 101-B, DEL worker was coming down from the monkey ladder without following the three-contact point.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ConditionEquipmentAt Road # 8, fire extinguisher seal on the hydro jetting machine was found missing.Plant AreaAt Road # 8StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-09Unsafe ConditionWork at HeightAt tank # 62, the expiry date on inspection tag of scaffolding was not available.Tank FarmTank # 62CivilCONTRACTORAKSRoutineKorangi RefineryteamClosed2026-01-11
2025-08-18Unsafe ActProcedureAt plant center, M/s DEL fork lifter was found wearing unapproved low ankle shoes.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-09Unsafe ConditionProcedureAt tank # 56, paramedic was not present on site. Informed to HSE lead AJC.Tank FarmTank # 62StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2025-08-18Unsafe ConditionEquipmentThe emission testing reports of the compressor and generators, as well as the fitness certificate of the gas cylinder, were not shared by the DEL teamPlant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-09Unsafe ActEquipmentAt tank # 56, the operator was not present on the running 200 KV generator. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKorangi RefineryteamClosed2026-01-11
2025-08-18Unsafe ConditionLack of SupervisionAt 107-C Parallel Scafolding Activity Perform by DESCON, Informed To S. Folding Supervisor And Counseling.Plant AreaAt 107-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActWork at HeightAt 108-C Where Worker Of DESCON Work on Height There Safety Harness Hook Was Hook At Same Folding Pipe. Counselling the worker .Plant AreaAt 108-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-12Unsafe ActLine of FireAt tank # 56, three workers were observed in the vicinity of hot work and grinding activity and exposed to sparks. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2025-08-18Unsafe ConditionPPEAt Plant Center Observe  DESCON Generator Stand Without Wheel Stopper. Informed To Generator Operator.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-12Unsafe ConditionProcedureAt tank # 56, fire extinguisher was present on site, but the monthly and yearly inspection tags were not attached. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2025-08-18Unsafe ActPPEAt Plant Center While Crane operation Was Perform, A crane Operator Observe Not Wear Safety Shoes Properly And Without goggle. Counselling the Worker.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-12Unsafe ConditionSlip/Trip/FallAt tank # 56, D door plate was lying in front of the main entrance ,creating a tripping hazard. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-15
2025-08-18Unsafe ActProcedureAt Plant Center Flag Man Not Found When Crane On Reverse .Plant AreaAt Plant CenterCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActProcedureIn front of heat exchanger area, the rest shed was being in use by M/S DEL without green tag. Informed to Mr. Arsalan of Civil department.Plant AreaHeat Exchanger AreaCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ConditionWork at HeightIn front of 108C loose scaffolding material was observed on the floor without barrication. Informed to safety supervisor.Plant AreaAt 108-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-12Unsafe ConditionSlip/Trip/FallAt tank # 56, cables were laying at the main entrance, posing a potential of tripping hazard. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-15
2026-01-12Unsafe ConditionWork at HeightAt tank# 56, contractor two welders were working at height (above 6 ft) without wearing safety harness, Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-15
2025-08-18Unsafe ConditionPPEAt DEL yard, the ambulance of M/s DEL was found locked and the driver and the key were not present, upon calling the driver it was found that he had no valid DDC and had not undergone safety induction/ medical examination. The ambulance was not equipped with approved medicines/ first aid kit, no fire extinguisher was found inside.Plant AreaDEL YardStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-01-12Unsafe ConditionProcedureAt tank # 56, M/s AJC contractor and stationary HSE representative were not present at site during the job, Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-15
2025-08-18Unsafe ActPPEA truck carrying the food for M/S DEL was observed crossing gate #03 upon inspection it was found that the driver had no valid DDC, had not undergone safety induction/ medical examination. The truck was not equipped with a fire extinguisher and the battery terminals were found missing rubber boots. (Closed)Plant AreaGate# 3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-18Unsafe ConditionSlip/Trip/FallIn front of furnace area, metallic plates were observed on the walkway without barrication,  creating tripping hazards.  Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-16Unsafe ConditionHousekeepingThe housekeeping at the construction site requires immediate attention. Used gloves, cartons, wrapping sheets, wooden bars, and other debris are scattered around the site.Tank FarmConstruction SiteStationaryCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2025-08-18Unsafe ConditionProcedureIn front of AFC and at heat exchanger area, wooden blocks and heat exchanger cover were found on walkway without barrication.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ConditionProcedureIn front of AFC, a compressor was observed in use without its battery terminal covered with rubber cover.Plant AreaIn Front of AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-16Unsafe ConditionHousekeepingA worker from M/s Afzal Construction was observed standing/ working on wooden planks placed over a drum.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionHousekeepingThe fire extinguisher placed at the side was found be low on pressure, its safety seal was removed and there was no evidence of refilling or a valid expiry tag.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionHousekeepingMultiple cans filled with lubricants/ chemicals were found placed directly on raw land instead of being stored in secondary containment.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionHousekeepingThe generator battery terminals were found without rubber protective boots.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionElectricalA wooden electrical extension board is being used on site without a weather protection cover and without inspection by the Electrical Department.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionElectricalGrinders was being placed directly on the floor as there are no proper grinder stands available.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionElectricalIt was observed that workers of M/s Afzal Construction were using electrical equipment such as grinders, electrical extension boards, welding rectifier,  drill machines, generators, etc., that either do not have electrical inspection tags or have expired tags.Tank FarmConstruction SiteConstructionCONTRACTORAfzalRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionElectricalTank #11: Electrical extension board found without inspection tag during safety round; informed HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionLine of FireTank #35: Vehicle No. JY-9404 arrived with non-functional reverse alarm and improper spark arrester; informed site supervisor.Tank FarmTank #35ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ConditionPPETank #35: IIW workers were found without wearing dust masks during civil work; informed HSE supervisor and masks provided immediately.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-18
2026-01-16Unsafe ActLack of SupervisionTank #35: Worker observed not maintaining safe distance during stone breaking; informed IIW HSE supervisor and counseling done.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-18
2026-01-17Unsafe ConditionHousekeepingAt Tank #56, during crane operation lifting an 1800 kg MS plate, a 3-ton sling Wair  was found damaged and was immediately replaced after informing HSE Supervisor AJC.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionLack of SupervisionAt Tank #56, during hot work, a filled diesel jerry can was found in the work area; informed HSE Supervisor AJC.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionLack of SupervisionAt Tank #56, during hot work, an electrical cable was found lying on a wet surface at the workplace; informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionElectricalAt Tank #56, during hot work, the main electrical cable was found damaged; informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionLine of FireAt Tank #56, during the safety round, the ambulance spark arrestor was found unsuitable and not approved by PRL and was immediately replaced after informing HSE Supervisor.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionProcedureAt Tank #56, during hot work, a fire extinguisher was found missing; informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionHousekeepingAt Tank #56, during the safety round, a worker’s safety shoes were found damaged and were immediately replaced after informing HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionElectricalAt Tank #56, during hot work, a 5" grinder electrical inspection tag was found damaged: informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionElectricalAt Tank #56, during hot work, a damaged electrical extension board was found in use; informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ConditionElectricalAt Tank #56, during the safety round, workers were observed without safety goggles; informed HSE Supervisor AJC .Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-17Unsafe ActSlip/Trip/FallAt Tank #56, during hot work, a temporary ladder was used without proper fixing, creating a fall hazard; informed HSE Supervisor AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-22
2026-01-18Unsafe ConditionEquipmentAt tank # 35, generator shade not installed at office area.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKemari TerminalteamClosed2026-01-22
2026-01-22Unsafe ActPPEAt tank #56, M/s AJC worker working with binding wire without safety glovesKTTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-06-25
2026-01-18Unsafe ConditionEquipmentAt tank # 35, generator shade not installed at office area.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-22
2026-01-22Unsafe ActWork at HeightAt tank # 11, loose material was found on scaffolding platform during hot work.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-28
2026-01-23Unsafe ActElectricalAt tank #56, M/s AJC DB (WP-01) was found without inspection tag. The DB was switch off and arrange an inspection tag and restore the operation.KTTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-26
2026-01-25Unsafe ActLack of SupervisionAt tank # 11, during hot work activities, the platform gap was not covered. Informed to the HSE Supervisor.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-28
2026-01-25Unsafe ActPPEAt tank # 11, during sandblasting, nearby some workers were found not wearing a face mask. Informed to the HSE Supervisor.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-28
2025-08-17Unsafe ActPPEAt plant center, DEL workers found without wearing gloves while handling the scaffolding materials. Counseled the team.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ActProcedureAt road # 3, crane operator and his helper were found wearing low ankle shoes.Plant AreaAt Road # 3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-07-10Unsafe ActPPE02 nos. DEL worker found at plant side without having safety induction stickers on their helmets. Counseled the team.Plant AreaPlant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionProcedureRoads # 3 and 6 were blocked due to crane parked on it. Counseled the team.Plant AreaRoads # 3 and 6StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionLack of SupervisionAt multiple locations. Low pressure and without monthly inspection tag Fire extinguisher of M/s DEL were found. Informed to safety supervisorPlant AreaMultiple Locations.StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionHousekeepingNear 108-C empty WD-40 cans & oily rags were found on floor. Informed to DEL supervisor for housekeeping.Plant AreaNear 108-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-01-17Unsafe ConditionLine of FireAt tank #56, A 200 KVA generator spark arrestor found installed with unapproved spark arrestor Informing HSE supervisor.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-30
2025-08-17Unsafe ConditionElectricalLow lighting was observed at 202-C1 & C2. Later electrical department provides light on the locations.Plant AreaAt 202-C1 & C2StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionHousekeepingAt 123-C & 124-C, loose materials were observed. Informed to DEL supervisor for housekeeping.Plant AreaAt 123-C & 124-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ActPPEAt 123-C & 124-C, 2 nos of M/s DEL workers were observed without wearing helmet chin strap. Counseling done.Plant AreaAt 123-C & 124-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ActSlip/Trip/FallAt AFC, 4 nos of M/s DEL riggers were found at scaffolding platform without wearing safety harness. Counseling done.Plant AreaAt AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-10
2025-08-17Unsafe ConditionProcedureAt near AFC, wooden blocks and heat exchanger cover were found on walkway without barrication.Plant AreaAt Near AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionWork at HeightAt heat exchanger area, scaffolding materials were found on walkway without barrication.Plant AreaHeat Exchanger AreaCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionLack of SupervisionAt heat exchanger area, pressurized hose was found without whip latch. Informed to safety supervisor.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ActLack of SupervisionNear furnace area, due to unavailability of rest shed, M/s DEL workers were found sitting on floor. Informed to safety supervisor.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionWork at HeightNear pump gallery, scaffolding loaded trolley was found without wheel chowk. ClosedPlant AreaNear Pump GalleryCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-06-19Unsafe ActWork at HeightAt Tank #04, M/S IIW worker was found working on the top platform without hooking his safety harness.Tank FarmAt Tank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2025-08-17Unsafe ActProcedureAt Gate 3, one worker of M/s AG was found wearing a metallic button coverall, and his medical and safety orientation had not been conducted. He was handed over to Mr. Shahzad of M/s WMS for medical and safety orientation.Plant AreaGate 3,StationaryCONTRACTORAGShutdownKorangi RefineryClosed2025-08-18
2025-08-18Unsafe ActElectricalAt PC 314 LPG line hot job, electric cold cutter and grinder found without electrical inspection tag.Plant AreaAt PC 314 LPGStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2026-01-22Unsafe ActProcedureAt tank #56, During crane operation AJC welder and worker movement in under crane boom barrication area.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-30
2026-01-22Unsafe ActWork at HeightAt tank #56, Safety harness SH-5 lan-yard hook was damaged and being used on height.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-30
2026-01-28Unsafe ConditionProcedureTank # 56: During lux monitoring, inadequate lighting was observed at several locations, resulting in poor visibility.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-30
2026-01-28Unsafe ConditionProcedureTank #11: During sand blasting activity, workers were exposed to high noise levels without using hearing protection (ear plugs). ATLTank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-30
2026-01-28Unsafe ConditionWork at HeightTank # 04: Sharp edges were observed on scaffolding pipes during cutting activity, posing cut hazards. IIWTank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-01-28Unsafe ConditionProcedureTank # 04: Workers’ rest shelter was not provided at the work site. IIWTank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-01-28Unsafe ConditionProcedureTank # 35: Authorized compactor operator (DDC/ 3rd party certificate) was not available during compaction activity. IIWTank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-01-28Unsafe ConditionEquipmentTank # 35: Generator shelter/shade was not installed, exposing equipment to environmental conditions. IIWTank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-01-30Unsafe ConditionProcedureAt Boiler No. 4, a painter from M/s UE was working inside a confined space while the SBM was present at another location. When the SBM was called, it was observed that, according to his checklist, the entry for the person working inside had already been recorded as “out”.Plant AreaBoiler No. 4CivilPRLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionHousekeepingTank # 11: Poor housekeeping observed around tank yard, with debris (such as feathers) scattered in the area. Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionElectricalTank # 11: The weather protection cover for the Electrical DB is faulty and needs replaced.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionElectricalTank # 11: Battery terminal boot of air compressor was not properly fixed.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionEnvironmentTank # 11: Oil leakage was observed from the breathing air compressor.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionElectricalTank # 11: The scaffolding structure used for placing welding rectifiers was found without proper earthing and the scaffolding tag was also missing.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionFalling ObjectTank # 04: Iron rods extracted from the demolished dyke wall have been kept on the ground and need to be removed.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionWork at HeightTank # 04: Scaffolding pipes were placed in the walking way, need to be removed.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionSlip/Trip/FallTank # 04: The D-door was kept inside the working area, which could cause a tripping hazard and needs to be removed.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionSlip/Trip/FallTank #11: It was observed that the air compressor in use had a punctured tire.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionPPETank #04: It was observed that M/s IIW workers coveralls were dirty and without proper reflective strips.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-30Unsafe ConditionProcedureTank #35: The scaffolding structure for the 25 kVA generator was found without a valid inspection tag.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-05
2026-01-29Unsafe ConditionProcedureTank #56: It was observed that during late-hour activities, the paramedic of M/s AJC was usually not available at the site.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2025-08-16Unsafe ActPPEAt rood 07, one of the M/s WMS worker was working on the LPG pipeline without wearing safety gloves, informed to supervisor to ensure no task on LPG pipeline is carried out without complete PPE.Plant AreaAt road #07StationaryCONTRACTORWMSShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ActLack of SupervisionAt 105- C3,two fitters of M/s UE were performing light lifting work in an area that was not barricaded, informed supervisor and instructed to Area fully barricaded and secured.Plant AreaAt 105- C3StationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-16
2025-08-16Unsafe ActPPEAt cooling tower, two workers were lifting a GI sheet without wearing safety gloves, informed to supervisor.Plant AreaAt Cooling TowerCivilCONTRACTORWMSShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ActElectricalAt below area of reactor, PRL lab staff was found using battery operated equipment (digital stopwatch) without tagging it from electrical department.Plant AreaAt Below Area of ReactorLabPRLShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ConditionWork at HeightAt road 10, scaffolding material loaded trolley was found parked with wheel chowks. Counseling done.Plant AreaAt Road# 10CivilCONTRACTORAKSShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ActProcedureAt road 10, M/s AKS workers were found wearing coverall having no reflective tape.Plant AreaAt Road# 10StationaryCONTRACTORAKSShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ActWork at HeightNear LPG header, M/s WMS worker was found working on red tag scaffolding platform. Counseling done.Plant AreaNear LPG HeaderStationaryCONTRACTORWMSShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ConditionProcedureAt heat exchanger area, pallet and spading plate were found on walkway. Counseling done.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ConditionVehicleAt DEL yard, one locked truck was observed parked without wheel chocks, with no driver and key available on site.Plant AreaAt DEL yardStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ConditionWork at HeightAt DEL yard, scaffolding structure for gas cylinders storage area was found without scaffolding tag.Plant AreaAt DEL yardCivilCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ActPPEAt 106-C, one of the M/s AKS worker was using a monkey ladder without wearing safety gloves and googles, counseling done.Plant AreaAt 106-CCivilCONTRACTORAKSShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ActProcedureNear WBL, M/s AKS worker was found wearing damaged safety shoes. Counseling donePlant AreaNear WBLStationaryCONTRACTORAKSShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ActWork at HeightAt 105-C3, M/s DEL worker was found working on scaffolding platform with hooking his harness. Counseling donePlant AreaAt 105-C3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ConditionWork at HeightNear -101-B and 101-C, sharp edges MS plates and scaffolding material were placed in the area without barrication. Counseled the team and instructed to barricade the area.Plant AreaNear -101-B and 101-CCivilCONTRACTORDELShutdownKorangi RefineryClosed2026-08-17
2025-08-17Unsafe ConditionWork at HeightAt 302-B scaffolding pipes were placed in the area without barrication. Counseled the team and instructed to barricade the area.Plant AreaAt 302-BStationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionWork at HeightAt 105-C3, during lifting the material at height by UE team the area was not barricaded, and poor housekeeping was observed. Counseled the team and instructed to barricade the area.Plant AreaAt 105-C3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-02-01Unsafe ActProcedureAt tank#56, During crane operation electrical team and unnecessary persons were moving under barricaded area.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2025-08-17Unsafe ConditionProcedureSIMOP activity was observed at plant corridor was observed. Counseled the team.Plant AreaPlant CorridorStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-02-01Unsafe ActPPEAt tank#56, AJC electrician was found working on electric supply board without gloves.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2025-08-17Unsafe ConditionSlip/Trip/FallAt plant corridor, steaming pipeline was laying on floor which have potential of tripping hazard. Informed to site supervisor.Plant AreaAt Plant CorridorStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-02-01Unsafe ActElectricalDamaged electric board# 11 was being used inside tank platform by AJC electrician . Electrical Bord was removed from site .Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-02-01Unsafe ActProcedureDuring crane operation AJC helper was moving under barricading area. Helper counseling was done.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-02-01Unsafe ConditionHousekeepingAt KT, Poor housekeeping was observed. Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-02-01Unsafe ConditionElectricalAJC welding machine #13 was being used without earthing.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2025-08-16Unsafe ActWork at HeightAt 105-C3, one of the M/s WMS worker was handling tools without wearing safety gloves ,consoling and informed to supervisor.Plant AreaAt 105-C3StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2025-08-16Unsafe ActPPEAt 105-C3, one of the M/s UE worker was using a monkey ladder without wearing safety gloves, informed to supervisor and immediately wearing a safety gloves.Plant AreaAt 105-C3StationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-17
2026-07-10Unsafe ActProcedureAt 105-C3, UE workers were lifting the material and tools without using tool bag. Counseled the worker.Plant AreaAt 105-C3StationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ConditionWork at HeightAt 101-B, scaffolding plank was not tie with steel wire. Counseled the worker.Plant AreaAt 101-BStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2026-02-07Unsafe ConditionProcedureAt tank #56, gas cutting cylinders were improperly chained and not identified as full or empty at storage place.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2025-08-16Unsafe ActWork at HeightAt 102-C, scaffolder was not hooked his harness properly. (Hooked both lanyard in single pipe). Counseled the worker.Plant AreaAt 102-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2026-02-07Unsafe ConditionEquipmentAt tank #56, the 100 KVA generator dip tray was found missing at the site.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionElectricalAt tank #56, a damaged electrical extension board insulation was observed during hot work inside the tank. Immediately removed from the site.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2025-08-16Unsafe ConditionPPEAt plant area, M/s DEL worker were loading scaffolding material on trolley without place the wheel stopper. Counseled the team.Plant AreaAt Plant AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2026-02-07Unsafe ConditionElectricalAt tank #56, tool bags were not used while working at height during shell fit-up activities. Counseling done and instructed to bring the tool bag.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionPPEAt tank #56, workers were observed not using KN-95 face masks during welding, back grinding, and related activities.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ActProcedureAt tank #56, personnel were observed working under suspended loads, creating a line-of-fire hazard during crane operations.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2025-08-16Unsafe ConditionElectricalAt 801-J, during hot work earthing cable found lose. Informed to site supervisor.Plant AreaAt 801-JStationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-17
2026-02-07Unsafe ActWork at HeightAt tank #56, workers were found working on scaffolding without properly hooked safety harnesses during crane and hot work activities.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-16Unsafe ActPPETank #35 – During civil work activity, one worker was observed not wearing safety gloves. Counseling was provided.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-16Unsafe ActWork at HeightTank #04 – During scaffolding erection, a 20-foot pipe was being handled by a single person, which is a manual handling violation. Counseling was provided.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-16Unsafe ActWork at HeightTank #04 – During erection of scaffolding, workers were not using a tool bag/bucket while working at height.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-16Unsafe ActPPETank #11 – During power brushing activity, one worker was observed not wearing a face mask. Counseling was provided.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionProcedureAt laydown area: The removed heat exchanger tubes were not properly stacked.Tank Farmlaydown areaStationaryCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionProcedureAt laydown area: The M/s UE fire extinguisher was found with low pressure and without a refilling/expiry date and without a monthly inspection tag.Tank Farmlaydown areaStationaryCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActPPEAt Tank#11: M/S ATL worker was found wearing low ankle shoesTank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionHousekeepingAt Tank#11: Poor housekeeping was observed. The area needs to be cleaned.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionProcedureAt tank#11: Dustbins were found full and need to be emptied.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-08-16Unsafe ConditionHousekeepingAt location 801-J, poor housekeeping was observed, various tools were scattered on the floor, welding and power cables were left unmanaged during hot work activities. This condition poses a potential tripping hazard.Plant AreaAt Location 801-JStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2026-02-11Unsafe ConditionProcedureThe cylinder kept in the M/s IIW ambulance was found embossed as “Nitrogen”. Additionally, the hydrostatic test date was not visible on the cylinder.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-08-16Unsafe ConditionProcedureAt M/s DEL yard, after sunset crane operation was performing without any light arrangements.Plant AreaAt M/s DEL yardStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2026-02-11Unsafe ConditionProcedureAt the front side of the storm pit, an open pit was found that needs to be covered.Plant AreaStorm PitCivilPRLRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-08-16Unsafe ConditionVehicleNear JP 1 gantry (DEL Office Area), Two locked trucks were observed parked without wheel chocks, with no drivers or keys available on site.Plant AreaNear JP 1 gantryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-16Unsafe ActElectricalNear JP 1 gantry (DEL Office Area), two energized electrical distribution boards (DBs) were found having no PRL’s electrical inspection tags.Plant AreaNear JP 1 gantryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-17
2026-02-11Unsafe ConditionPPEAt Tank #35 Yard, during excavation work, most M/s IIW workers were found without wearing dust masks in a dusty environment.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionProcedureThe first aid kit was not available in the M/s IIW ambulance.Tank FarmIIW AmbulanceConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActWork at HeightAt the M/s IIW Yard, workers were found sitting on the pipes of a red-tagged scaffolding structure.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActPPEAt the DEL Yard, M/s DEL worker was found working without a safety helmet and most workers were found without wearing safety goggles.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ConditionProcedureAt the DEL Yard, M/s DEL workers were found wearing coveralls not approved by PRL, having metallic buttons.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionEnvironmentAt Road #7, the waste yard was found overfilled and needs to be cleanedPlant AreaRoad #7StationaryPRLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionWork at HeightAt the Heat Exchanger area, scaffolding pipes were placed on the walkway without barrication.Plant AreaBoiler No. 4CivilCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActWork at HeightAt Gantry substation: M/s QK Builders were working inside a confined space without following the confined space protocol. Furthermore, no ladder was provided for safe entry or exit.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-07-29Unsafe ConditionProcedureTank # 51 fire wall crack on different location. Need to be repair.Tank FarmTank # 51CivilPRLRoutineKemari TerminalClosed2025-07-30
2025-07-29Unsafe ConditionProcedureFoam tank 2900ltr main valve rusty need clean & paint requitTank FarmFoam TankCivilPRLRoutineKemari TerminalClosed2025-07-30
2025-07-29Unsafe ConditionProcedureFoam tank 2900 & 5330ltr foundation crack. Need concrete wall/foundation requit.Tank FarmFoam TankCivilPRLRoutineKemari TerminalClosed2025-07-30
2025-07-29Unsafe ConditionProcedureFoam skid pump & circulation motor Centre area concrete floor need to be repaired.Tank FarmFoam Skid PumpCivilPRLRoutineKemari TerminalClosed2025-07-30
2025-07-29Unsafe ConditionProcedureFire wall Tank # 51 & 63 sub-surface Hyderant need paint.Tank FarmTank # 51 & 63CivilPRLRoutineKemari TerminalClosed2025-07-31
2025-07-29Unsafe ConditionProcedureIsolation valve # 3 (Road # 4) & tank # 62 by-pass valve need paint.Tank FarmRoad # 4 & tank # 62CivilPRLRoutineKemari TerminalClosed2025-07-31
2026-02-17Unsafe ConditionProcedureAt backside of control room: M/s smart climate worker was observed wearing low-ankle footwear and failing to wear his coverall properly.Plant AreaBackside of Control RoomElectricalCONTRACTORSmartRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-07-29Unsafe ConditionProcedureConcrete plate form required in front of tank # 59 manifold.Tank FarmTank # 59CivilPRLRoutineKemari TerminalClosed2025-07-31
2025-07-29Unsafe ConditionProcedureHydrant # 1 concrete plat form need to be repair.Tank FarmHydrant # 1CivilPRLRoutineKemari TerminalClosed2025-07-30
2026-02-17Unsafe ActPPEAt DEL Yard: One worker was not wearing safety goggles.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ActPPEAt Tank #35: During stone compaction activities, the roller operator was not wearing safety goggles.Tank FarmTank # 35ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ActWork at HeightAt Tank #04: During scaffolding work at height, one scaffolder was not using a tool lanyard (tool tie).Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ActPPEAt Tank #11: During vacuum testing at the tank bottom, two workers were not using rubber gloves.Tank FarmTank # 11ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ActPPEAt gate #3. M/s DEL vehicle (LZJ-9227) was operated by a driver without a valid DDC certification. Furthermore, the vehicle’s spark arrestor was found to be substandard, the vehicle was not equipped with a reverse alarm and the fire extinguisher was expired.Gate # 03Gate #3ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ConditionHousekeepingAt ATL Yard: A gas cylinder was stored upright without being secured by a safety chain.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-17Unsafe ConditionHousekeepingAt ATL Yard: Multiple filled diesel cans were found stored directly on the ground instead of within a designated secondary containment area.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-20
2025-07-31Unsafe ConditionEquipmentSkid generator concrete foundation damage. Need repair.KOR RefinerySkid Generator AreaStationaryPRLRoutineKorangi RefineryClosed2025-08-01
2026-02-21Unsafe ConditionProcedureAt tank 56, AJC  Muneer rigger safety shoes was found damage inform to AJC shahid.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-27
2025-07-31Unsafe ActPPEAt tank #05, a scaffolder was observed wearing damaged gloves. Informed the site supervisor.Plant AreaTank #05CivilCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ActPPEAt tank #05, a worker was observed with mask within the premises of sand blasting activity. Woker was counseled.Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2026-02-21Unsafe ConditionProcedureAt tank 56, AJC One electric board's insulation was damaged.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-27
2025-07-31Unsafe ActVehicleAt tank #05, a truck was observed blocking the firefighting equipment. Informed the site supervisor.Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2026-02-21Unsafe ActWork at HeightAt tank 56, AJC worker was found walking on third shell platform without properly hooked harness walk on third shell platformTank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-27
2025-07-31Unsafe ConditionElectricalAt tank #05, the earthing wire of the fresh air compressor was not attached properly. Informed the site supervisor.Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ActHousekeepingAt tank #05, an energized grinder was observed on the ground and was not placed on grinder stand. Informed the site supervisor.Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ConditionLack of SupervisionAt tank #05, combustible material (dried bushes) was observed within the premises of hot work and smoke was also observed. Informed and instructed the site supervisor to remove the combustible material."Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ActWork at HeightAt tank #11, a worker was observed working on the scaffolding platform with both the lanyards of the harness attached to the same pipe. Worker was counseled.Plant AreaTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2026-02-25Unsafe ActEnvironmentAt decanting area: it was observed that waste bin is overflowing, needs to be cleaned.Tank FarmDecanting AreaLogisticPRLRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-25Unsafe ActVehicleAt decanting area: PRL staff and bowser driver were found walking on the bowser without wearing a safety harness. Counseling done.Tank FarmDecanting AreaLogisticPRLRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-28Unsafe ConditionHousekeepingDEL Yard – Improper storage and segregation of oxygen and DA cylinders; cylinders not secured with chains.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-05
2026-02-28Unsafe ConditionProcedureTank #35 – Excavator operating without functional swing alarm.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-05
2026-02-28Unsafe ConditionProcedureTank #04 – Hot work area not properly covered and clean as per procedure during gas cutting. immediately as per procedure clean and covered gas cutting area. CloseTank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-05
2026-02-28Unsafe ConditionVehicleTank #11 – Ambulance driver was engaged in material loading using another vehicle inside the tank yard, and no backup ambulance driver was available on duty.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-05
2025-07-31Unsafe ConditionElectricalAt tank #11, the insulation of the earthing wire of the welding machine was observed damaged. Informed to site supervisor.Plant AreaTank #11StationaryCONTRACTORATLRoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ConditionElectricalAt storm water pit, a damaged electrical extension board was observed on site. Informed the site supervisor.Plant AreaAt Storm Water PitStationaryCONTRACTORRERoutineKorangi RefineryClosed2025-08-01
2025-07-31Unsafe ConditionElectricalAt storm water pit, an uninsulated joint in the earthing wire was observed, lacking proper taping or insulation. Informed the site supervisor.Plant AreaAt Storm Water PitConstructionCONTRACTORRERoutineKorangi RefineryClosed2025-08-01
2025-08-01Unsafe ActPPEAt tank #05, M/S ATL worker was observed working while wearing torn gloves. Informed and instructed the site supervisor to get it replaced with new gloves.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-02
2025-08-01Unsafe ActWork at HeightAt tank #11, M/S ATL workers were observed working parallel on the scaffolding platform during plates fit up activity. Informed the site supervisor and counseled the workers.Tank FarmTank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-02
2025-08-01Unsafe ActPPEAt tank #05, M/S ATL worker observed working without safety gloves and folded sleeves. The worker was counseled down.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-02
2025-08-01Unsafe ConditionProcedureAt road #07, cracks were observed on the steps of the walkway. Please take necessary corrective actions.Plant AreaAt Road #07CivilPRLShutdownKorangi RefineryClosed2025-08-02
2025-08-01Unsafe ConditionLack of SupervisionAt storm water pit, the trolley of the gas cutting set was observed rusted and corroded. Informed the site supervisor.Plant AreaAt Storm Water PitStationaryCONTRACTORREShutdownKorangi RefineryClosed2025-08-02
2026-02-28Unsafe ActPPETank #11 – Workers handling MS plates without proper rigging gloves counselling done.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-05
2026-02-28Unsafe ConditionProcedureTank #11 – Workers found inside confined space without standby man. counselling done.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-05
2026-02-28Unsafe ConditionHousekeepingPoor housekeeping found inside tank#56 inform to AJC (HSE supervisor) Osama and removed all combustible materials. (Close)Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-03-05
2026-02-28Unsafe ConditionElectricalA welding rectifier was observed without earthing and bonding. Electrician were asked to install the same. (Close)Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-03-05
2025-08-01Unsafe ConditionEquipmentAt storm water pit, the generator tire was observed burst. Informed the site supervisor.Tank FarmAt Storm Water PitStationaryCONTRACTORREShutdownKorangi RefineryClosed2025-08-02
2026-07-09Unsafe ConditionProcedureElectric board #12 are found insulation damage inform to AJC electrician . (closed)Plant AreaAt 202 Air CoolerStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-01Unsafe ActHousekeepingAt tank #05, M/S ATL worker was observed wearing damaged safety shoes. Informed and instructed the site supervisor to get it replaced with new shoes.Plant AreaTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-02
2025-08-09Unsafe ActEquipmentWelding Supervisor Changed The Grinder Disc Without Disconnected From Safetigal.Plant AreaPlant AreaStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2026-03-06Unsafe ConditionProcedureRoad No. 01: M/s RE workers were observed sitting on the road due to the unavailability of a designated rest shade.Tank FarmRoad No. 01ConstructionCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-06Unsafe ConditionProcedureRoad No. 01: M/s RE rigger was found using damaged gloves.Tank FarmRoad No. 01StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-06Unsafe ConditionVehicleRoad No. 01: an approximately 20-ft pipeline was being shifted using a forklift without securing it with belts, which may lead to collapse. Counseling done.Tank FarmRoad No. 01StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-10
2025-08-09Unsafe ConditionEquipmentMiller Machine Also Found Without Earthing Wire.KTKTStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2026-03-03Unsafe ConditionEquipmentAt DEL Yard, a generator was lifted by forklift under unsafe conditions, with an unbalanced suspended load striking the forklift.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-03Unsafe ConditionPPEAt DEL Yard, a worker was observed wearing safety shoes not approved by PRL.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-03Unsafe ConditionWork at HeightAt Tank #21, the scaffolding walkway was observed without an inspection tag.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2025-08-08Unsafe ActPPE3 person of civil worker folding was erecting roof top of office building without safety goggle. Counseling was done.KOR RefineryKOR RefineryStationaryCONTRACTORAJCShutdownKorangi RefineryteamClosed2025-08-10
2026-03-03Unsafe ConditionWork at HeightAt Tank #21, the workers’ rest area was incomplete and without required scaffolding inspection tag.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-03Unsafe ConditionElectricalAt Tank #21, the welding electrode oven was found without an electrical inspection tag and was immediately reported to the HSE Lead for replacement.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-03Unsafe ActWork at HeightAt Tank #15, the Civil UE team was observed working at height in unsafe position.Tank FarmTank #15CivilCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-10
2025-08-08Unsafe ActProcedureDuring grinding works a fitter was observed having covered his face with clothes. Advised him to remove it while doing hot works.KTTank FarmStationaryCONTRACTORAJCShutdownKorangi RefineryClosed2025-08-09
2025-08-08Unsafe ConditionElectricalElectrical extension board # 13 damaged receptacle was replaced with new one.KTKTStationaryCONTRACTORAJCShutdownKorangi RefineryClosed2025-08-09
2026-03-05Unsafe ConditionWork at HeightTank #04 (IIW): during scaffolding pipe cutting, the activity was obstructing workers using the walkway.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-05Unsafe ConditionPPETank #04 (IIW): during cutting work inside the tank, two riggers were observed not wearing face masks.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-10
2025-08-07Unsafe ActLack of SupervisionAt tank#05, during sandblasting activity, the required safe distance was not maintained, the workers were instructed to maintain and clearly mark the safe distance during sandblasting operations informed site supervisor "Tank FarmTank #5ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-08
2026-03-05Unsafe ConditionProcedureTank #04 (IIW) : during gas cutting work, gas cutter hose was found without proper double isolation (metallic flexible hose pipe).Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-10
2025-08-07Unsafe ConditionPPEAt tank#05, main entrance door was blocked, informed to HSE supervisor and obstruction was removed, and the main entrance was cleared for safe access.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-08
2026-03-09Unsafe ConditionHealthTank #30 – M/S DEL: Worker rest shade was not available at the work site, which is required for worker welfare and heat stress control.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ActProcedureAt Tank #05, a fitter was observed not wearing over-glasses during the task. The concerned person was informed and instructed to wear proper eye protection.Tank FarmAt Tank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-09Unsafe ConditionProcedureTank #30 – M/S DEL: During main shell plate cutting activity, the HSE representative was not present at the work site.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-09Unsafe ConditionElectricalTank #21 – M/S DEL: Fire extinguisher was not available at the main electrical distribution board, which is a critical safety requirement.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-09Unsafe ActPPETank #21 – M/S DEL: A gas cylinder trolley was moving over the red-tagged scaffold walkway, which is an unsafe practice and must be stopped immediately.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-09Unsafe ConditionHousekeepingTank #21 – M/S DEL: Gas cylinder shade in the classified zone was found incomplete, requiring immediate completion to ensure safe storage.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ConditionProcedureAt Tank #05, two fabrication teams were performing parallel hot work activities in the same area. It was advised to ensure proper coordination, implement adequate safety measures.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-09Unsafe ActHousekeepingATL Yard – M/S ATL: A worker was observed moving in the ATL yard without a safety helmet; the worker was immediately counseled on PPE compliance.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-09Unsafe ActPPETank #04 – M/S IIW: During firewater line excavation, workers were found using damaged safety gloves and not wearing face masksTank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ConditionSlip/Trip/FallAt tank #11, the 60 kVA generator at Tank No. 11 was repeatedly tripping during operation. The issue was reported to the maintenance team and concerned supervisor for immediate inspection and necessary corrective.Tank FarmTank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-13Unsafe ConditionHousekeepingAt Tank #30, M/S,DEL ,the HSE person was not regularly present, housekeeping was poor, and a worker performing gas cutting was not using a mask.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionHousekeepingAt the DEL yard, M/S,DEL, during crane operation four riggers were present but the required third-party rigger was not available.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ConditionHousekeepingAt Tank #05, Hot work canopy contained grass and combustible materials, posing a potential fire hazard. The area was immediately cleared of all combustible materials, and housekeeping was carried out.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-13Unsafe ConditionWork at HeightAt Tank #04, M/S,IIW, a G.I. sheet used for work at height was found lying unsecured and not properly tied.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionSlip/Trip/FallAt Tank #04, M/S,IIW ,a walkway coupling was lying on the walkway creating a tripping hazard.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionSlip/Trip/FallTank #30: M/S,DEL, Poor housekeeping observed inside the tank area and no worker rest shade was provided at site.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionWork at HeightTank #04: M/S,IIW, Modified walkway scaffolding platform was found without re-inspection and re-tagging after alteration.Tank FarmTank # 4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ActPPEAt Tank #05, workers were not wearing N-95 masks during power brushing and housekeeping activities. Work was stopped immediately, and the workers were instructed to wear appropriate respiratory protection (N-95 masks).Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-13Unsafe ConditionSlip/Trip/FallTank #11: M/S,ATL, during hot work activity, an electrical power tool was left inside the tank bottom, creating a potential tripping hazard.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionProcedureTank #11:M/S,ATL, during gas cutting activity, gas cylinders were found without a protective shade at the tank yard.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ConditionPPEAt tank #05, Grinder No. 32 (5-inch) suddenly stopped working during operation. The equipment was handed over to the relevant electrician for immediate inspection and necessary repair.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-13Unsafe ConditionProcedureAt Road No. 14 – M/S Construction & IIW: Civil excavation work of around 5 ft depth was observed without a valid Confined Space Certificate and required safety protocols.Tank FarmRoad No. 14ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-13Unsafe ConditionProcedureAt Road No. 16 – M/S Construction: Civil excavation of approximately 5 ft depth was in progress without issuing a Confined Space Certificate and required safety protocol implementation.Tank FarmRoad No. 16ConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ActPPEAt tank #05, During the dismantling of scaffolding inside Tank No. 05, it was observed that the worker was not wearing an N-95 mask, which is required for respiratory protection in confined spaces and dusty environments. The worker was immediately instructed to stop work and wear the required N-95 mask.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-16Unsafe ConditionVehicleDEL Yard: M/s DEL. MS plate was observed shifting with a forklift without proper tying/securement, creating an unsafe lifting activity.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-04Unsafe ActPPEAt tank #05, During the vacuum test on Tank No. 05 Today, the workers were handling oil and chemicals without wearing the appropriate protective gloves. Informed construction representative and HSE supervisor.Tank FarmAt Tank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-16Unsafe ConditionProcedureTank #30: M/s DEL. HSE representative was not present at the work site during ongoing activities.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-16Unsafe ConditionSlip/Trip/FallTank #21: M/s DEL. Dismantled MS plate of tank 21 was lying at the tank main entrance creating a tripping hazard.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-16Unsafe ActPPETank #21: M/s DEL. Worker performing internal cutting work at the tank bottom was not wearing a face mask.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-16Unsafe ConditionProcedureTank #04:M/s IIW. Dismantled MS plate of tank 04 was found without proper barrication inside the tank yard.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-15
2025-08-05Unsafe ActElectricalAt Tank #05, two workers were wearing damaged coveralls. Informed Bilal HSE Officer and They were advised to replace the damaged PPE immediately to maintain safety standards.Tank FarmAt Tank #05ConstructionCONTRACTORATLShutdownKorangi RefineryteamClosed2025-08-05
2026-03-17Unsafe ConditionPPEAt Tank #30, A critical unsafe act was observed involving the Rotary team manually handling an electrical pump (approx. 100 kg) from the tank yard to the road. The task was performed without proper lifting equipment or appropriate rigging gloves.Tank FarmTank #30RotaryCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-17Unsafe ActProcedureAt Road No. 01(M/S DEL), a Descon crane was observed moving without a flagman.Tank FarmRoad No. 01ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-04Unsafe ActElectricalAt tank #05, ATL electrician was on leave, and in his absence, the electrical work was carried out by an electrician helper. The helper was not approved by the PRL Electrical Department, and no job card was issued for the task. Informed HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-17Unsafe ConditionElectricalAt DEL Yard (M/S DEL), the electrical distribution board (D.B.) was found without a protective shade.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-17Unsafe ConditionEquipmentAt Tank #30, (M/S DEL), during hot work activities using grinders/millers, no shade was available for the workers.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-17Unsafe ConditionProcedureAt Tank #11, (M/S ATL),  an excavation area was observed without proper barricading.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-05Unsafe ActPPEAt Tank #11, a worker was hammering without using a tool tie. Worker was instructed to use tool tie to prevent dropped object hazards.Plant AreaAt Tank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-17Unsafe ConditionProcedureAt Tank #11 (M/S ATL), during the safety round and site closing, some materials were found not properly barricaded.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-05Unsafe ActPPETt tank #05, C-channel was observed being lifted with a rope and gripped incorrectly, instructed to use proper lifting methods and correct grip point"Tank FarmTt Tank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2026-03-18Unsafe ConditionWork at HeightAt Road#0 near Gantry Area: The welding electrode desiccator's cable gland and lux were not in good condition and need to be replaced.Tank FarmRoad#0LogisticCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-05Unsafe ActLack of SupervisionAt Tank #11, two fire extinguishers of ATL had not been inspected for the past 2 months, informed HSE supervisor and immediate inspection was advised"Tank FarmAt Tank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-06
2026-03-18Unsafe ConditionPPEAt Road#0 near Gantry Area: A worker from M/s UE was using a grinder while wearing a welding face shield instead of a proper grinding shield and he was also not wearing a safety helmet.Tank FarmRoad#0LogisticCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-05Unsafe ActWork at HeightAt tank #05, during mechanical work on shell no.2, a scaffolder was modifying the same platform on which the work was being carried out, inform to site HSE supervisor ensure proper coordination.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-06
2026-03-19Unsafe ConditionWork at HeightAt tank # 35-yard and M/s IIW yard , partition wall of corrugated sheet and scaffolding structure have been collapsed due to the recent thunderstorm, needs to be securedTank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-19Unsafe ConditionWork at HeightAt tank # 11, the soil around the scaffolding base plate has been excavated and removed, which may compromise the stability of the structure.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-07-10Unsafe ConditionEnvironmentA product line running from Tank 38 to Tank 01 had leakage from a valve, causing product dropping, inform Mr. Ijaz PRL(oil movement) The leaking valve was immediately reported to the concerned department, and the line was secured to prevent further spillage.Tank FarmTank 38OM KTPRLShutdownKorangi RefineryClosed2025-08-08
2026-03-19Unsafe ConditionProcedureAt tank # 11, contractor safety sign board has been fell on the ground, needs to be re-fix and secure the safety board.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-08Unsafe ConditionProcedureAt road #0, a PSO oil tanker, which arrived for fuel filling, was blocking the fire hydrant on informed HSE department and remove oil tanker.KOR RefineryAt Road #0LogisticCONTRACTOROMCShutdownKorangi RefineryClosed2025-08-09
2026-03-19Unsafe ConditionHousekeepingAt material storage area near the construction workshop, several corrugated sheets have become detached and are currently lying on the ground. These sheets need to be properly secured to prevent them from being blown away by strong winds and to avoid the risk of injury to personnel.Construction WorkshopMaterial Storage AreaConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-19Unsafe ConditionHousekeepingAt Road 16, CCTV camera cables have been detached and lying on ground due to the recent thunderstorm, needs to be secured to prevent further damage.Tank FarmRoad No. 16A&SPRLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-07Unsafe ActProcedureAt road no#16 ,a worker was using a mobile phone, inform to Mr. Usman and the worker was instructed to avoid mobile usage in operational areas and counseled on safety protocols.KOR RefineryAt Road #16ConstructionCONTRACTOROMCRoutineKorangi RefineryteamClosed2025-08-09
2026-03-19Unsafe ConditionFalling ObjectAt Road 12, the pipeline is resting on temporary supports with stones used as wedges. Proper wedges must be installed to prevent the pipeline from falling.Tank FarmRoad No. 12StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-25Unsafe ConditionPTWAt IIW Yard, M/S IIW, work was being carried out without a valid work permit and no safety personnel or paramedic were present on siteTank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-08Unsafe ConditionEnvironmentTank # 56 100kva diesel generator during operation radiator leakage was noticed.Tank FarmTank #56StationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-09
2026-03-25Unsafe ConditionEquipmentAt DEL Yard, M/S DEL, Inadequate weather protection observed for MS plate rolling and winch machine motors.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-25Unsafe ConditionSlip/Trip/FallAt ATL Yard, M/S ATL, Oxygen cylinders were found tilted, posing a falling hazard. Furthermore, the entrance to the storage area was blocked.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-08Unsafe ActProcedureAt tank#05, during the lifting operation, one rigger was holding the suspended load by hand, informed rigging supervisor and Instruct riggers to use tag lines and avoid holding suspended loads by hand during lifting operationsTank FarmTank #05StationaryCONTRACTORATLShutdownKorangi RefineryAhsanClosed2025-08-09
2026-03-25Unsafe ActPTWAt ATL Yard, M/S ATL, a 25 KVA generator was observed in operation without a valid Work Permit. Furthermore, both the Safety Officer and the ambulance driver were absent.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-09Unsafe ConditionEquipmentWelding Machine, No (01,08,03) Found Without Earthing Wire.KTKTStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2026-03-25Unsafe ConditionPTWTank #30, M/S DEL, the rest area roof is currently uncovered. Please install a cover to provide shade and protect workers from the sun.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-25Unsafe ConditionProcedureAt Tank #30, M/S DEL, the metal plate at the main tank entrance has sharp edges that need to be protected.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-25
2025-08-09Unsafe ConditionElectricalElectrical Board No (03) Found Safetigal Wire Without Protection.KTKTStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2025-08-09Unsafe ConditionElectricalElectrical Board No (12) Found With Without Nuts.KTKTStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2026-03-26Unsafe ConditionPPEAt DEL Yard (M/S DEL), two workers were observed moving in the yard without wearing safety helmets.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-08-08Unsafe ConditionLack of SupervisionAt tank#05, the distance between the three blasters during blasting operations was too short, informed to HSE supervisor and site supervisor maintain safe distance as per OSHA standard.Tank FarmTank#05StationaryCONTRACTORATLShutdownKorangi RefineryteamClosed2025-08-10
2026-03-26Unsafe ConditionLack of SupervisionAt ATL Yard (M/S ATL), the ambulance driver was absent and no standby driver was available on site and the ambulance was being driven by a diesel mechanic without a valid driving license and DDC approval.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionPPEAt IIW Yard (M/S IIW), some riggers and scaffolders were not equipped with safety gloves and safety goggles.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-08-08Unsafe ConditionLack of SupervisionAt tank#05, three air compressors were being used for sand blasting activities had only one operator on standby, informed site supervisor.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-09
2026-03-26Unsafe ActLack of SupervisionAt IIW Yard (M/S IIW), the ambulance driver was absent and no standby driver was available on site.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionLack of SupervisionAt Road#12: An oil bottle was found in the generator area without a spill pallet.Tank FarmRoad#12ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-08-08Unsafe ConditionHousekeepingAt road no#12, at sprinkle lines wall one cement block was placed unsafely, which could fall and hit workers below, informed rigging sup , HSE sup remove immediately.KOR RefineryAt Road #12ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-09
2026-03-26Unsafe ConditionSlip/Trip/FallAt Tank#35: An unstable segregation barrier was found leaning dangerously over workers in the rest area, posing a struck-by hazard.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-08-08Unsafe ActWork at HeightAt tank#11, one worker was working at height without clipping the lanyards of the harness with two different pipes, informed HSE sup and counseling.Tank FarmTank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-10
2026-03-26Unsafe ConditionEquipmentAt DEL yard: A generator trolly was found without a wheel chocks.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionProcedureAt DEL yard: The compressor fire extinguisher’s inspection is expired and its pipe was also damaged.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-08-08Unsafe ConditionLack of SupervisionAt tank#11, for the MS plate fit-up, wedge, U-clamps, and jigs were not secured with a chain, informed to HSE supervisor and secure the wedge, U-clamps, and jigs with a chain before starting the MS plate fit-up.Tank FarmAt Tank#11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-09
2026-03-29Unsafe ActPTWAt DEL yard: M/s DEL worker was observed performing maintenance work of compressor at height without a ladder or stool. Also, work was being carried out without a valid maintenance permit.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ConditionEnvironmentAt DEL yard: Diesel leakage was observed from a compressor causing environmental contamination.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-07Unsafe ActLine of FireAt tank 05, during hot work a fitter using grinder at main D-door ,sparks hitting to the passing workers. Informed to ATL,  HSE  supervisor and barricade ,stop entry during grinding activity.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-08
2026-03-29Unsafe ConditionProcedureAt Tank#11: The area needs to be properly barricaded as no work is currently in progress at the tank.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionProcedureAt IIW yard: A material shifting trolly was found parked without wheel chock.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-07Unsafe ActLack of SupervisionAt tank # 05, air compressor found without shield cover. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-08
2026-03-26Unsafe ConditionFalling ObjectAt IIW yard: Cylinders were not properly tied and one was in a falling position.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionSlip/Trip/FallAt IIW yard: Two GI sheets were found lying on the ground, needs to be secure.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-08Unsafe ActFalling ObjectAt tank# 05, spark were falling directly on the gas cylinder while using the grinder. Informed to HSE supervisor and immediately remove gas cylinder remove this place.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-09
2026-03-29Unsafe ConditionWork at HeightAt Road#07: M/s UE worker perform a work at height without tool tie, also supervisor is not present at the siteTank FarmRoad#07ConstructionCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-08Unsafe ActProcedureAt tank # 05, D-door was hold by the workers instead of hold by the chain block while its installing and welding.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-09
2026-03-29Unsafe ConditionPPEAt Road#12: M/s UE workers were observed working without safety gloves.Tank FarmRoad#12CivilCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActPPEAt Road#07: M/s QK workers were found performing soil-related tasks without wearing face mask and safety googles, leading to dust exposure.Tank FarmRoad#12CivilCONTRACTORQK BuildersRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActPPEAt Utility Area: M/s AKS worker was observed working at height without using tool tie. A falling object risk to workers below.Plant AreaUtility AreaStationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-08Unsafe ActWork at HeightAt 103E, 104E, and 102E, during scaffolding dismantling, one AKS scaffolder was found not using tool tie.Plant AreaAt Different LocationsCivilCONTRACTORAKSRoutineKorangi RefineryClosed2025-09-10
2026-03-29Unsafe ActFalling ObjectAt Road#1(Near Gantry): The pipeline is resting on temporary supports with stones used as wedges. Proper wedges must be installed to prevent the pipeline from fallingTank FarmRoad#1StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-04Unsafe ActWork at HeightAt 105 C1, 105 C7, and 105 C8, during scaffolding dismantling by the DEL team, a scaffolding pipe was struck by the product line. The worker was counseled.Plant AreaAt 105 C1, 105 C7, and 105 C8CivilCONTRACTORDELRoutineKorangi RefineryClosed2025-09-05
2026-03-29Unsafe ActProcedureAt DEL Yard: The rest area is incomplete and a worker was observed sitting in the unfinished area.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActEquipmentAt DEL Yard: Two grinders were left attended on a conductive MS plate with the power supply still connected.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-04Unsafe ActWork at HeightAt 107-F &117-C during scaffolding erection a worker found without tied his tool with tool teether at height. Informed to supervisor and counseling.Plant AreaAt 107-F &117-CCivilCONTRACTORAKSRoutineKorangi RefineryClosed2025-09-05
2026-03-27Unsafe ConditionProcedureAt Tank#11: Third-Party inspection tag was missing on the fire extinguisher.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-05Unsafe ActPPEAt tank 05, a wroker found without wearing rigging gloves while rigging activity of pipes. Informed to HSE supervisor and counseling .Tank FarmAt Tank #5CivilCONTRACTORAKSRoutineKorangi RefineryClosed2025-09-06
2026-03-29Unsafe ActEquipmentAt Road#12: GI sheet in the Generator Area was not tied properly. Secure all loose sheets immediately.Tank FarmRoad#12ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActEquipmentAt IIW Yard: Access of the generator was found blocked by another generator. Provide clear access for emergency situations.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActPPEAt Tank #30, M/S UE, M/s UE painter was found wearing damaged safety shoes.Tank FarmTank # 30ConstructionCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActProcedureAt Tank #30, M/S DEL, during the replacement of the gas cylinder used for gas cutting, the cutting torch regulators were left open, which created a risk of fire.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-28Unsafe ConditionProcedureAt tank-21, M/s DEL scaffolding shed for electrical DP was found with green tag.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-11Unsafe ActPPEAt tank #05, during the cutting work use grinder worker not wearing ear plug. Informed to HSE supervisor.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2026-03-29Unsafe ConditionLack of SupervisionAt tank-21, M/s DEL site safety supervisor was not present at site while work was being in process.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-28Unsafe ConditionPPEAt tank-4, M/s IIW electrician was found working without gloves.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-11Unsafe ActPPEAt tank #05, during the IFR work use Hammar workers not wearing an ear plug, high Noice present in inside tank. Informed to HSE supervisorTank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-11
2026-03-29Unsafe ActProcedureAT tank -35, The movement of M/s IIW excavator was observed without flagman.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-10Unsafe ConditionLack of SupervisionAt tank # 05, nearby main D .Door  scattered material was present. Informed to HSE supervisor and immediately remove these materials.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-11
2026-03-29Unsafe ActPPEAt tank-30-yard, M/s AKS workers (Usman ,Qurban, Noor, Haneef, Siddiq) were found wearing damaged safety shoesTank FarmTank # 30CivilCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-29Unsafe ActPPEAt Tank 35, M/s IIW, during civil activities, some workers were not wearing safety glasses and face masks.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-11Unsafe ActPPEAt tank#05, ATL 1 fitter during the main D. Door MS  plate fit up hammering work not wearing safety glove, informed to HSE supervisor and wearing a safety gloves.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2026-03-30Unsafe ActPPEAt Tank 35, M/s IIW, during civil activities, some workers were not wearing safety glasses and face masks. Counseling was conducted.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-11Unsafe ActLack of SupervisionAt tank #05,  ATL 3 workers were found in confined space without medical fitness certificate .informed to HSE supervisor and site in charge.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2026-03-30Unsafe ActPPEAt Tank 30, M/s DEL, during gas cutting inside the tank, the mechanical supervisor was not wearing a face mask. Counseling was conducted.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ConditionLack of SupervisionAt tank#11, during the tool inspection, it was observed that the electrical inspection tags of 2 LED lights were found expired. Informed to HSE supervisor and immediately electrical inspection tag install.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2026-03-30Unsafe ConditionProcedureAt Tank 35, M/s IIW, during civil work, a dumper was being used without a functioning reverse alarm.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-03-30Unsafe ActPPEAt DEL Yard, M/s DEL, some workers were not wearing safety goggles and safety gloves.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-03-30Unsafe ActProcedureAt Road No. 1, M/S RE, during hot work activities, no HSE person was present at the worksite.Tank FarmRoad # 1ConstructionCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ActLack of SupervisionAt tank # 11, while working on chain block, the impact gloves of rigger was found damaged, informed to HSE supervisor and immediately replace gloves.Tank FarmAt Tank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-13
2026-04-01Unsafe ActVehicleA low-pressure fire extinguisher was found on M/s AKS vehicle (No. JU-2694).Tank FarmAKS vehicleCivilCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ActPPEAt tank # 05, during handing of MS plate, the scaffolders were found without wearing impact gloves, informed to HSE supervisor.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-13
2026-04-01Unsafe ActVehicleAt tank 27, M/s AKS workers were observed working at height without using tool tie.Tank FarmTank 27CivilCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ConditionElectricalAt tank # 05, during the painting work, the electrical inspection tag of mixture machine was found expired. Informed to HSE supervisor and Electrician immediately inspection and tag install.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-13
2026-04-01Unsafe ConditionPPEFabrication Yard near JP-01 gantry: During MS plate shifting using a forklift: Tye of M/s Crescent fork lifter was in bad condition, M/s Crescent Fork lifter operator wasn’t wearing safety shoes, Workers were not wearing rigging glove, A helper was sitting at the back side of the forklift, Work permit was not available at the site.Tank FarmFabrication YardConstructionCONTRACTORCrescentRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureTank #04: M/s IIW, Safety signboard was observed in a tilted position.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-13Unsafe ActPPEAt tank # 05, Mr. Shahid Lodhi CM use scaffolding ladders without wearing safety gloves informed to HSE supervisor wearing a safety glove immediately.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2026-04-01Unsafe ConditionPPETank #21: M/s DEL, during splash plate removal at tank roof, the mechanical supervisor handled plates without wearing rigging gloves.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ActPPEAt tank #05, one worker was using a drill machine without wearing safety gloves. Informed to HSE supervisor.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-10
2026-04-01Unsafe ConditionWork at HeightTank #21: M/s DEL, during hot work at height, the ground area below was not barricaded.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionHousekeepingTank #21: M/s DEL, Gas cylinders were found lying in a horizontal position at the worksite.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-12Unsafe ActPPEAt tank #11, one fitter was lifting and shifting a Garder without wearing rigging gloves. Informed to HSE supervisor during lifting /shifting activities to avoid hand injuries.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-13
2026-04-01Unsafe ConditionEquipmentRoad No. 12: Oil leakage was observed from the main engine rotary part of M/s ATL's 60 KVA generator during operation.Tank FarmRoad#12ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureAt M/s ATL Yard: The door handle of the M/s ATL Ambulance was found damaged and the internal cleanliness was in poor condition.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionElectricalTank #30: M/s DEL, Earthing cable of the electrical distribution board (DB) was found damaged.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureTank #30: M/s DEL, during bottom plate removal, third-party of riggers were not available at the site.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionPPETank #30: M/s DEL, some workers were using safety helmets that were not approved by PRL, as they had 4-point suspensions and no air vents.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ActPPEFabrication yard near JP1 fork lifter helper was handling material without rigging gloves.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-14Unsafe ActPPEAt tank # 05 ,one fitter during the power brushing not wearing a face mask and Ear plug, informed to HSE supervisor and insure to use PPEs as per job requirements.(Waseem).Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-15
2026-04-01Unsafe ActProcedureAt road 9, M/s DEL scaffolding materials were placed without barrication.Tank FarmRoad#9ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-14Unsafe ConditionEquipmentAt tank # 11 and at tank #05, two generators were used despite their 3rd party inspection were being expired. Informed to HSE Lead ensure timely renewal of inspection and only operate certified equipment.Tank FarmAt tank # 11 and at tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-14Unsafe ConditionProcedureAt tank # 05,the scaffolding team and fabrication team were working in parallel at the same location, informed to HSE supervisor coordinate work and avoid parallel high -risk activities.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-15
2025-09-14Unsafe ConditionLack of SupervisionAt tank # 11, the HSE lead and HSE supervisor were not present at site.Tank FarmAt Tank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-15
2025-09-19Unsafe ConditionProcedureTop purer manifold found barricaded and blocked due to excavation.KOR RefineryKOR RefineryCivilPRLRoutineKorangi RefineryteamClosed2025-09-17
2026-04-01Unsafe ActHousekeepingAt tank-21, M/s DEL were placed combustible material (wooden planks) inside tank yard.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionWork at HeightAt tank-21, M/s DEL scaffolding materials were stake without barrication.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionLine of FireAt tank-21, M/s DEL fire blanket was unable to bear sparks.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureAt tank-21, DCP fire extinguisher was placed near M/s DEL electrical DB, however CO2 extinguisher is recommended.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-19Unsafe ConditionProcedureRoad-06 found depressed near tank-18.KOR RefineryRoad-06CivilPRLRoutineKorangi RefineryteamClosed2025-09-17
2026-04-01Unsafe ConditionProcedureAt tank-35, fire extinguishers were not available in M/s IIW tractor and road roller.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureAt tank-4, M/s IIW placed trolly inside the tank without stoper.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-01Unsafe ConditionProcedureAt tank-11, fire extinguisher was not available in M/s ATL Shazoor truck.Tank FarmTank # 11ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-02Unsafe ConditionWork at HeightAt Tank #56, missing of expiry date was observed on scaffolding green tag.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ActProcedureAt Tank #56, During shell fit-up, a C-channel was being lifted using only with a rope without proper lifting/ hoisting method by M/s AJC workersTank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ConditionWork at HeightAt Tank #56, M/s AJC safety sign was found hanging improperly on the top scaffolding platform.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ConditionWork at HeightAt Tank #56, M/s AJC grinder operator’s face shield was loose while working on the top scaffolding platform.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ConditionEquipmentAt Tank #56, The terminal tumble of M/s AJC welding machine was found damaged. The HSE team was informed and advised immediate replacement before continuing work.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ConditionPPEAt Tank #56, During back grinding at the shell, M/s AJC workers were not using KN-95 masks. The HSE team was informed.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-02Unsafe ConditionElectricalAt Tank #56, The main electrical supply cable of the M/s AJC automatic girth welding machine was found exposed. The HSE team and Electrical team were informed.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2025-09-15Unsafe ConditionLack of SupervisionAt tank#05, during crane operation, the mechanical team was moving inside the barricaded area. Informed to HSE Supervisor and hold the mechanical activates.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2026-04-02Unsafe ActWork at HeightAt Tank #56, It were observed that M/s AJC workers using stool on scaffolding platform.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2025-09-15Unsafe ActFalling ObjectAt tank#05, on the dome roof ,a worker was pulling the sprinkler line using his safety harness lanyard. The lanyard hook was not anchored; an no supervisor was present at the location. Informed to HSE lead.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2025-09-15Unsafe ConditionPPEAt tank#05, while installing the sprinkler line on the dome roof, workers were working during light rain. This was unsafe because the roof surface had become slippery. Informed to Nizam sb. And work should be stopped during rain and the dome roof surface must be ensured dry. Tank FarmAt Tank#05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2026-04-03Unsafe ConditionFalling ObjectAt DEL Yard: Cylinders found without proper securing/tie-up,  creating a falling hazard.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionHousekeepingAt Tank#11: Splash plates were placed on wooden pieces, proper support/ stand is required.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionProcedureAt Tank#11: M/s ATL Material shifting trolly has no proper wheel chocks.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionProcedureAt Tank#11: Construction Material found without proper barricading; immediate barricading is required.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionElectricalAt Tank#21: M/s DEL Electrical DB(Distribution Board) was found without a proper weather shade.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionHousekeepingAt Tank#30: M/s DEL Material is placed outside of barricaded area, and MS plates are kept on wooden Pieces.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionSlip/Trip/FallAt Tank#30: M/s DEL MS plate laying in yard, creating a tripping hazard. Sharp edges need to be removed & proper stacking is required.Tank FarmTank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-18Unsafe ActVehicleAt tank # 05,during the lifting operation ,the truck driver was not present, and both the truck and the crane were being drive by the same operator.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-19
2026-04-03Unsafe ActPPEAt Road#14: M/s GMC worker was observed working in sand without wearing a proper mask.Tank FarmTank # 30ConstructionCONTRACTORGMCRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ActProcedureAt Tank#4: Depressed ground surface was noted due to rain; backfilling is required.Tank FarmTank # 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-18Unsafe ActPPEAt tank # 05,ATL fabricator was handling an MS plate ring on the doom roof without wearing safety gloves and without hooking his safety harness. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-19
2026-04-03Unsafe ActProcedureAt Road#6 (Front side of fire manifold): Depressed ground surface was observed due to recent rain; backfilling is required to stabilize the area.Tank FarmRoad#6CivilPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ActHousekeepingAt Road#4: The Pit cover was found missing; it needs to be replaced with a proper cover immediately.Tank FarmRoad#4CivilPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionSlip/Trip/FallAt Tank#30 Yard: A walkway step was found damaged/broken, immediate repair is required to prevent tripping hazards.Tank FarmTank # 30CivilPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionEnvironmentAt Decanting Area: Hazardous waste was found mixed with recyclable and general garbage; waste segregation is required and bins need to be emptied.Tank FarmDecanting AreaLogisticPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionVehicleAt Decanting area: Bowser no. GLTA 8619 & HNZ 2077 doors were found locked.Tank FarmDecanting AreaLogisticPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-20Unsafe ActEquipmentAt tank # 05, while changing the disc of grinder the plug was connected (energized). Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-20
2025-09-20Unsafe ActProcedureAt tank # 05, some person entered the tank whose names were not included in the SBM medical list,(Mr. Khalid Anwar, Mr. Majeed sb.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-21
2025-09-20Unsafe ConditionElectricalAt tank # 05, after replacement of the breaker and switch in the generator , the electrical tag was not re-tagged. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-21
2025-09-20Unsafe ConditionSlip/Trip/FallUnnecessary material placed near fire hydrant and foam trolley Infront of G-2 warehouse.KOR RefineryG-2 warehouse.ConstructionPRLRoutineKorangi RefineryClosed2025-09-21
2025-09-23Unsafe ConditionProcedureFire hydrant #08 access found block and wild bushes around fire hydrant.KOR RefineryFire hydrant #08WarehousePRLRoutineKorangi RefineryClosed2025-09-24
2026-06-24Unsafe ConditionProcedureAt Tank #35,M/s IIW. MS plate was found near resting shade without barrication.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-06-23Unsafe ConditionSlip/Trip/FallAt Tank #56, M/s AJC. on the rear side of the tank, loose planks were observed on the scaffolding platform.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-23Unsafe ConditionElectricalAt Tank #56, M/s AJC. during welding work, the earthing wire connection was found loose.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-23Unsafe ActLack of SupervisionAt Tank #30 – M/S DEL: Parallel activities are being carried out simultaneously on the tank without proper coordination.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-23Unsafe ActPPEAt Tank #30 – M/S DEL: Fabricator's safety gloves were found damaged and require immediate replacement.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-07-11
2025-09-23Unsafe ConditionProcedureAt warehouse near salt yard wild, bushes around fire water line (hydrant#0 7) and EEWS-1, needs to be removed.WarehouseNear Salt YardCivilPRLRoutineKorangi RefineryClosed2026-07-11
2025-09-23Unsafe ConditionProcedureMCP # 53 at warehouse G-3 needs to be re-paint.KOR RefineryWarehouseCivilPRLRoutineKorangi RefineryClosed2026-07-11
2025-09-23Unsafe ActWork at HeightAt tank #05, during inspection QC inspection team were found without chain strip wearing at work at height .informed to HSE supervisor .Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-07-11
2025-09-23Unsafe ActEquipmentAt tank #05, dustbin was found filled garbage. Informed to HSE supervisor immediately empty to dustbin.)Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-11
2025-09-23Unsafe ActLack of SupervisionAt tank # 05, during the material shifting worker using damage rope, informed to HSE supervisor and immediately replace lifting rope .Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-11
2025-09-23Unsafe ConditionEquipmentAt tank#05, during hot work , the Electrical D.B was tripping repeatedly, after inspection, it was found that the electrodes were shorting, which caused the tripping. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-11
2026-07-11Unsafe ConditionLack of SupervisionAt ATL workshop, filled gas cylinders were stored lying on each other, which is unsafe and may cause leakage or cylinder damage. Informed to HSE supervisor.KOR RefineryATL workshopConstructionCONTRACTORATLRoutineKorangi RefineryAhsanOpen
2026-04-01Unsafe ActProcedureAt tank-4, M/s IIW walkway ramp was red tag, while workers were using it.Tank FarmTank #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-03-29Unsafe ActPPEAt Tank #30, M/S UE, M/s UE painter was found wearing damaged safety shoes.Tank FarmTank # 30ConstructionCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-04-01Unsafe ConditionPPETank #30: M/s DEL, some workers were using safety helmets that were not approved by PRL, as they had 4-point suspensions and no air vents.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-24Unsafe ActPPEAt tank #11, during fabrication work, one fabricator was not wearing a safety glove. Informed to HSE supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-11
2025-09-24Unsafe ActLack of SupervisionAt tank # 11, sparks from the grinder were hitting to another worker. Informed to HSE lead.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-11
2025-09-24Unsafe ActWork at HeightAt tank # 11, during the scaffolding modification one scaffolder safety harness’s lanyard was not hooked. Informed to HSE supervisor and counseling doneTank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-24
2025-09-23Unsafe ConditionSlip/Trip/FallAt ATL workshop, filled gas cylinders were stored lying on each other, which is unsafe and may cause leakage or cylinder damage. Informed to HSE supervisor.Tank FarmATL WorkshopConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-09-24
2025-09-24Unsafe ActWork at HeightAt tank#11, during the safety round one worker harness does not hook. Informed to HSE Supervisor and immediately action.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-24
2025-09-24Unsafe ConditionHousekeepingAt tank#11, during the safety round, loose materials(cutting disk, channel pace ,planks etc.). were found on the scaffolding platform and tank roof ,creating a potential falling object or tripping hazard. Informed to HSE supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-25
2026-03-29Unsafe ConditionWork at HeightAt Road#07: M/s UE worker perform a work at height without tool tie, also supervisor is not present at the siteTank FarmRoad#07ConstructionCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2025-09-24Unsafe ActSlip/Trip/FallAt tank#05, during the safety round found the MS plate was not barricaded, creating a potential tripping and injury hazard. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-25
2025-09-25Unsafe ConditionSlip/Trip/FallAt tank#11, the main entrance of tank the corner of an MS plate was raised, creating a tripping hazard .informed to HSE supervisor and immediately remove tripping hazard.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-09-09
2025-09-25Unsafe ActWork at HeightAt tank#11, during reinforcement fit up using hammer tool tie was found damage. Informed to HSE supervisor and immediately change tool tieTank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-12
2025-09-25Unsafe ConditionHousekeepingAt tank#05, during the hot work activities and crane operation, tank yard surface not level and poor housekeeping ,informed to HSE supervisorTank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-12
2025-09-25Unsafe ActPPEAt tank#05, during the tank main hole box up, 2 fitters not wearing a safety gloves. Informed to HSE supervisor and workers counseling.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-07-12
2025-09-25Unsafe ConditionEquipmentAt tank#05, during the fabrication work change cutting disk, grinder lock not working. informed to HSE supervisor immediately change the grinder.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-12
2025-09-25Unsafe ConditionProcedureAt ATL workshop, filled gas cylinders were stored lying on each other, which is unsafe and may cause leakage or cylinder damage. Informed to HSE supervisor.Tank FarmATL workshopConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-12
2025-09-25Unsafe ConditionWork at HeightAt tank#05, loose materials were scattered on the permanent /temporary platform, creating a potential tripping and falling hazard. Informed to HSE supervisor.Tank FarmTank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-26Unsafe ActSlip/Trip/FallAt tank#05, loose materials were scattered on the permanent /temporary platform, creating a potential tripping and falling hazard. Informed to HSE supervisor.Tank FarmTank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-09-26Unsafe ActPPEAt tank #11, during fabrication work, one fabricator was not wearing a safety glove. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-09-26Unsafe ConditionLine of FireAt tank # 11, sparks from the grinder were hitting to another worker. Informed to HSE lead.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-09-26Unsafe ActLack of SupervisionAt tank # 05, during the crane operation, 01 worker was crossing the barricaded area. Informed to HSE supervisor and counseling done.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-09-26Unsafe ActLack of SupervisionAt tank#11, during the safety round one worker harness does not hook. Informed to HSE Supervisor and immediately action.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-07Unsafe ActFalling ObjectAt tank#11, during the safety round, loose materials(cutting disk, channel pace ,planks etc.). were found on the scaffolding platform and tank roof ,creating a potential falling object or tripping hazard. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-07
2025-10-07Unsafe ConditionWork at HeightAt tank#11, during the safety round one worker harness does not hook. Informed to HSE Supervisor and immediately action.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-07Unsafe ConditionSlip/Trip/FallAt tank#05, during the safety round found the MS plate was not barricaded, creating a potential tripping and injury hazard. Informed to HSE supervisor.Tank FarmTank #5ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-13Unsafe ConditionSlip/Trip/FallAt tank # 05, the rope of the basket used for lifting material was found damaged. Informed to HSE supervisor and immediately replace the rope.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-07-12
2025-10-10Unsafe ConditionWork at HeightAt tank # 05, loose material was found scattered on the scaffolding plate form. Informed to HSE supervisor and immediately remove loos material.Tank FarmTank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-07Unsafe ActLack of SupervisionAt tank# 11, during hot work, welding and grinder sparks were falling on the green blanket which is a combustible material. Informed to HSE supervisor covered hot workplace with fire blanket.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2025-10-07Unsafe ConditionPTWAt tank # 05, Excavation work was in progress, but work permit was not present at site. Informed to HSE supervisor.Tank FarmTank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-10Unsafe ActLack of SupervisionAt tank # 05, the rope of the basket used for lifting material was found damaged. Informed to HSE supervisor and immediately replace the rope.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ActPPEAt Tank #5, during sand loading, workers were not wearing the required PPE such as masks and safety goggles. The HSE Supervisor was informed, and the workers were instructed to wear proper PPE.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ConditionLack of SupervisionAt Tank #11, during the pre-operation visual inspection, a damaged tire was observed on the crane. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ConditionLack of SupervisionAt Tank #11, during the pre-operation visual inspection, a damaged tire was observed on the crane. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ConditionLack of SupervisionAt Tank #11, during the pre-operation visual inspection, a damaged tire was observed on the crane. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ConditionHousekeepingAt Tank #11, poor housekeeping was observed. Sandblasting materials were scattered in the work area, creating slip and trip hazards. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ConditionSlip/Trip/FallAt Tank #11, loose materials were scattered on the scaffolding platform, creating a potential tripping and falling hazard. The HSE Supervisor and Site Supervisor were informed. (Waseem, Niazi).Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ActPPEAt tank #11,during sand blasting activities, workers were not wearing face masks.(N.95)informed to HSE supervisor and wearing a face mask.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ActPPEAt tank #11,during sand blasting activities, workers were not wearing face masks.(N.95)informed to HSE supervisor and wearing a face mask.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ActPPEAt tank #11,during sand blasting activities, workers were not wearing face masks.(N.95)informed to HSE supervisor and wearing a face mask.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-15Unsafe ActFalling ObjectAt tank #11,the portable air compressor was connected with an electrical plug while activity was stopped. Informed to HSE supervisor and immediately disconnect plug.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-07
2025-10-15Unsafe ActFalling ObjectAt tank #11,the portable air compressor was connected with an electrical plug while activity was stopped. Informed to HSE supervisor and immediately disconnect plug.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-07
2025-10-17Unsafe ConditionVehicleAt tank#11, an electrode box was lying on the scaffolding platform ,creating risk of falling. Informed to HSE supervisor and the electrode box was immediately removed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-21Unsafe ConditionEnvironmentAt tank#15, during the hot work activities found the fire Extinguisher were not available near the generator, informed to HSE person.Tank FarmTank #15ConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-21Unsafe ActWork at HeightAt tank #11, an ATL staff member was observed working on a high scaffolding platform without a chin strap and his safety harness not hooked. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-21Unsafe ConditionEnvironmentAt tank#05, during grinding work, no support was provided to hold the pipeline in position which could cause movement or vibration. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-22Unsafe ActPPEAt ATL yard during MS plate shifting and cleaning 1 worker not wearing a safety impact glove. Informed to HSE supervisor and use PPE,s as per job reequipments.Tank FarmATL YardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-22Unsafe ConditionWork at HeightAt tank#05 , during the fabrication work the crude line spool was temporarily supported on scaffolding pipes and cement block ,which is an unsafe and unstable method of support. Informed to HSE supervisor and use chain block.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-22Unsafe ConditionHousekeepingAt tank#11,the Air compressor tire was sent yesterday for puncture repair and has not been returned yet (till 11;00 A.M)and the Air compressor placed and supported on a small pipeline piece ,which is unsafe and unstable. Informed HSE sup.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-22Unsafe ConditionLack of SupervisionAt tank #05,different types of materials were lying scattered in the tank yard and not barricaded / poor housekeeping. Informed to HSE supervisor.Tank FarmTank #05LogisticCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-22Unsafe ConditionVehicleAt multiple locations (Near Kachra Kundi Road 4, access to tank 15 yard and opposite to weigh bridge), leftover material needs to be removed.KOR RefineryAt multiple locationsCivilPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionHousekeepingAt temporary M/s DEL fabrication yard, poor housekeeping was observed, such as leftover material, pipes, metallic sheets, plastic bags, cable rolls, etc., which need to be removed from the area.KOR RefineryDEL Fabrication YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ActPPEAt tank #11,during the material shifting one fitter was lifting a C-channel without wearing rigging gloves ,which poses a risk of hand injury. Informed HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionElectricalAt tank #11,during the safety round, one 3-phase female socket on the Electrical distribution board,(D.B) was found without a safety cover ,posing an electrical contact hazard. Informed HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionWork at HeightAt tank#05, during safety round different loose materials were present on the scaffolding plate form ,creating falling object hazard. Informed HSE supervisor and immediately remove loos materials.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ActWork at HeightAt tank#05,during work at height activities ,one hammer and two spanners were being used without tool tie. Informed to HSE supervisor and concealing done.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionVehicleAt At tank# ATL yard, the ambulance driver was driving other vehicles, and no standby driver was present for the ambulance. Informed HSE teem/ construction teem.Tank FarmAt tank#05 & ATL yardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionElectricalAt tank #11, during the safety, round and Electrical tool inspection one Electrical Extension bord Expire .informed to HSE supervisor and remove expire tool.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ConditionElectricalAt tank #11, during safety round, the ventilation fan installed at the tank did not have an electrical inspection tag. Informed to HSE supervisor immediately install electrical inspection tag.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-28Unsafe ActPPEAt tank#05,during the safety round, four fitters were manually lifting and shifting the pipeline  without wearing impact-resistant gloves. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-07-12
2025-10-30Unsafe ConditionHousekeepingAt the rotary workshop, several housekeeping and safety issues were observed: lube cans stored without secondary containment, an overflowing AC drain bucket, a cup of tea placed on the notice board, and improperly marked waste bins.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionElectricalElectrical cabling at the WMS office was found poorly managed, and a non-industrial extension board was in use, posing a risk of electrical hazardKOR RefineryWMS OfficeElectricalCONTRACTORWMSRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionHousekeepingAt WMS store, poor housekeeping was observed, including safety helmets and coveralls scattered on the floor, improper management of electrical cabling, broken almirah door,  and damage false ceiling, which poses a potential falling object hazard.Tank FarmWMS StoreOperationCONTRACTORWMSRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionElectricalAt the mobile workshop, an electrical distribution board was found open, posing a potential electrical safety hazard.KOR RefineryMobile WorkshopElectricalPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionHousekeepingAt mobile workshop, oil/ HSD drum found placed outside the secondary containment and some empty drum placed outside the workshop.KOR RefineryMobile WorkshopOperationPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionProcedureAt outside electrical workshop, oxygen cylinder was found with damage pressure gauges and hazardous material were scattered on the floor.KOR RefineryElectrical WorkshopElectricalPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionElectricalAt electrical workshop, improper stacking of material was observed.KOR RefineryElectrical WorkshopElectricalPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionProcedureEmpty paint cans were found dumped behind the contractor’s paint store. These should be properly disposed of at the designated location (Cargill scrap yard).Plant AreaAt 202 Air CoolerCivilPRLShutdownKorangi RefineryteamClosed2026-07-09
2025-10-30Unsafe ConditionEquipmentAt civil rest/change room, metallic almirah was found damaged at the bottom, posing a risk of collapse.KOR Refineryrest/changeCivilPRLRoutineKorangi RefineryClosed2026-07-12
2025-10-30Unsafe ConditionHousekeepingAt multiple points, poor housekeeping was observed (such as leftover materials, wooden pallets, plastic bags, and used cotton rags and cloths).KOR RefineryMultiple LocationsOperationPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionElectricalNear Electrical rest room, newspapers placed between the wires or inside the electrical distribution board can increase the risk of fire which needs to be removed.Tank FarmElectrical Rest RoomElectricalPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-30Unsafe ConditionEnvironmentAt scrap yard, poor waste management was observed (waste found mix), which needs to be properly segregated and dumped as per marking.KOR RefineryScrap YardStationaryPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-31Unsafe ConditionHousekeepingStagnant water was observed around the portable storage tanks used for office purposes. It may become a potential breeding source for mosquitoes, should be drained promptly.KOR RefineryKOR RefineryA&SPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActProcedureAt Road #1, M/s RE: A welder was observed working on the fire water line while a helper was sitting on the same line.KOR RefineryRoad #1StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActProcedureAt Road #1, M/s RE team was observed using a tarpaulin as a fire blanket during hot work activity.KOR RefineryREStationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActWork at HeightAt Tank #30, M/s DEL welder was observed descending from the roof while holding a harness hook in one hand and welding material in the other and failed to maintain three-point contact while using the stairs.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ConditionFalling ObjectAt Tank #30, M/s DEL worker was carrying out gas cutting on the tank roof, and sparks were observed falling outside through the D-door.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ConditionProcedureAt Tank #35, M/s IIW: Shuttering work was in progress, and wooden ballies were not properly stacked.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActElectricalAt the DEL yard fire canopy area, the area was found congested. Two workers were observed performing welding and grinding activities, with sparks falling on electrical cables, and the welder was also standing on the cables.KOR RefineryDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActProcedureAt Tank #35, M/s IIW shuttering work at the tank ring wall was in progress. The ramp was found red-tagged. However, workers were observed using it.KOR RefineryTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-14Unsafe ActLine of FireAt IIW Yard: A roller compactor was found without wheel chocks and with a damaged spark arrestor; ensure the wheels are properly chocked and the spark arrestor is correctly installed.KOR RefineryIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-15Unsafe ActWork at HeightAt tank 56, during scaffolding removal, M/s AJC worker was using a hammer without tool tie.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ConditionFalling ObjectAt tank 56, during welding activity, M/s AJC welder was wearing non-compatible clothing (Romal).Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ActProcedureAt tank 56, during welding activity, M/s AJC welder was wearing non-compatible clothing (Romal). At tank 56, a welding electrode desiccator and a water bottle were observed being lifted using only a rope, without a tool bag.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ConditionLine of FireAt tank 56, M/s AJC fire blankets showed poor heat resistance, grinding/ welding sparks caused visible burn holes through the material.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ActProcedureAn engine oil leak was observed on the 100 kVA generator operated by M/s AJC. Furthermore, no drip tray was provided to contain the spill.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ActProcedureAt tank 56, three scaffolders were working at height without having third-party certification.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-04-15Unsafe ActWork at HeightAt tank 56, a welding electrode desiccator and a water bottle were observed being lifted using only a rope, without a tool bag.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-03-15Unsafe ActLack of SupervisionAt tank 56, one scaffolder hooked the safety harness to a shell plate, which is not a proper anchorage point.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-03-25
2026-04-15Unsafe ConditionWork at HeightAt tank 56, during scaffolding removal, parallel grinding work was being carried out by one fitter.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-06-19Unsafe ActProcedureTank#30 M/s DEL, the flagman was observed walking alongside the moving trailer, disregarding safe clearance distances.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-19Unsafe ActHousekeepingM/s IIW Workshop area, poor housekeeping was found observed (tools, paper and plastic materials were observed near the gas cylinders).KOR RefineryIIW WorkshopConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActEquipmentTank#4 M/s IIW, there was no sitting arrangement for generator operator.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActEquipmentTank#4 M/s IIW, there was no sitting arrangement for generator operator.Tank FarmTank #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ConditionElectricalAt Tank #30 – M/S DEL: Electrical extension board cable was found damaged.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ConditionFalling ObjectTank#4 M/s IIW, Electrical cables were observed lying unprotected on the ground and exposed on the walkway.Tank FarmTank #04ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-06-19Unsafe ActEquipmentTank#4 M/s IIW, oil leakage was observed from the generator.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActProcedureAt DEL Yard: Poor housekeeping observed during safety round, need to clean the area.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActProcedureAt DEL Yard: MS sheets were found lying unsecured in front of the gas cylinder storage area.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActEnvironmentAt DEL Yard: Hazardous waste and recycle material are found mixed in the Bins; waste segregation is required and bins need to be emptied.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ConditionHousekeepingAt Tank #30 – M/S DEL: Grinders were observed placed on a steel plate instead of being stored in the designated grinder stand.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ActProcedureAt Tank # 30: M/s DEL worker was observed not maintaining a 3-point contact while using the stairs.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ConditionFalling ObjectAt Tank #30 – M/S DEL: During stairs steps build-up activities, sparks were observed falling to ground.Tank FarmTank #30ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ConditionEnvironmentAt DEL Yard: Hazardous waste and recycle material are found mixed in the Bins; waste segregation is required and bins need to be emptied.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ActPPEAt Tank # 35: Supervisor (Bilal) was observed not wearing safety goggles continuously during work activities.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ActPPEAt Tank #21 – M/S DEL: Worker was not wearing safety gloves and was not following the three-point contact rule while using stairs.KOR RefineryTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ActPPEAt Tank # 35: a steel fixer was working without wearing a protective glove during the task.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-06-19
2026-06-22Unsafe ConditionProcedureAt Tank 21: A knotted lifting rope was found in use during lifting activities.KOR RefineryTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-22Unsafe ActProcedureAt Tank 21: Three M/s DEL worker hook harness at the same lifeline.KOR RefineryTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-08Unsafe ConditionElectricalAt Tank #56,M/s AJC, the main electrical changeover handle was missing and was being operated using plier.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-22Unsafe ConditionHousekeepingAt Tank 30: welding plant was placed on metal wedges and supporting by splash plate hanger.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-08Unsafe ConditionElectricalAt Tank #56, M/s AJC, gas cylinders were being used without tying with chains and the fire blanket was also damaged.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-22Unsafe ConditionHousekeepingAt Tank 21: The existing davit arm and its winch had been inspected and certified by a third party. However, the old davit arm was removed and replaced with a new davit arm that had not been load tested or certified by a third party.KOR RefineryTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-08Unsafe ActWork at HeightAt Tank #56, M/s AJC, a scaffolder has hooked his harness onto the shell plate, which was not a designated anchor point.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-08Unsafe ActElectricalAt Tank #56, M/s AJC, during scaffolding modification, the RED tag was not displayed. Additionally, a rigger was using the same platform, which had damaged and broken planks.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-24Unsafe ConditionProcedureAt Tank 25 Yard: Substandard pipe supports (wooden pieces) were being used to support the newly installed pipeline. Additionally, no proper walkway or crossover arrangement was provided for safe access across the pipeline.KOR RefineryTank #25StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-08Unsafe ConditionFalling ObjectAt Tank #56, M/s AJC, a tool bag was found damaged.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-07
2026-04-08Unsafe ConditionElectricalAt Tank #56, M/s AJC, the main electrical cable was observed exposed above ground level.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-08Unsafe ActLack of SupervisionAt KT foam tank, M/s AKS , during scaffolding installation, workers were not using tool bag.Tank FarmTank #56ConstructionCONTRACTORAKSRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-24Unsafe ActProcedureAt Tank 30 & at DEL Yard, during spool piece facing, the worker was holding the spool piece by hand instead of securing it in a vice.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-24Unsafe ActWork at HeightAt Tank #04, M/s IIW during scaffold dismantling activities, two scaffolders were observed working without hooking their safety harness lanyards.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-09Unsafe ConditionWork at HeightAt tank 30, The railing supporting the lifeline scaffolding pipes is fragile. It needs to be repaired before proceeding with the next activity.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-09Unsafe ConditionWork at HeightAt tank 30, M/s DEL workers are walking directly on the roof, whereas it was agreed that they would place scaffolding planks and move over them.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-24Unsafe ConditionWork at HeightAt the DEL Yard, M/s DEL. scaffolding materials, including oversized pipes, were being transported by forklift. The pipes were not tied down during the lifting and shifting operation.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-25Unsafe ConditionFalling ObjectTank #30 M/S DEL, sparks observed falling on ground during steps build up activity.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-09Unsafe ActProcedureAt tanks 21 and 30, during hot work on the roof, only a welding blanket was tied to the railing, whereas it was agreed that a proper welding canopy would be provided wherever hot work is carried out.Tank FarmTank # 21 & 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ActProcedureAt Tank #21 – M/S DEL: During welding activities, sparks were observed spreading outside the work area.Tank FarmTank #21ConstructionCONTRACTORDELRoutineKorangi RefineryteamClosed2026-07-11
2026-04-09Unsafe ActLine of FireAt Tank #30, during hot work arrangements, workers were crossing over product lines and sprinkler lines.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-23Unsafe ActEquipmentAt Tank #56, M/s AJC. the generator operator was absent from the worksite.KTAt Tank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-09Unsafe ActWork at HeightAt Tank #04, one worker was observed sitting on a scaffolding pipe.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-20Unsafe ConditionSlip/Trip/FallAt Tank #21, M/s DEL. Roof plates were lying on the walkways, creating a tripping hazard.KOR RefineryTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionPTWAt the DEL yard, maintenance work was being carried out without having permit and dropping of oil was also observed.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-27Unsafe ActProcedureAt Tank #11, structure material was found on walkway without barrication.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionProcedureAt Tank 21, the cut/open section of the roof was found without barrication.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-27Unsafe ActPPETANK# 04  M/S IIW, rigger was using damaged gloves.KOR RefineryTANK# 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ActPPETank #11: Worker was not wearing safety gloves during civil work.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-27Unsafe ConditionFalling ObjectTANK# 04  M/S IIW,  during gas cutting on the shell, sparks were falling to the area below.KOR RefineryTANK# 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionProcedureTank #11: GI sheet was lying on the ground, creating a tripping hazard and risk of sharp-edge injury.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-27Unsafe ActWork at HeightTANK #11 M/S ATL,  Workers were found working on red tagged scaffold during dismantling activities.KOR RefineryTANK #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ActPPETank #11: Electrical work on a live Distribution Board (DB) was carried out without safety gloves, and improper tool handling/bag was observed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-27Unsafe ActProcedureAt Tank #05, while performing hot work activity, M/s ATL team was not properly build a canopy.KOR RefineryTANK# 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ActPPETank #21: Civil Supervisor and HSE Supervisor were wearing unapproved safety helmets (not compliant with PRL standards).Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-27Unsafe ConditionElectricalTANK # 30 M/S DEL, damaged welding cable that had been repaired with electrical tape was being used.KOR RefineryTANK# 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-04-10Unsafe ActPPETank #21: Civil workers were not wearing face masks during work.Tank FarmTank #21ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-15Unsafe ConditionPPEM/S DEL Yard: One gas cutting operator was working without gloves, and another worker was wearing damaged gloves.Tank FarmDEL YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-10Unsafe ConditionProcedureTank #04: A scaffolding plank on the main walkway was improperly placed, creating a tripping hazard.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-15Unsafe ActPPEAt the DEL M/s DEL. Yard, during testing activities, a welder was found not wearing a welding safety helmet and was using an unapproved safety helmet.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-04-10Unsafe ConditionWork at HeightIIW Yard: Diesel storage area was not properly contained.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-15Unsafe ActProcedureTank #4 – M/S IIW: During crane activity, the rigging supervisor was not present at the worksite.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-04-10Unsafe ConditionHousekeepingIIW Yard: Gas cylinder was improperly placed and not tagged.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ActPPEIIW Yard: Worker was filling diesel without wearing proper PPE.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-06-15Unsafe ActProcedureTank #21 – M/S DEL: A worker was wearing a damaged coverall and had used banding wire to tie the sleeves.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionWork at HeightIIW Yard: Scaffolding materials were not stacked properly.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-07Unsafe ConditionPPEAt tank #05 , during the scaffolding materials shifting one worker not wearing a safety gloves, informed to HSE supervisor counseling done.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2026-06-16Unsafe ConditionProcedureMCP boiler  Utility area  paint required. And fire hydrant Isom boiler area and power house all hydrant paint required.Tank FarmMCP boiler  Utility area CivilCONTRACTORPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-16Unsafe ConditionProcedureRoad 01 and 06 safety sign board broken condition.Tank FarmRoad 01 and 06StationaryCONTRACTORPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-17Unsafe ConditionFalling ObjectAt Tank #04, M/s IIW: During gas-cutting work, sparks were observed falling onto dry grass. All combustible materials should be removed from the work area prior to the commencement of hot work activities.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-17Unsafe ConditionWork at HeightAt Tank #30, M/s DEL: The roof railing was found detached from the tank structure. A lifeline was observed anchored to a scaffolding pipe fixed to the unstable railing.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-17Unsafe ConditionFalling ObjectAt Tank #30, M/s DEL: The fire blanket was found damaged and sparks were observed falling through the Tank D door opening.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-17Unsafe ActProcedureAt Tank #30, M/s DEL: Workers were observed wearing damaged, loose-fitting coverall. Some workers were also found wearing PRL’s non-approved coveralls.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-18Unsafe ActPPEAt DEL yard and at tank #30 M/s DEL worker was found wearing damaged welding shoes and mechanical supervisor was working without safety gloves.Tank FarmDEL yard and at tank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionProcedureTank #35: Permanent stair railing was damaged.KOR RefineryTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActElectricalTank #11: M/s ATL worker was observed sitting on an energized extension board.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-18Unsafe ActPPEAt tank #30 and at tank #21, M/s DEL workers were found wearing damaged coverall, with rolled-up sleeves and loose-fitting coveralls and some workers were also found wearing PRL’s unapproved safety helmets.Tank FarmTank #30 & 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-18Unsafe ActPPEAt tank #30, M/s DEL welder was found working without wearing helmet and found wearing damaged welding gloves.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-18Unsafe ConditionProcedureAt tank #30, M/s DEL: Improper placement of sharp-edged plates was observed.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ConditionProcedureTank #11: Tarpaulin was used as a fire blanket, which is not fire-resistant.8KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-18Unsafe ConditionElectricalAt tank #21, M/s DEL: Poor cable management was observed.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActPPETank #11: M/s ATL workers were performing simultaneous operations (SIMOP) (welding in the upper area and cleaning work in the lower area).KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActPPETank #30: M/s DEL worker used the stairs without wearing a chin strap and without gloves.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-18Unsafe ConditionElectricalAt tank #30, tank #2 and at M/s DEL yard: Electrical DBs and extension boards receptacle caps were found damaged/ missing.Tank FarmTank #30 & 02ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActPPETank #30: M/s DEL generator operator was working without wearing gloves, safety goggles and hearing protection.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-18Unsafe ConditionEnvironmentNear M/s ATL yard: Drums containing combustible materials were found overloaded, needs to be removed.Tank FarmNear M/s ATL yardConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ActProcedureAt Tank #04, M/S IIW worker was found working on the top platform without hooking his safety harness.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ConditionSlip/Trip/FallTank #4: Scaffolding plank was found on the main walkway, creating a tripping hazard.Tank FarmTank #4ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-06-19Unsafe ConditionProcedureAt Tank #04, M/S IIW, the gas cylinders were not covered with a fire blanket.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ConditionWork at HeightDEL Yard: Worker sitting under an incomplete, red-tagged scaffolding shade.Tank FarmDEL YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-19Unsafe ConditionProcedureAt Tank #04, M/S IIW, during crane operation, one side of the work area was not barricaded.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActProcedureDEL Yard: Worker was found wearing two-piece coverall.Tank FarmDEL YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-19Unsafe ConditionHousekeepingNear Tank #32, M/S N.H, poor housekeeping was observed, leftover materials needs to be removed.Tank FarmTank #32ConstructionCONTRACTORNHRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-11Unsafe ActLack of SupervisionTank #4: The generator operator was sitting near running equipment without hearing protection.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-06-19Unsafe ConditionProcedureAt Tank #21, M/s DEL, during stair repair work, the hot work area was not covered with a fire blanketTank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-31Unsafe ConditionEquipmentAt tank # 55, a hose pipe hanging form the roof of tank which needs to be removed.  KTTank #55OM KTPRLRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-10Unsafe ActWork at HeightAt Tank #56, M/s AJC, welder was found working at height without hooking his safety harness hook.KTTANK# 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-07-09
2025-10-31Unsafe ConditionProcedureBottom pad of tank # 55 found damage needs to be repaired to avoid further deteriorate.Tank FarmTank #56CivilPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionEquipmentAt  DEL yard M/s DEL, during a safety visit, it was observed that the gas cutter was neither properly closed nor in working condition. However, the gas supply was left open through the regulators, and the equipment was not covered with a fire blanket.KOR RefineryDeConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-04-05Unsafe ConditionWork at HeightAt  DEL Yard, M/s DEL, scaffolder working on pipe without proper planks.KOR RefineryDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-07-09
2025-10-31Unsafe ConditionProcedureAt multiple locations (KT) inside the tank yards and along the roads, wild bushes have grown which needs to be removed. The removal activity by the civil team was in progress. However, the team was requested to expedite the job.KTMultiple LocationsCivilPRLRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-05Unsafe ActPPEAt  Tank #11, M/s ATL ,Worker’s -welding/grinding without dust masks and earplugs.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-08Unsafe ActPPEAt the DEL Yard, during grinding work, a worker was observed wearing a scarf wrapped around his head.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionProcedureAt  Tank #35, M/s IIW ,material trolley found without stoppers.KOR RefineryTANK# 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-08Unsafe ActPPEAt Tank #04, some workers of M/s IIW were using damaged rigging gloves.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActWork at HeightAt  Tank #04, M/s IIW , workers manually handling 20 ft 2 scaffolding pipes.KOR RefineryTANK# 04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-08Unsafe ConditionHousekeepingAt tank#35, diesel-filled jerry cans were found stored outside the secondary containment area, as the designated containment area was already occupied with drums.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActPPEAt  Tank #35, M/s IIW, supervisor not wearing safety goggles during civil work.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-06-11Unsafe ActWork at HeightAt tank #04: A mobile scaffold was relocated with an M/s IIW worker still standing on it.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionProcedureAt  Tank #30, M/s DEL, miller stand was found road#04 without stoppers.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-11Unsafe ConditionProcedureAt tank #04: During gas cutting activity, M/s IIW rigger was standing beneath the hot work area.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActProcedureAt  Tank #11, M/s ATL ,welding done without following confined space entry procedure.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-11Unsafe ConditionWork at HeightAt tank #04: while holding a C-channel, M/s IIW worker was observed on scaffolding without wearing a safety harness.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-11Unsafe ActPPEAt tank #21: M/s DEL worker was observed wearing damaged rigging gloves.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionProcedureTank#56,M/s AJC, during crane operations at Tank #56, no safety personnel was present at the site.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-11Unsafe ActProcedureAt tank #30: A welder was performing welding work without wearing welding shoes.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActLine of FireTank#56,M/s AJC, during crane operations, one fitter entered the fire line zone, which is unsafe.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActPPEAt road #4, during crane activity, M/s DEL workers were observed not wearing approved safety helmets and safety shoes. Additionally, the rigging supervisor was not wearing a PRL-approved coverall.Tank FarmRoad #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionEquipmentTank#56,M/s AJC, the generator (200 KVA) distribution board (DB) door was found open/not properly closed.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-12Unsafe ConditionProcedureAt tank #30, during crane operations, gas cylinder of M/s DEL was found within the crane boom radius.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActProcedureTank#56,M/s AJC, during fit-up activities, U-type fittings were not secured with a safety chain.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActProcedureAt tank #30, M/s DEL workers were observed crossing over pipelines instead of using proper passage.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-05Unsafe ConditionProcedureTank#56,M/s AJC, Loose materials (fit-up fittings) were not properly segregated or barricaded.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-12Unsafe ConditionProcedureAt Tank #30, during the inspection of the crane and lifting gears, two 8-ton shackles were found without valid third-party inspection certificates.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionElectricalTank#56,M/s AJC, A damaged receptacle was observed on the electrical board.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-12Unsafe ConditionProcedureAt Road No. 01, during work in a temperature of 34°C, workers were not provided with sweet drinking water or cold water.Tank FarmRoad No. 01ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ActProcedureTank#56, M/s AJC, during back grinding work on a temporary platform, a loose/unfixed stool was used, which is unsafe.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ConditionEquipmentAt Road No. 01, diesel was being filled into the generator without a pump.Tank FarmAt Road No. 01,ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-13Unsafe ActPPEM/S DEL Yard: One gas cutting operator was working without gloves, and another worker was wearing damaged glovesTank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-05Unsafe ConditionWork at HeightTank#56,M/s AJC, A grinder was being lifted using a rope tied to it outside the tank area, which is unsafe.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-13Unsafe ConditionElectricalM/S DEL Yard: A worker was using a damaged welding cable.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-13Unsafe ConditionLack of SupervisionTank #4 – M/S IIW: During crane activity, the rigging supervisor was not present at the worksiteTank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-13Unsafe ConditionEnvironmentTank #4 – M/S IIW: During the soap test, gas leakage was found from the cylinder regulators.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-13Unsafe ActProcedureTank #21 – M/S DEL: A worker was wearing a damaged coverall and had used banding wire to tie the sleeves.Tank FarmTank #21ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-13Unsafe ConditionProcedureTank #4 – M/S IIW: During crane activity, a gas cylinder was found within the crane boom radius.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-04Unsafe ConditionProcedureAt Tank 35 (M/S IIW), A damaged wheelbarrow was found using by worker.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-06-03Unsafe ConditionSlip/Trip/FallTank #04:M/s IIW. MS plates were lying scattered in the yard, creating a tripping hazard.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-03Unsafe ConditionProcedureTank #04: M/s IIW.  During crane movement flagman was found without flag.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-03Unsafe ConditionHousekeepingTank #04: M/s IIW.  During crane operations, a gas cylinder trolley was placed within the barricaded area.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-03Unsafe ActPPETank #04: M/s IIW.  Workers were observed using damaged safety gloves.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-03Unsafe ConditionSlip/Trip/FallTank #21: M/s DEL. The 50 KVA generator was repeatedly tripping when load was applied and requires inspection and corrective action.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionProcedureAt Tank #04, oil traces were observed near the hot work activity area.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionProcedureAt Tank #04, during crane movement, sub-standard flag was being used for signaling.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ActPPEAt Tank #04, some workers were using PRL’s unapproved safety gloves.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionProcedureAt Tank #04, a loaded dumper was moving on Road No. 16 without a flagman.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionProcedureAt the IIW Yard, during ambulance inspection, the low-fuel warning indicator was ON and the fuel gauge showed empty.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionHousekeepingAt the IIW Yard, MS plates were found lying in the fabrication yard without barricading, creating a safety hazard.Tank FarmIIW YARDConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionHousekeepingAt the IIW Yard, gas cylinders in the storage area were found without securing chain.Tank FarmIIW YARDConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-04Unsafe ConditionEquipmentAt Tank #30, diesel leakage was observed from the lift pump of a 100 KVA generator.Tank FarmTank #30ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-06Unsafe ActLack of SupervisionM/s DEL yard, during welding activity, wielding supervisor was wearing non-compatible clothing (Romal).Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-06Unsafe ConditionElectricalM/s DEL yard, a welding lead was found damaged, the receptacle cap of an extension board was missing, a waste bin was overflowing and poor cable management were observed.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-06Unsafe ConditionWork at HeightTANK 21 M/S DEL; housekeeping was observed (bitumen, scaffolding materials and waste materials were found scattered in work area) and receptacle caps of distribution box were missing.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-06Unsafe ActFalling ObjectTank #56, during wind girder fit-up work, M/s AJC worker was using a hammer without a tool tieTank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-06Unsafe ConditionProcedureAt Tank #56, M/s AJC, during hot work activities, the area outside the tank shell was not covered with a fire blanket.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-06Unsafe ConditionProcedureAt Tank #56, M/s AJC, during crane operations, electrical fault was identified due to a fuse issue.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-18Unsafe ConditionProcedureAt tank#04, M/S IIW, during crane operation, an unbalanced load was being lifted. Counseling was conducted for the riggers and crane operator.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-18Unsafe ActPPEAt Road #16, M/s NH Construction, one steel fixer was observed not wearing a safety helmet and safety goggles. Another worker was wearing damaged safety shoes, while one supervisor was observed wearing low-ankle safety shoes.Tank FarmRoad #16ConstructionCONTRACTORNHRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-18Unsafe ConditionProcedureAt tank#21,M/S DEL, Crane operation was being carried out at the site without proper area barricading.Tank FarmTank #04ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-18Unsafe ConditionSlip/Trip/FallAt Tank #04, M/s IIW, plate laying was found in an unbalanced condition with sharp edges, creating trip hazards.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-18Unsafe ConditionLine of FireAt Tank #30, M/S DEL, during hot work, sparks were spreading outside the work area.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-19Unsafe ConditionProcedureAt boiler # 03,  two open pits were observed without proper covering; immediate covering is required.Tank FarmTank #03StationaryCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-19Unsafe ConditionHousekeepingTank # 56 (M/s AJC), poor housekeeping was observed in the work area. face shield, face masks, bending wires , and poorly managed cables around the workplace, creating slip and trip.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-19Unsafe ConditionProcedureTank # 56 (M/s AJC) ,during wielding activity inside tank, the work area was not adequately barricaded, allowing uncontrolled access and creating a potential safety hazard for personnel.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-19Unsafe ConditionPPETank # 56 (M/s AJC) , a worker was observed working at height without using a tool tie, in addition, proper three-point contact was not maintained during movement, increasing the risk of fall and dropped objects.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-19Unsafe ActElectricalTank # 56 (M/s AJC) , electrical extension board cable was found loose from gland side, which may increase the risk of exposed wiring and risk of electric shock or fire. Immediate removed from the site. Proper tightening and securing are required.KOR RefineryTANK #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-19Unsafe ActPPETank # 56 (M/s AJC), several workers were observed not wearing safety goggles ,while other were using unclear (foggy / blurry) goggles, reducing eyes protection, some workers found working without gloves and other were wearing inappropriate gloves , in addition several workers were using damaged safety shoes.  Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-19Unsafe ConditionEquipmentAt Tank #30,M/s DEL, a 100 KVA generator was found leaking oil during operation.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-19Unsafe ConditionProcedureAt Tank #04, M/s IIW, hot work activities were being carried out outside the tank without a safety canopy.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-19Unsafe ActWork at HeightAt Tank #04, M/s IIW, scaffolding materials were being lifted without using a bucket.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-19Unsafe ConditionEquipmentAt Tank #04, M/s DEL,  a 25 KVA generator was found in operation without an operator present.Tank FarmTank #04ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-22Unsafe ConditionProcedureAt junction of Road no. 3 & 6: convex mirror found detached from pole, re-fix the convex mirror onto the pole.Tank FarmRoad no. 3 & 6StationaryCONTRACTORStationaryRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-24Unsafe ActWork at HeightTank#4 M/S IIW, the gas cutting operator was observed performing the task while standing on the scaffolding top rail.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-24Unsafe ConditionProcedureM/S IIW, while work in progress, paramedic or ambulance driver were not available.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-24Unsafe ActLack of SupervisionTank #21 M/S DEL , the safety supervisor was not present at the worksite.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-23Unsafe ConditionSlip/Trip/FallTank#4 M/S IIW, workers coveralls were found damaged due to welding sparks, and some workers were observed wearing coveralls without reflective strips.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-23Unsafe ConditionFalling ObjectTank#4 M/S IIW, MS plates, pipes and angles were found on walkway.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-31Unsafe ConditionProcedureAt multiple location (tank yard # 55 & 53), oil traces were observed. The areas need to be properly dressed up and cleaned.KTTank 55 & 53OM KTPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ConditionProcedureAt tank yard # 55, some left civil debris found, needs to be removed.KTTank #55CivilPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ConditionFalling ObjectAt the civil store, poor stacking of materials was observed. Proper stacking is required to prevent objects from falling.KTKTCivilPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ActProcedureAt workshop, oil can was found without secondary containment.KTKTOM KTPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ConditionProcedureThe walkway leading to Tank Yard 57 from Road 3 was obstructed by wild bushes.KOR RefineryTank Yard 57CivilPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-31Unsafe ConditionHousekeepingPoor housekeeping was observed behind the fire water pump house, scrape needs to be dump at designated location.KTKTOM KTPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ConditionProcedureAt Road 3, sandblasting grit was found exposed to the open air and scattered on the surface. It needs to be properly collected and stored.KTKTOM KTPRLRoutineKemari TerminalteamClosed2026-07-13
2025-10-31Unsafe ConditionEnvironmentAt the workshop, mixed waste was observed in a single bin. Waste needs to be disposed of separately as per the markings on the binsKTWorkshopOM KTPRLRoutineKemari TerminalClosed2026-07-13
2025-10-31Unsafe ConditionProcedureAt multiple locations, some civil cracks were observed, needs to be repaired.KOR RefineryMultiple LocationsCivilPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-30Unsafe ConditionProcedureAt road # 12, road found damage which needs to be repaired to avoid further deteriorate.KOR RefineryRoad 12CivilPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-30Unsafe ConditionHousekeepingAt multiple locations ( near local decanting, near ISOM), poor housekeeping was observed.KOR RefineryMultiple LocationsA&SPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-30Unsafe ConditionProcedureAt road # 10 electrical sub-station, wild bushes found with transformer which needs to be removed.KOR RefineryRoad 10CivilPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionEnvironmentAt scrap yard, poor waste management was observed (waste found mix), which needs to be properly segregated and dumped as per marking.KOR RefineryScrap YardCivilPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionProcedureNear Electrical rest room, newspapers placed between the wires or inside the electrical distribution board can increase the risk of fire which needs to be removed.KOR RefineryElectrical Rest RoomElectricalPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionProcedureA wooden piece was observed misaligned between the support and the fire water pipeline for Hydrant #12, potentially affecting the pipeline’s support and integrity.KOR RefineryHydrant 12StationaryPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionElectricalAt electrical workshop, single drum is being used for dumping waste without any marking.KOR RefineryWorkshopElectricalPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionSlip/Trip/FallAt electrical workshop, improper stacking of material was observed.KOR RefineryWorkshopElectricalPRLRoutineKorangi RefineryClosed2026-07-13
2025-10-29Unsafe ConditionProcedureAt electrical workshop, improper stacking of material was observed.KOR RefineryElectrical WorkshopElectricalPRLRoutineKorangi RefineryClosed2026-06-24
2025-10-29Unsafe ConditionElectricalAt outside electrical workshop, oxygen cylinder was found with damage pressure gauges and hazardous material were scattered on the floor.KOR RefineryWorkshopElectricalPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-29Unsafe ConditionEnvironmentAt mobile workshop, oil/ HSD drum found placed outside the secondary containment and some empty drum placed outside the workshop.KOR RefineryMobile WorkshopOperationPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-30Unsafe ConditionSlip/Trip/FallAn empty lube oil drum was found placed in front of Hydrant #11, obstructing access and creating a potential safety hazard.KOR RefineryHydrant # 11CivilPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-30Unsafe ConditionHousekeepingAt WMS store, poor housekeeping was observed, including safety helmets and coveralls scattered on the floor, improper management of electrical cabling, broken almirah door,  and damage false ceiling, which poses a potential falling object hazard.KOR RefineryWMS StoreCivilPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-10-30Unsafe ConditionElectricalElectrical cabling at the WMS office was found poorly managed, and a non-industrial extension board was in use, posing a risk of electrical hazardKOR RefineryWMS OfficeConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-27Unsafe ConditionProcedureAt Tank #05, unavailability of HSE officer was observed during hot work activity.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-07Unsafe ConditionLack of SupervisionAt Boiler #01, the ventilation system was initially unavailable during the confined space tube replacement job but was promptly arranged after informing the Stationary Supervisor.Plant AreaBoiler #01StationaryCONTRACTORSWIFTRoutineKorangi RefineryClosed2026-06-24
2025-11-07Unsafe ConditionPPEAt boiler # 01,during the confined space tube replacement job, confined space entry log sheet was not available. Informed HSE supervisor.Plant AreaBoiler # 01ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-10-29Unsafe ActPPEAt tank #05 , during the scaffolding materials shifting one worker not wearing a safety gloves, informed to HSE supervisor counseling done.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-07Unsafe ActLack of SupervisionAt Tank #11, parallel activities were observed during the wind guard reinforcement work. The HSE Supervisor was informed, and safe distance was ensured.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-13
2025-11-05Unsafe ActLack of SupervisionAt tank#11,One welder’s coverall was damaged, which may lead to injury or fire hazard during welding activities. Informed to HSE Supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-05Unsafe ActElectricalAt tank#11,The ventilation fan’s wire dressing was not done properly, leaving cables in a disorganized and unsafe condition. Informed to HSE supervisor.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2025-11-16Unsafe ActPPEAt tank # 05, during confined space cleaning work, workers were not wearing safety goggles. Informed to SBM and wearing PPEs as per job requirements.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-16Unsafe ConditionElectricalAt tank # 05, during the hot work , the electrical cable was not properly organized. Informed to HSE supervisor.KOR RefineryAt Tank # 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-14Unsafe ActProcedureAt tank # 05, ATL worker was not wearing safety gloves while closing the Electrical cables. Informed HSE Lead.KOR RefineryTANK# 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-16Unsafe ConditionHousekeepingAt tank # 11, during the safety round poor housekeeping was observed at the back side of the tank. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-08-23
2025-11-16Unsafe ConditionHousekeepingAt Tank #11, loose material was found on the scaffolding platform. The HSE supervisor was informed and the loose materials were removed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2025-11-14Unsafe ActPPEAt tank #11, ATL worker not wearing a safety goggle at workplace. Informed to HSE supervisor.Tank FarmTank #11ElectricalCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-13Unsafe ActProcedureAt tank # 05, SGS inspectors entered the confined space for a calibration without having a valid confined space medical fitness test. Informed to Construction team.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-13
2025-11-13Unsafe ConditionWork at HeightAt tank #11,during the welding work found the welding cable was damaged. Informed to HSE supervisor and immediately replace the welding cable.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-13Unsafe ActWork at HeightAt tank #11, mechanical work at height started without HSE personnel present and without supervision. Informed to Construction team.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-13
2025-11-13Unsafe ConditionElectricalAt tank #11, during welding work, the male and female joints of the welding cable were found melted. Informed HSE supervisor and immediately replace.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-10Unsafe ActElectricalAt tank#11, ATL workers during tank inside grinder machine using not wearing an ear plug .informed the HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-10Unsafe ConditionLack of SupervisionAt tank#05,The ATL crane performed a lifting operation ,but after it went out of order, Mr. Sankar sb. PRL did not inspect it. Informed HSE supervisor.Tank FarmAt Tank#05ConstructionPRLRoutineKorangi RefineryClosed2026-06-24
2025-11-10Unsafe ConditionWork at HeightAt tank #05, scaffolding was installed for lifting and holding the valve, but the inspection tag was not attached. Informed HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-10Unsafe ConditionLack of SupervisionAt tank #05,the workers removing water from the confined space were not wearing gum boots ,informed Mr. Usman sb and HSE supervisor.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-10Unsafe ConditionSlip/Trip/FallAt tank #05,sacaffolding material is scattered ,not barricaded ,and it is a tripping hazard .informed HSE supervisor.Tank FarmAt Tank #05ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-10Unsafe ConditionProcedureAt Tank #05, the mesh in front of the ventilation fan was damaged. informed to HSE supervisor and Mr. Usman sb.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-12Unsafe ConditionHousekeepingAt road 6, the manifolds of tanks 15, 18, 19, 22 and 23 are blocked due to hard barrication around the excavation area and metal planks have not been placed for access to the manifolds.KOR RefineryRoad #6ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-17Unsafe ConditionLack of SupervisionAt tank # 11, during confined space mechanical work, the ventilation system was not being used. Informed to HSE supervisor.Tank FarmAt Tank # 11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-17Unsafe ConditionVehicleAt tank # 05, flagman was not available for the movement of heavy vehicle (concrete mixture machine). Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-17Unsafe ConditionHousekeepingAt tank # 05, grinder was found placed on surface instead of stand. Informed to HSE supervisor.KOR RefineryTANK# 5ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-07-09
2025-11-18Unsafe ConditionFalling ObjectAt Tank 5, access to the confined space is posing a falling hazard due to excavation.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-23Unsafe ConditionProcedureTank#4 M/S IIW, the material shifting trolley rear site tire was found damaged.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-23Unsafe ConditionLine of FireTank#30/21 M/S DEL, welding sparks were spreading outside the tank.Tank FarmTank #30 & 21ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-05-12Unsafe ConditionFalling ObjectAt Tank #56, during hot work activities, parallel activities were observed and sparks were falling to ground where the hot work area was not properly covered.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2025-11-18Unsafe ConditionEquipmentAt tank 5, grinder stand was not available at the site. The HSE supervisor was informed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-12Unsafe ActProcedureAt Tank #56, during welding work at the D-door, burned spots were found on the welder’s coveralls and he was not using a welding apron or safety sleeves.Tank FarmTank #30StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2025-11-18Unsafe ConditionPPEAt tank 5, Parallel activities were observed, welding work in the upper area and scaffolding modification in the lower area. The activities were stopped immediately and the team was counseled at the site.KOR RefineryTANK #5ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-12Unsafe ActProcedureAt Tank #56, during the lifting operation, the rigger was handling the suspended load by hand and the signalman was not wearing a safety jacket.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2025-11-18Unsafe ActPPEAt tank 11, parallel activity was observed, welding work on above area and scaffolding modification in below area. Immediately stopped the activity and counseling of team was done at site.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-12Unsafe ConditionProcedureAt Tank #56, the gas cutter regulator gauge glass was found missing.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2026-05-12Unsafe ActProcedureAt Tank #56, during the lifting operation while removing the shackle, the rigger had hooked his harness onto the shell plate.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2025-11-18Unsafe ConditionProcedureAt Tank 11, out of the two exhaust fans, one was found out of order.Plant AreaTank #11ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2026-07-09
2025-11-18Unsafe ActProcedureAt Tank #11, operating handle of fire extinguisher was found damaged. HSE supervisor was informed.KOR RefineryAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ConditionHousekeepingAt M/s IIW yard, gas cylinders weren’t protected with fire blankets during gas cutting work and the gas cylinders were placed nearby hot work area.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ActElectricalAt M/s IIW yard, a worker was observed performing grinding work without wearing earplugs.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ConditionProcedureDuring nozzle cutting activities at Tank #04, it was observed that M/s IIW had not properly cleaned the sludge from the inside of the nozzle.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ConditionElectricalDuring reinforcement installation at Tank #04, it was observed that the welding earthing lead used by M/s IIW was damaged.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ConditionSlip/Trip/FallDuring hot work and fit-up activities at the bottom of Tank #04, housekeeping was found to be inadequate. Various materials, including welding eyes, wedges, U-clamps, and C-channels, were left scattered across the work area, creating tripping hazard.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-14Unsafe ActPPEM/s IIW welder at Tank #04 was found wearing a cloth mask during welding work.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-19Unsafe ConditionEnvironmentAt Tank #11, unavailability of waste bin was observed. HSE supervisor was informed.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-15Unsafe ConditionProcedureAt Tank #4, reflective tape was found detached from the coveralls of several workers of M/s IIW.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-15Unsafe ConditionLine of FireAt Tank #04, during MS plate laying activities, sparks were observed outside the canopy area.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-19Unsafe ConditionElectricalAt Tank #11, insulation of earthing cable was found damaged.KOR RefineryAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-15Unsafe ConditionWork at HeightAt Tank #04, the scaffolding walkway inspection tag was found expired.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-15Unsafe ConditionElectricalAt Tanks #21 and #30, during fit-up and bottom plate installation activities, housekeeping at the worksite was observed to be very poor, as welding and electrical cables, sharp-edged plates, wedges, and tools were scattered around the area.Tank FarmTank #21 & 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-21Unsafe ConditionHousekeepingAt Tank #11, poor housekeeping was observed and the HSE supervisor was informed.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-04Unsafe ActProcedureAt tank #4, M/s IIW workers were moving on a damaged roof without proper planks.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-04Unsafe ConditionWork at HeightAt tank #4, loose materials (splash plates and GI sheets) were found lying on the scaffolding platform.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-06-30
2026-05-04Unsafe ConditionProcedureAt tank #4, during roof cutting, two lifelines/ rope supports were found loose.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-04Unsafe ConditionProcedureAt tank #35, during shuttering material shifting, nails were exposed, which could cause cuts or injuries to workers.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-21Unsafe ConditionHousekeepingAt Tank #05, poor housekeeping was observed at the backside of the tank.KOR RefineryTank #5ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-04Unsafe ActPPEAt tank #30, during asphalt activities, workers were not using required (PPE), specifically safety goggles and face masks, exposing them to fumes, dust, and potential eye and respiratory hazards.KOR RefineryTank #30ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-11
2025-11-21Unsafe ConditionProcedureAt Tank #05, no rest shed was available.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ActWork at HeightAt tank #56, fitter was observed using a mini hammer while working at height without a tool tie.Tank farmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-13
2025-11-26Unsafe ActPPEAt Tank #05, while performing civil work, M/s ATL workers were found without wearing safety gloves & dust mask. Counseling done.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ConditionProcedureAt tank #56, during the crane operation, the fitter team was observed moving under the suspended load within the barricaded area.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2025-11-21Unsafe ActProcedureAt Tank #05, construction staff Usman Sahib, Nizam Sahib, and ATL Shahid Lodhi were found inside the confined space without following the confined space entry protocol. There was no standby man available outside for entry monitoring.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-26Unsafe ConditionHousekeepingAt Tank #11, poor housekeeping was observed around tank yard.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-05-06Unsafe ConditionHousekeepingAt tank #56, poor housekeeping was observed inside tank, as binding wire pieces, a used grinding disk, and cotton rags were left on the floor.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-06Unsafe ConditionWork at HeightAt tank #56, during pipeline and wind girder banding work, the installed scaffolding structure was found with a green tag that did not mention an expiry date.Tank farmTANK# 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2025-11-21Unsafe ActElectricalAt Tank #05, the electrical team was working on electric cables without wearing safety gloves.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ActProcedureAt tank #56, during welding work at the manhole, the welder was observed not using a welding apron or sleeves, and the coverall was found in poor/damaged condition.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2025-11-26Unsafe ActWork at HeightTo mitigate the risk of falling objects at Tank #11, mesh was not found installed beneath the scaffolding structure.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ConditionEquipmentAt tank #56, 100 KVA generator was observed operating with engine oil seepage.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-06Unsafe ConditionWork at HeightAt tank #56, during pipeline banding, excessive load was placed on a scaffolding pipe, causing it to bend.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-05-06Unsafe ActWork at HeightAt tank #56, during back grinding work, a worker was moving on top of scaffolding without hooked safety harness.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2025-11-25Unsafe ConditionLack of SupervisionAt Tank #05, excavation was found without barrication. HSE supervisor was informed.KOR RefineryAt Tank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ActProcedureAt tank #56, during plumb inspection, a worker was observed hooked his harness on shell plate.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2025-11-24Unsafe ConditionLack of SupervisionAt Tank #11, waste bins were found filled with waste. HSE supervisor was informed.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-09Unsafe ActProcedureAt Tank # 30, workers were found using stairs which alternate steps had been cut down. Counselled the staff.Tank farmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-09Unsafe ConditionProcedureAt Tank # 30, during hot work activities, the fire blanket was found in damaged condition.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-05-09Unsafe ConditionProcedureAt Tank # 30, loose materials were found on the stair steps.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-24Unsafe ConditionLack of SupervisionAt Tank #11, M/s ATL QC person was found at height with hooking his harness hooks. Counseling done.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-09Unsafe ConditionEquipmentAt Tank # 30, while using the stairs, workers were not following the three-point contact rule, and materials/equipment were being handled improperly. Counselled the staff.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-24Unsafe ConditionPPEAt Tank #05, grinder operator was found without wearing safety gloves and ear plugs. Counseling done.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-09Unsafe ConditionProcedureAt Tank # 35, the dustbin found overflow, needs to be emptied.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-09Unsafe ConditionHousekeepingAt Tank # 35, during the safety round, housekeeping at the site needs to be improved.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-09Unsafe ConditionProcedureAt Tank # 35, during the safety round, diesel containment was found improper.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2025-11-24Unsafe ConditionLack of SupervisionAt Tank #05, poor housekeeping was observed and the HSE supervisor was informed.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-08Unsafe ActLack of SupervisionAt Tank #04, during the crane operation, the rigging supervisor was not visible, and signals were being given by another worker instead of the designated riggerKOR RefineryTANK #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-08Unsafe ConditionWork at HeightAt Tank #04, during crane operation, the suspended load (MS plate) was hitting the scaffolding structure.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionProcedureAt Tank #04, during gas cutting work, the gas cylinder hose was damaged/melted. RepetitiveTank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionProcedureAt Tank #04, during roof cutting work, loose materials were found on the damaged roof.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionProcedureAt Tank #04, During roof cutting work, the cut plates were being stacked on top of each other, while the roof condition was already deteriorated, creating an unsafe condition.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionWork at Height4. At Tank #04, during scaffolding material shifting, one scaffolder was crossing the product line. A proper platform is required.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionEquipmentAt IIW Yard, during grinding work, 5” and 9” grinders were being used without Deadman switch installation, and the lock system was active.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-05-08Unsafe ConditionProcedureAt IIW Yard, during the safety round, the ambulance driver was not present.Tank FarmIIW YardConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-27Unsafe ConditionProcedureAt Kargil area: The air filter of the breathing air compressor for sandblaster was missing.Tank FarmKargil areaConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-27Unsafe ConditionWork at HeightAt Kargil area: The scaffolding rest was found without tagging.Tank FarmKargil areaConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-27Unsafe ConditionVehicleAt Kargil area: A fire extinguisher handle was found damaged. Additionally, vehicle CAG-7981 was found without a fire extinguisher.Tank FarmKargil areaConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-27Unsafe ConditionSlip/Trip/FallAt Kargil area: Multiple Metallic bars were scattered across the walkway, creating a tripping hazard.KOR RefineryKargil areaConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-27Unsafe ActProcedureAt tank#35 M/s IIW ,during civil work, one worker was walking on steel reinforcement (rebar) using formwork wooden pieces with protruding nails, creating a risk of injury.KOR RefineryTANK# 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-27Unsafe ConditionProcedureAt tank#04 M/s IIW ,during gas cutting activities at the tank roof, the lifting pulley did not have a valid third-party inspection tag.Tank FarmTank #04ElectricalCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ConditionVehicleAt Road#16 (M/s DEL) : A truck GLBT- 767 was observed moving without a flagman, the designated flagman was found sitting inside the cabin with the driver.Tank FarmRoad#16ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ConditionHousekeepingAt Tank#35, 04 & at IIW Yard: Poor housekeeping was observed due to scattered materials, these areas need to be cleaned immediately.Tank FarmTank#35, 04 & IIW YardConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ConditionWork at HeightAt Tank#35: A wooden ladder was being used by M/s IIW workers.Tank FarmTank#35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ConditionElectricalAt DEL yard: Receptacle of electrical extension board was found damaged.Tank FarmDEL yardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ConditionLack of SupervisionAt Tank#21: The safety supervisor was not present at the site.Tank FarmTank#21ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ActPPEAt Tank#30: Some M/s DEL civil workers were wearing helmets not approved by PRL.Tank FarmTank#30StationaryCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-28Unsafe ConditionProcedureDuring lifting gear inspection at Tank #56, one lifting belt was found damaged and the tag line was improperly jointed.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKorangi RefineryClosed2026-06-24
2026-04-28Unsafe ConditionEquipmentAt Tank #56, combustible materials were found on top of the power supply for automatic girth welding machine & its tumble was also found melt.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-06-24
2026-04-28Unsafe ConditionElectricalAt Tank #56, welding cables were not properly dressed at the backside of the tank.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2026-04-28Unsafe ConditionWork at HeightAt Tank #56, one stool was observed placed on top of the scaffolding platform unsafe.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2026-04-28Unsafe ActLine of FireAt Tank #56, during crane operation, a worker was observed moving within the line of fire.Tank FarmTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2026-04-30Unsafe ConditionVehicleThe ready-mix truck was entering through the newly constructed gate while the flagman was standing outside Tank 35.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-30Unsafe ConditionElectricalAt Tank #35: A mixture filling pump was found without having a spark arrestor and battery terminals rubber boots. Furthermore, its tires were damaged, holes were observed on silencer and an open electrical circuit was also observed.KOR RefineryTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-30Unsafe ConditionLine of FireAt Tank #35: Vehicle No. TAR-047 was found operating without spark arrestor. Additionally, its tires are in poor condition with visible cuts/ damage.KOR RefineryTANK# 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-30Unsafe ActPPEAt Tank #35: a ready-mix truck was found working without wearing safety helmet and shoes.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-20Unsafe ConditionProcedureAt Road#01: Access of MCP-21 was blocked due to the placement of new MS line, a proper walkway/ crossover is required for safe access.KOR RefineryRoad#01StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-07-09
2025-11-27Unsafe ActPPEAt Tank #05, while performing excavation work, M/s ATL team were found without dust mask.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ActWork at HeightAt Tank #11, grinder operator was found without wearing ear plugs. Counseling done.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ActPPEAt Tank #11, while handling of structural material M/s ATL worker was found without wearing safety gloves. Counseling done.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ActProcedureAt Tank #05, during hot job M/s ATL fire extinguisher was not available at site. Informed to Mr. Majid of M/s ATL.KOR RefineryAt Tank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ConditionProcedureAt Tank #05, no rest shed was available.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ActProcedureAt Tank #05, unavailability of HSE officer was observed during hot work activity.KOR RefineryAt Tank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-28Unsafe ActPPEAt tank 5, while performing excavation and masonry work, M/s Kundi workers were found working without wearing dust mask. Counseling done.Tank FarmTank #05CivilCONTRACTORKundiRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-12-03Unsafe ConditionProcedureAt Tank #11, no rest shed was available.KOR RefineryAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-12-01Unsafe ConditionProcedureAt Tank #11, loose materials were found on walkway without barrication. Informed to Mr. Majid of M/s ATL.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-12-01Unsafe ConditionProcedureAt Tank #11, operating lever of M/s ATL fire extinguisher was found damaged. Informed to Mr. Majid of M/s ATL.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2026-04-20Unsafe ActProcedureAt Gantry substation:  M/s Kundi workers were found performing work inside confined space without maintaining a SBM Entry sheet, additionally, the excavated area was not barricaded.KOR RefineryGantry SubstationConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-20Unsafe ConditionLine of FireAt tank# 30: During hot work activity, the fire blanket was found to be damaged and not properly secured, failing to effectively prevent sparks.KOR RefineryAt Tank 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-20Unsafe ConditionHousekeepingAt DEL Yard: Diesel drum was found on wooden pallet without secondary containment, additionally there is no secondary containment in storage area.KOR RefineryAt DEL yardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-26Unsafe ConditionHousekeepingAt DEL yard: Poor housekeeping was observed, waste bins were overflowing and found to contain discarded food items(roti) and used oil filters.KOR RefineryDEL YardConstructionPRLRoutineKorangi RefineryClosed2026-06-24
2026-04-20Unsafe ConditionHousekeepingAt DEL yard: Poor housekeeping was observed, waste bins were overflowing and found to contain discarded food items(roti) and used oil filters.KOR RefineryDEL YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-07-13
2026-04-20Unsafe ConditionElectricalAt Tank #21,M/s DEL. the electrical distribution board (D.B) scaffolding shade inspection tag was missing.Tank FarmTank 21ConstructionCONTRACTORDelRoutineKorangi RefineryClosed2026-07-13
2026-04-16Unsafe ActPPEM/s DEL workers handling tank bottom asphalt material were not using KN95 face masks.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-20Unsafe ConditionPPEAt Tank #35, M/s IIW worker was found working without wearing safety helmet.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-26Unsafe ConditionWork at Heightsscaffolding planks were stacked on the tank roof without being secured.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-25Unsafe ActLack of SupervisionM/S DEL , the safety supervisor was not present at the worksite.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-21Unsafe ConditionFalling ObjectAt Tank #56 (M/s AJC), the 100 KVA generator shed was not properly covered. Some GI sheets are missing, and the drip tray is too small.KTTank #56ConstructionCONTRACTORAJCRoutineKemari TerminalClosed2026-06-24
2026-04-21Unsafe ConditionLack of SupervisionAt Tank #56 (M/s AJC), the Main Distribution Board (MDB) changeover handle is loose and requires immediate replacement for proper operation.KOR RefineryTank #56ConstructionCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-06Unsafe ConditionWork at HeightDuring pipeline banding, excessive load was placed on a scaffolding pipe, causing it to bend.Tank farmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-21Unsafe ConditionVehicleAt Tank #56 (M/s AJC), the 45-ton mobile crane’s main block wire rope shows banding/ deformation. Crane must be inspected and corrective measures taken before further use.KTAt Tank #56ConstructionCONTRACTORATLRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-21Unsafe ConditionHousekeepingAt Tank #56 (M/s AJC), welding cables were not properly dressed, creating a tripping hazard.KTAt Tank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-07-09
2026-04-21Unsafe ConditionWork at HeightAt Tank #56 (M/s AJC), while working at height two workers were found working without hooking their safety harnesses.Tank FarmAt Tank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-06Unsafe ConditionHousekeepingM/s AJC, gas cylinders were not properly secured with chains in the storage area and protective valve caps were not fixed.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-23Unsafe ConditionProcedureAt Tank #21, M/s DEL modified the scaffolding without applying a Red Tag. Tank FarmAt Tank #21ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-07-13
2026-04-10Unsafe ConditionWork at HeightThe railing supporting the lifeline scaffolding pipes is fragile. It needs to be repaired before proceeding with the next activity.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-23Unsafe ConditionProcedureAt Tank #21, a hand compactor operated by M/s DEL was found without a valid emission test certificate and an approved spark arrester.Tank FarmAt Tank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-23Unsafe ConditionProcedureAt IIW store Area, bitumen cans were stored without secondary containment arrangement.Tank FarmAt IIW Store AreaConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-04-23Unsafe ConditionWork at HeightAt Tank #04,M/s IIW, during lifeline installation, a scaffolder was observed moving on a damaged roof without proper planking.Tank FarmAt Tank #04,ConstructionPRLRoutineKorangi RefineryClosed2026-06-24
2026-04-10Unsafe ActWork at HeightOne worker was observed sitting on a scaffolding pipe.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-23Unsafe ConditionPPEAt WWTP, Mr. Nasir and Mr. Zubair was performing welding work without using welding safety helmets. Additionally, the work area canopy was covered with a tarpaulin sheet without the use of a fire blanket.Tank FarmAt WWTPConstructionCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-02-12Unsafe ConditionVehicleThe doors of two bowsers (TML-559 and TMN-332) were found locked.Tank FarmGantry areaLogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-04-24Unsafe ConditionWork at HeightAt Tank #04,M/s IIW during the safety round, loose materials (Splash plates) were observed lying on the scaffolding platform.Tank FarmAt Tank #04ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-24Unsafe ActProcedureAt Tank #21, M/s DEL the HSE representative was not present at the worksite during asphalt activities.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-04-24Unsafe ConditionPPEAt Tank #21 and at Kargil area, M/s DEL workers involved in asphalt activities were not following proper PPE requirements (heat-resistant PPE and cartridge masks) were not being worn and the jeep driver was not wearing safety shoes.Tank FarmAt Tank #21ConstructionCONTRACTORDELRoutineKorangi RefineryteamClosed2026-07-09
2026-04-25Unsafe ConditionPPEAt Tank #04 (M/s IIW): A worker was observed not wearing safety goggles.Tank FarmAt Tank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-03-31Unsafe ConditionProcedureM/s IIW, during civil work, a dumper was being used without a functioning reverse alarm.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-26Unsafe ConditionEnvironmentTank#56 M/s AJC, leakage of oil was observed from the tappet cover and fuel injector of 100 KVA generator.Tank FarmTank #56ConstructionCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-25Unsafe ConditionLine of FireTank#56 M/s AJC ,during crane operations, an automatic girth welding machine was shifted at the top shell inside the tank without proper barricading of the work area, workers were moving within the line of fire.Tank FarmTank#56StationaryCONTRACTORAJCRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-25Unsafe ConditionWork at HeightTank#56 M/s AJC, 4 nos of workers were observed on a scaffolding platform without hooking their safety harnesses.KTTank#56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-24Unsafe ActProcedureAt Tank #04, M/s IIW the gas cutter hose was not properly installed with double insulation using a flexible pipe.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2025-07-20
2025-07-18Unsafe ConditionSlip/Trip/FallAt tank #11, the fan for ventilation system was repeatedly tripping. HSE officer and site supervisor were informed and instructions to replace the fan were given.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-07-19
2025-07-03Unsafe ActProcedureAt tank #13, a worker was observed shifting materials while using the stairs. As both of his hands were occupied, he failed to maintain three points of contact. The worker was counseled.Tank FarmTank #13CivilCONTRACTORWMSRoutineKorangi RefineryClosed2025-07-04
2025-07-29Unsafe ConditionProcedureSkid generator bottom frame need paint.KTFoam TankCivilPRLRoutineKemari TerminalClosed2025-07-30
2025-07-29Unsafe ConditionProcedureSkid generator concrete foundation damage. Need repair.KTKTCivilPRLRoutineKemari TerminalClosed2025-07-31
2025-07-28Unsafe ActVehicleDuring the safety round at Tank #11, it was observed that an iron beam was loaded onto a Shehzor truck, but it was extending beyond the truck’s body, posing a risk of striking objects or causing accidents while in transit. This is for your information and necessary corrective actions.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-07-28
2025-08-09Unsafe ConditionProcedureCrane Found with Indication.KTKTStationaryCONTRACTORAJCShutdownKemari TerminalClosed2025-08-10
2025-08-08Unsafe ActPPEAt tank#05, a worker was observed inside the tank during sand blasting without wearing PPEs, informed to site HSE supervisor and worker consoling .Tank FarmTank#05ConstructionCONTRACTORATLShutdownKorangi RefineryteamClosed2025-08-10
2026-07-15Unsafe ActErgonomicstesting from finallahoregate 2CivilPRLRoutineKorangi RefineryAhsanOpen
2025-08-04Unsafe ActPPEAt Tank #05, a rigger was observed not wearing gloves during the lifting operation. The rigger was instructed to wear proper hand protection (gloves) as per safety protocol.Tank FarmTank #05ConstructionCONTRACTORATLShutdownKorangi RefineryClosed2025-08-05
2025-08-07Unsafe ActHousekeepingThe safety shoes of 3 AJC workers were found damaged. Immediately replaced.KTKTStationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2025-08-09
2025-08-07Unsafe ActEnvironmentA product line running from Tank 38 to Tank 01 had leakage from a valve, causing product dropping, inform Mr. Ijaz PRL(oil movement) The leaking valve was immediately reported to the concerned department, and the line was secured to prevent further spillage.KOR RefineryTank FarmTank FarmPRLRoutineKemari TerminalteamClosed2025-07-08
2025-08-16Unsafe ActLine of FireAt 801-J, sparks were hitting to the M/s UE worker stand nearby. Counseled the team.Plant AreaAt 801-JStationaryCONTRACTORUEShutdownKorangi RefineryClosed2026-08-17
2025-08-16Unsafe ActPPEAt 801-J, M/s UE worker were not using safety gloves and wearing damage coverall during working. Counseled the team.Plant AreaAt 801-JStationaryCONTRACTORUEShutdownKorangi RefineryClosed2025-08-17
2025-08-17Unsafe ConditionPPEAt AFC, while climbing a ladder, M/s DEL worker was found without wearing safety gloves. Counseling done.Plant AreaAt AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-17Unsafe ConditionElectrical02 nos. DEL worker found at plant side without having safety induction stickers on their helmets. Counseled the team.KOR RefineryKOR RefineryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-18
2025-08-18Unsafe ConditionEquipmentThe same worker of M/s AG, who was found yesterday at Gate 3 without having undergone medical and safety orientation and was handed over to Mr. Shahzad of M/s WMS, was again found today near the fire camp. Upon investigation, it was revealed that his medical and safety orientation has still not been conducted. He has now been handed over to Mr. Fahad Alvi.KOR RefineryGate# 3StationaryCONTRACTORAGShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ActProcedureAt the heat exchanger area, the towing jack of the hydro jetting machine was placed right next to the B1166:B1198Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-18Unsafe ConditionEquipmentAt road # 8, uncovered battery terminal was observed of WOMA machine. Informed to site supervisor.Plant AreaAt Road # 8StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-19Unsafe ConditionHousekeepingAt the heat exchanger area, spool piece was found on walkway, posing tripping hazard.Plant AreaFurnace AreaStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-20
2025-08-19Unsafe ConditionProcedureAt the heat exchanger area, the safety latch of the chain block is not properly fixed. It needs to be properly secured.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-19
2025-08-20Unsafe ConditionProcedureAt heat exchanger area, chain blocks & Stud bolt tray were found on walkway. Informed to DEL HSE representative for removal.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-20
2025-08-20Unsafe ConditionProcedureAt road 10, pressurize pipe of air compressor was found without whip latch. Informed to operator.Plant AreaAt Road# 10StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-21
2025-08-21Unsafe ActWork at HeightIn front of the control room, PRL operations operator was found on scaffolding platform without hooking his safety harness, although he was wearing it.Plant AreaControl RoomStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-21Unsafe ActWork at HeightAt 1101-C, during a lifting operation, a DEL worker was observed holding the suspended load by hand instead of using a tag line. Additionally, DEL HSE supervision was not present at the time. The worker was not wearing safety harness while on the scaffolding platform, and the area was not properly barricaded.Plant AreaAt 1101-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2026-07-09
2025-08-21Unsafe ActHousekeepingHousekeeping required near heat exchanger, used disposable coverall were found on floor.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-21Unsafe ActPPEAt AFC area, M/S DEL worker was found wearing unapproved coverall without reflector tapes and was found with folding sleeves. Informed the site supervisor and counseling done.Plant AreaAt AFCStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-22
2025-08-22Unsafe ConditionProcedureThe reverse alarm and spark arrestor of the DEL ambulance were missing, and a paramedic staff member was also absent todayPlant AreaDEL AmbulanceStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionSlip/Trip/FallAt intersection of road 3 and 10, a tray loaded with oily rocks and sludge filled bags (pyrophoric material suspected) were observed, informed to Mr. Arsalan for removal.Plant AreaAt Intersection of road 3 and 10StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionProcedureAt heat exchanger area, a trolley carrying scaffolding material was observed parked without wheel chowks. Instructed to place wheel chowks.Plant AreaHeat Exchanger AreaStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-24Unsafe ActProcedureSince the start of the shutdown, the HSE lead for the night shift of M/s DEL has not reported.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryteamClosed2025-08-23
2025-08-22Unsafe ActProcedureA hot job was carried out in the Utility and Pump Gallery, but no fire watcher from M/s DEL were available.Plant AreaUtility and Pump GalleryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionSlip/Trip/FallAt multiple locations (below area of AFC, utility, heat exchanger and pump gallery area) loose materials (pipes, nut/ bolts, exchanger head, gasket, valves ) were observed on the walkway without barrication.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActProcedureAt 301-F while working at height, M/s DEL worker was using spanner without tie his tool with tool tether.Plant AreaAt 301-FStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActWork at HeightAt 304-C, while working at height M/s DEL TE was found scaffolding platform without wearing safety harness. Counseling donePlant AreaAt 304-CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionLine of FireAt the Utility and Pump Gallery, sparks were observed coming out of the welding canopy. The working team was immediately instructed to cover the area.Plant AreaUtility and Pump GalleryStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionLine of FireAt plant center, during crane operation M/s DEL team standing in barricaded area.Plant AreaAt Plant CenterStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ConditionLack of SupervisionAt 123C And 124C leftover material was found. Informed to M/s DEL’s safety supervisor.Plant AreaAt 123C And 124CStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActVehicleAt road 10 near fire camp,M/s DEL’s truck was observed carrying tent material upon inspection it was found that its battery terminals were not covered with rubber boots. Instructed to cover the battery terminals covered with rubber boots.Plant AreaAt Road 10StationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2025-08-22Unsafe ActHousekeepingAt multiple locations (furnace area, road 5, heat exchanger area) mixed waste (hazardous and non- hazardous) were found, informed to M/s HSE supervisor.Plant AreaMultiple LocationsStationaryCONTRACTORDELShutdownKorangi RefineryClosed2025-08-23
2026-06-23Unsafe ActPPEAt Tank #56, M/s AJC. during top shell fit-up work, a hammer was being used without a tool lanyard (tool tie).KTAt Tank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-06-25Unsafe ActPPETank #21, Multiple workers were wearing damaged chin straps, and scratches were observed on their safety goggles.Tank FarmTank #21ConstructionCONTRACTORDELRoutineKorangi RefineryteamClosed2026-06-24
2026-06-25Unsafe ActProcedureTank #11 M/S ATL, confined space entry data sheet was not maintained during tank cleaning activity.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2026-06-25Unsafe ActPPETank #30, Multiple workers were wearing damaged chin straps, and scratches were observed on their safety goggles.Tank FarmTank #30ConstructionCONTRACTORDELRoutineKorangi RefineryteamClosed2026-06-24
2026-06-25Unsafe ActWork at HeightTank #04 M/S IIW, during scaffolding modification, scaffolders were observed attaching lanyard hook to the same pipe.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-06-24
2026-06-25Unsafe ConditionProcedureTank #21 MS DEL: The scaffold red tag had faded and turned white, making it difficult to identify the scaffold status.Tank FarmTank #21ConstructionCONTRACTORDELRoutineKorangi RefineryteamClosed2026-06-24
2026-06-27Unsafe ActLack of SupervisionROAD # 0  M/S IIW, the crane flagman was observed walking behind the crane during its movement.KOR RefineryROAD # 0ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-27Unsafe ActPPETANK #11 M/S ATL, workers were wearing damaged coveralls and safety shoes.KOR RefineryTANK #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-15Unsafe ConditionEquipmentTank #4 – M/S IIW: During the soap test, gas leakage was found from the cylinder regulators.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-15Unsafe ActEquipmentAt the IIW Yard, M/s DEL.  crane operations for MS plate offloading were being conducted while the wind speed was 34 km/h.KOR RefineryAt the IIW YardConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-27Unsafe ConditionEnvironmentIIW YARD M/S IIW, waste bins were found full and poor housekeeping was observed in workshop.KOR RefineryIIW YARDConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-15Unsafe ActPPEAt the DEL Yard, M/s DEL.  during grinding work, a worker was observed not wearing ear plugs.Tank FarmDEL YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-06-15Unsafe ConditionEnvironmentAt Tank #30, M/s DEL. a diesel leakage was observed from the 50 KVA generator. The generator should be replaced immediately.Tank FarmAt Tank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-15Unsafe ActLine of FireTank #4 – M/S IIW: During crane activity, a gas cylinder was found within the crane boom radius.KOR RefineryTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-07-09
2026-06-15Unsafe ActProcedureM/S DEL Yard: A worker was using a damaged welding cable.KORDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-19Unsafe ConditionHousekeepingNear Tank #32, M/S N.H, poor housekeeping was observed, leftover materials need to be removed.Tank FarmTank #32ConstructionCONTRACTORNHRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-06-19Unsafe ConditionEnvironmentAt Tank #21, M/s DEL, during stair repair work, the hot work area was not covered with a fire blanketTank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-06-19Unsafe ConditionLine of FireAt Tank #04, M/S IIW, during crane operation, one side of the work area was not barricaded.Tank FarmAt Tank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-01-30
2026-06-19Unsafe ConditionProcedureAt Tank #04, M/S IIW, the gas cylinders were not covered with a fire blanket.Tank FarmAt Tank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-06-30
2026-06-20Unsafe ActProcedureAt Tank #56: Inside the tank, a scaffolding structure had a red tag, but workers were still using it. Counseling doneKTAt Tank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-16
2026-06-20Unsafe ConditionEnvironmentAt Tank #56: Oil leakage was observed from two engine sides of the 100 kV generator. Informed to Mr. FarrukhKTAt Tank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-16
2026-06-20Unsafe ConditionProcedureAt Tank #56: the paramedic was absent from duty / No paramedic was available on-site. Informed to Mr. Farrukh KTAt Tank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-16
2026-06-20Unsafe ActWork at HeightAt Tank #56: M/s AJC worker was found lifting too many wages at once on top of the tank. Counseling doneKTAt Tank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-16
2026-06-08Unsafe ActProcedureAt tank#35, the potable stair being used to cross the ring wall was not properly fixed.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-08Unsafe ActPPEAt the DEL Yard, welder was performing welding work without wearing a safety helmet.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ConditionProcedureAt tank #30,  grinder of M/s DEL was found without a functional dead-man switch.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActPPEM/S DEL Yard: One gas cutting operator was working without gloves, and another worker was wearing damaged glovesTank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ConditionElectricalM/S DEL Yard: A worker was using a damaged welding cable.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActProcedureTank #4 – M/S IIW: During crane activity, the rigging supervisor was not present at the worksiteTank FarmTank #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActProcedureTank #4 – M/S IIW: During the soap test, gas leakage was found from the cylinder regulators.Tank FarmTank #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActProcedureTank #21 – M/S DEL: A worker was wearing a damaged coverall and had used banding wire to tie the sleeves.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-06-12Unsafe ActLine of FireTank #4 – M/S IIW: During crane activity, a gas cylinder was found within the crane boom radius.Tank FarmTank #4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-18Unsafe ConditionEquipmentAt Tank #35, M/s IIW, a tractor with a punctured rear tire was found parked inside the tank ring wall and a substandard spark arrestor was installed.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-05-23Unsafe ActLine of FireTank#4 M/S IIW, a helper was standing under the gas cutting area while sparks were falling.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-29Unsafe ConditionProcedureAt Tank #21, a hydraulic jack was found at the worksite without having valid third-party report at site.Tank FarmTank#21ConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-06-24
2026-04-29Unsafe ActProcedureAt Tank #35, during civil work for tank ring wall installation, workers were moving on an exposed steel structure.Tank FarmTank#35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-06-24
2026-04-21Unsafe ConditionLine of FireAt Tank #56 (M/s AJC), during welding work, sparks were observed hitting two nearby fitters.KTAt Tank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-07-09
2026-04-25Unsafe ConditionLine of FireAt Tank #30 (M/s DEL): During splash plate hanger removal activity, sparks were observed spreading outside the work area.Tank FarmAt Tank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-25Unsafe ConditionEnvironmentTank#56 M/s AJC, leakage of oil was observed from the tappet cover and fuel injector of 100 KVA generator.KTTank#56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-25Unsafe ConditionProcedureTank#56 M/s AJC, on the backside manhole scaffolding platform, planks were not securely tied.KTTank#56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-25Unsafe ActLine of FireAt Road #6 (M/s DEL): During crane activity, a roller operator was positioned in the line of fire.KOR RefineryAt Road #6ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-16Unsafe ActWork at HeightAt Tank #30, M/s DEL workers were carrying out scaffolding removal and tank bottom material handling at the same time.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-16Unsafe ConditionProcedureAt the access of Tank #04, backfilling and leveling were required.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-16Unsafe ActWork at HeightAt Tank #04, M/s IIW workers did not use a bag or bucket during scaffolding material lifting.Tank FarmAt Tank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-15Unsafe ActProcedureAt Tank #11, M/s ATL, a vacuum box test (VBT) was being conducted inside the tank while welding and grinding activities were carried out simultaneously.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-15Unsafe ActPPEAt Tank #11, M/s ATL, a worker was performing greasing and soap testing without wearing gloves and safety goggles, and his sleeves were folded.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-15Unsafe ActWork at HeightAt Tank #11, M/s ATL, a scaffolder was carrying out scaffolding work without properly tying and securing the planks.Tank FarmAt Tank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-19Unsafe ActPPERoad#4 M/s DEL planning team staff was observed without wearing safety helmet.KOR RefineryRoad#4ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-19Unsafe ActProcedureTank#30 M/s DEL, the flagman was observed walking alongside the moving trailer, disregarding safe clearance distances.KOR RefineryTank#30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-19Unsafe ActProcedureTank#4 M/s IIW, there was no sitting arrangement for generator operator.KOR RefineryTank#4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-19Unsafe ConditionSlip/Trip/FallTank#4 M/s IIW, Electrical cables were observed lying unprotected on the ground and exposed on the walkway.KOR RefineryTank#4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-19Unsafe ConditionEnvironmentTank#4 M/s IIW, oil leakage was observed from the generator.KOR RefineryTank#4ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ConditionFalling ObjectAt Tank # 30: A splash plate hanger was observed falling from height during work activity, posing a risk of injury to personnel below.Tank FarmAt Tank # 30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ConditionFalling ObjectAt DEL Yard: MS sheets were found lying unsecured in front of the gas cylinder storage area.Tank FarmAt DEL yardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-07Unsafe ConditionHousekeepingAt DEL Yard: Poor housekeeping observed during safety round, need to clean the area.Tank FarmAt DEL yardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-10Unsafe ConditionHousekeepingAt outside area of Tank #56, Poor housekeeping was observed, welding slag was scattered at multiple locations.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-16
2026-04-10Unsafe ActWork at HeightAt Tank #56,M/s AJC, welder was found working at height without hooking his safety harness hook.KTAt Tank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-16
2026-04-05Unsafe ConditionEquipmentTank#56, M/s AJC, A fitter was carrying a grinder by hand while moving on a temporary platform without hooking his safety harness.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-05Unsafe ConditionEquipmentTank#56, M/s AJC, A fitter was carrying a grinder by hand while moving on a temporary platform without hooking his safety harness.Tank FarmTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-09-09
2026-04-05Unsafe ConditionWork at HeightAt  Tank #30,M/s DEL, during the shifting of scaffolding materials to the tank roof via stairs, proper three-point contact was not maintained.KOR RefineryTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-09
2026-04-04Unsafe ConditionProcedureAt Tank4 (M/S IIW), A Trolley was found parked without stoper.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ConditionLack of SupervisionAt Tank 11 (M/S ATL), The mechanical supervisor was not present at work while workers were performing wielding and grinding.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ConditionLine of FireAt Tank 21 (M/S DEL) during wielding and grinding operations that fire blanket was present but not suitable to withstand sparks or molten metals.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ConditionLine of FireAt Tank30 (M/S DEL) during wielding and grinding operations that fire blanket was present but not suitable to withstand sparks or molten metals.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ConditionHousekeepingAt Tank 21(M/S DEL) Found site not properly dress up, housekeeping required.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ConditionElectricalAt Tank 21 (M/S DEL) The electrical DB shade was found without the required scaffolding tag.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-04Unsafe ActPPEAt M/S DEL yard, during crane maintenance work worker was found not using required PPEs (safety goggles and gloves) and work with folded sleeves.Tank FarmM/S DEL yardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-09-07
2026-04-03Unsafe ConditionProcedureAt Tank#35: M/s IIW GI sheets found without proper barricading and are not in a secured condition.Tank FarmTank#35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionElectricalAt Tank#21: M/s DEL has no proper access to operate electrical DB, and There is no fire extinguisher near DB.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionEnvironmentAt Tank#30: No Waste Bins available on-site; bins need to be place immediately.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionEnvironmentAt Tank#21: No Waste Bins available on-site; bins need to be place immediately.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionProcedureAt Tank#35: M/s IIW work is being carried out without the presence of a safety officer at the site.Tank FarmTank#35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionElectricalBird nests were observed inside MCP N1 & N2. Needs to be removed.KOR RefineryMCP N1 & N2ConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-03Unsafe ConditionEnvironmentThe open oily pit near Tank 24 needs to be covered/closed immediately, as hot work is currently in progress at the adjacent Tank 21.Tank FarmTank #21ConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-02Unsafe ActProcedureAt Tank #56, Materials were being lifted using only a rope without proper lifting methods (no bucket, tool bag, or pulley used) by M/s AJC workers.Tank FarmTank # 56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-04-05
2026-03-30Unsafe ActProcedureAt Tank 35, M/s IIW, during civil work, a tractor was being used with a spark arrestor that was not approved by PRL.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-03-28Unsafe ActPPEAt tank-30-yard, M/s AKS workers (Usman, Qurban, Noor, Haneef, Siddiq) were found wearing damaged safety shoesTank FarmTank # 30ConstructionCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-28Unsafe ActProcedureAT tank -35, The movement of M/s IIW excavator was observed without flagman.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-28Unsafe ActProcedureAt tank-21, M/s DEL site safety supervisor was not present at site while work was being in process.Tank FarmTank # 21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActProcedureAt Tank #30, M/S DEL, during the replacement of the gas cylinder used for gas cutting, the cutting torch regulators were left open, which created a risk of fire.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActProcedureAt Tank #30, M/S UE, M/s UE painter was found wearing damaged safety shoes.Tank FarmTank #30ConstructionCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActEquipmentAt IIW Yard: Access of the generator was found blocked by another generator. Provide clear access for emergency situations.Tank FarmIIW YARDConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActEquipmentAt Road#12: GI sheet in the Generator Area was not tied properly. Secure all loose sheets immediately.KOR RefineryRoad# 12ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActEquipmentAt DEL Yard: Two grinders were left attended on a conductive MS plate with the power supply still connected.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActProcedureAt DEL Yard: The rest area is incomplete and a worker was observed sitting in the unfinished area.Tank FarmDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-27Unsafe ActFalling ObjectAt Road#1(Near Gantry): The pipeline is resting on temporary supports with stones used as wedges. Proper wedges must be installed to prevent the pipeline from fallingTank FarmRoad #1StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActWork at HeightAt Utility Area: M/s AKS worker was observed working at height without using tool tie. A falling object risk to workers below.Tank FarmUtility AreaCivilCONTRACTORAKSRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActPPEAt Road#07: M/s QK workers were found performing soil-related tasks without wearing face mask and safety googles, leading to dust exposure.Plant AreaRoad#07CivilCONTRACTORQKRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActPPEAt Road#12: M/s UE workers were observed working without safety gloves.Plant AreaAt Road#12CivilCONTRACTORQKRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActPPEAt Road#07: M/s UE worker perform a work at height without tool tie, also supervisor is not present at the sitePlant AreaRoad#07CivilCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionProcedureAt Tank#11: The area needs to be properly barricaded as no work is currently in progress at the tank.Plant AreaTank#11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ConditionEnvironmentAt DEL yard: Diesel leakage was observed from a compressor causing environmental contamination.Plant AreaDEL yardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActWork at HeightAt DEL yard: M/s DEL worker was observed performing maintenance work of compressor at height without a ladder or stool. Also, work was being carried out without a valid maintenance permit.Plant AreaDEL yardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActProcedureAt Tank #30 (M/S DEL), unsafe activity was observed during the movement of empty and filled gas cylinders across the fire water line, posing a risk of personal injury.  Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-26Unsafe ActPPEAt Condensate Decanting Area: M/s swift worker were working without hand gloves and safety goggles. Also, oily waste needs to be cleaned from the area.  Tank FarmCondensate Decanting AreaTank FarmCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-03-30
2026-03-18Unsafe ActWork at HeightAt decanting Point 12: Bowser driver found walking on top of the bowser without connecting his safety harness to the fall arrestor.Tank FarmDecanting Point 12LogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-18Unsafe ActWork at HeightAt decanting area: Bowser driver was observed in an unsafe posture, resting on the gantry’s swing ladder.Tank FarmDecanting PointLogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-03-25
2026-03-16Unsafe ActProcedureRoad No. 1: M/s RE. Welders were observed wearing combustible cloth (romal/scarf) during welding work.Tank FarmRoad No. 1StationaryCONTRACTORRERoutineN/AKorangi RefineryteamClosed2026-03-15
2026-03-05Unsafe ActWork at HeightTank #21: M/s DEL workers were moving on scaffolding platforms that were tagged with a red tag.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-05Unsafe ConditionElectricalTank #21 (DEL): an extension lead with an improper joint was found and immediately replaced.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-05Unsafe ConditionElectricalTank #21 (DEL): the electrical cable of grinder was found without proper double isolation.Tank FarmTank #21ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-06Unsafe ConditionProcedureTank #04 – M/s IIW: During gas cutting activity, the provided double isolation was found damage due to contact by the hot surface.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-06Unsafe ConditionProcedureTank #04 – M/s IIW: Workers’ rest shade was found incomplete and not properly arranged for worker comfort.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-03-06Unsafe ConditionProcedureTank #11- M/s ATL: During crane operation, workers were observed standing under the boom of crane.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-03-10
2026-02-23Unsafe ActPPEAt Tank #11, during sandblasting work, two workers were observed without face masks and were immediately counseled.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-23Unsafe ConditionWork at HeightAt Road No. 03, scaffolding inspection tag missing at walkway ,tag immediately installed and corrected.KOR RefineryRoad No. 03ConstructionPRLRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-27Unsafe ConditionElectricalA welding rectifier was observed without earthing and bonding. Electrician were asked to install the same.KTKTStationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-17
2026-02-27Unsafe ConditionHousekeepingPoor housekeeping found inside tank#56 inform to AJC (HSE supervisor) Osama and removed all combustible materials.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-07-17
2026-02-23Unsafe ActLine of FireAt tank#56, welder helper exposed to welding sparks due to improper positioning , counseled on hot work safety and safe distance maintenance.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-27
2026-02-23Unsafe ActLine of FireAt Tank #56, rigger entered crane line of fire during lifting operation, counseled on exclusion zone and lifting safety.KTTank #56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-27
2026-02-23Unsafe ConditionEquipmentAt Tank #11, during live generator operation, the authorized operator was absent, and a standby authorized person was arranged immediately.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-23Unsafe ConditionEquipmentAt Tank #04, a 20 KVA generator was operating without a protective shade.TATank #04ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-23Unsafe ActPPEAt Tank #30, a worker inside the tank was using a face mask with a damaged cartridge.Tank FarmTank #30ConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-23Unsafe ActProcedureAt DEL yard, two scaffoldings were found without attached shade and inspection tags.KOR RefineryDEL YardConstructionCONTRACTORDELRoutineN/AKorangi RefineryteamClosed2026-02-27
2026-02-19Unsafe ConditionElectricalAt tank 56, AJC Welding Electrode oven was being used with expired electrical tag.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-17Unsafe ActElectricalAt Tank #11: During vacuum testiAt backside of control room: Battery operated device was in use without prior tagging/ inspection by Electrical Department. Additionally, battery operated equipment was not ticked on the equipment to be used in hot work permit. ng at the tank bottom, two workers were not using rubber gloves.Plant AreaControl RoomElectricalCONTRACTORSmart ClimateRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-09Unsafe ConditionVehicleATL Yard: The ambulance was found non-operational. The battery was discharged and the fuel pump was not functioning.KOR RefineryATL YardConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-17
2026-02-09Unsafe ConditionSlip/Trip/FallDESCON Yard: Materials were not properly barricaded and were scattered, creating potential safety and trip hazards.KOR RefineryDESCON YardConstructionCONTRACTORDELRoutineKorangi RefineryClosed2026-07-17
2026-02-09Unsafe ConditionProcedureTank No. 35: The damper driver was observed operating the vehicle without wearing a seat belt.KOR RefineryTank No. 35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-02-10Unsafe ConditionLine of FireAt the FO Gantry Bay #2, bowser (TML-558) was found parked without wheel chocks and a spark arrestor, with the door locked. As per another bowser driver, the driver had left the refinery to have breakfast.KOR RefineryGantry Bay #2LogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionVehicleAt the Gantry area, the doors of two bowsers (TML-559 and TMN-332) were found locked.KOR RefineryGantry AreaLogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionProcedureAt the Gantry area, no fire extinguisher was found in front of bowser (TML-559) and the light cover was missing, exposing the electrical circuit.KOR RefineryGantry AreaLogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionVehicleAt the Gantry area, the ignition key for bowser (JQ-5734) was not found in the ignitionKOR RefineryGantry AreaLogisticCONTRACTOROMCRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ConditionEnvironmentAt Road #02, the doors of the garbage, hazardous, and recycling waste yards were found broken and need to be repaired.KOR RefineryAt Road #02CivilPRLRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ActPPEAt Boiler-4, during insulation work at height, M/s Swift workers were not wearing helmet chin straps.KOR RefineryAt Boiler-4CivilCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ActPPEAt the Heat Exchanger area, while carrying out filling work on the exchanger cover, an M/s Swift worker was found working without wearing gloves.KOR RefineryHeat Exchanger AreaCivilCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ActSlip/Trip/FallAt Boiler #4, a spool piece was found lying on the walkway, posing a tripping hazard.KOR RefineryAt Boiler #4CivilCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-10Unsafe ActProcedureAt the opposite side of Boiler #4, a used gaskets were found on the ground and needs to be removed.KOR RefineryAt Boiler #4CivilCONTRACTORSWIFTRoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActProcedureAt laydown area: M/s U.E worker was found wearing a PRL-unapproved coverall (with metallic buttons and without reflective tape).Tank FarmAt Laydown AreaStationaryCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActEquipmentAt laydown area: The grinder was found in an energized condition, and an M/s UE worker had removed the used disc without isolating the power source. Additionally, no grinder stand was available.Tank FarmAt Laydown AreaStationaryCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-02-20
2026-02-11Unsafe ActEquipmentAt laydown area: The generator trolly was found without wheel chock.Tank FarmAt Laydown AreaStationaryCONTRACTORUERoutineN/AKorangi RefineryteamClosed2026-02-20
2026-04-02Unsafe ActHousekeepingTank #11: During sand blasting activities using an air compressor, multiple times tire puncher was observed. The defective component was replaced immediately.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-02Unsafe ActHousekeepingTank #11: During ongoing sand blasting and fabrication works, site housekeeping was found unsatisfactory, posing potential safety and operational risks.Tank FarmTank # 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-04-02Unsafe ActHousekeepingTank #35: During civil works, workers were observed using scratched safety goggles, which may compromise eye protection effectiveness.KOR RefineryTank # 35ConstructionCONTRACTORIIWRoutineN/AKorangi RefineryteamClosed2026-04-05
2026-02-02Unsafe ConditionElectricalTank #56: Welding machine and electrical DB found without inspection tags (AKS team not available on Saturday).KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionVehicleTank #56: During lifting operation, the truck was strucked due to suspended load and improper tagline control; counseling done.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionPPETank #56: Unapproved and non-100% cotton masks used during back grinding on tank shell.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionProcedureTank #56: Inadequate barricading observed during hot work activities (shell fitting and C-channel installation).KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionWork at HeightTank #56: Scaffolding platform found unsafe and unsuitable for grinder operator to maintain a safe working position.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionEquipmentTank #56: Grinder operator’s face shield found scratched and dirty, reducing visibility and safety.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionElectricalAt tank#56, AJC electrician was found working on electric supply board without gloves.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-02Unsafe ConditionElectricalAt tank#56, AJC electrician was found working on electric supply board without gloves.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-02-07Unsafe ConditionWork at HeightAJC inspection team was working at height without hooked safety harness.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionWork at HeightAJC welding machine #13 was being used without earthing.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionWork at HeightAt KT, Poor housekeeping was observed. Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionWork at HeightDuring crane operation AJC helper was moving under barricading area. Helper counseling was done.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-02-07Unsafe ConditionWork at HeightDamaged electric board# 11 was being used inside tank platform by AJC electrician. Electrical Bord was removed from site.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-10
2026-01-29Unsafe ConditionProcedureTank #56: During night-time welding activities, it was observed that the lighting was insufficient, with lux levels recorded at 35–41, below the required standard.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-01-29Unsafe ConditionElectricalTank #56: It was observed that the live main DB and welding machine were inadequately covered with a poly sheet, posing an electrical safety hazard.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-01-29Unsafe ConditionElectricalTank #56: It was observed that M/s AJC worker, Mr. Shazad, was using safety shoes that are not approved by PRLTank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-01-29Unsafe ConditionEquipmentTank #56: It was observed that the 100 kVA generator was in operation without a drip tray, posing a potential oil spill hazard.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-02-05
2026-01-24Unsafe ConditionElectricalAt tank #56, three electrical board was found withou proper insulation, electric board was removed from site and informed to AJC shahid.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-24Unsafe ConditionElectricalAt tank #56, Grinder #02 was found on site without electric tag, informed to AJC shahid.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-24Unsafe ActPPEAt tank #56, M/s AJC workers were not wearing gloves and goggles on site, counseling was done and inform to M/s AJC HSE representativeKTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-23Unsafe ActEquipmentAt tank #56, One Grinder was found without safety guard on site; the grinder was removed from the site.KTTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-26
2026-01-23Unsafe ActPPEAt tank #56, AJC electrician was working on electric DP without safety gloves.KTTank #56ConstructionCONTRACTORAJCRoutineN/AKemari TerminalteamClosed2026-01-26
2026-01-22Unsafe ActLine of FireAt Tank#56, AJC grinder men was grinding near crane operation, while the safety supervisor were at other side for site works.  KTTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-06-25
2026-01-19Unsafe ActWork at HeightAt tank #56, A temporary ladder was being used which was found lose from the fixing point, creating a fall hazard; informed HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActPPEAt tank #56, M/s AJC workers were observed without safety goggles, informed to HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActElectricalAt tank #56, A damaged electrical extension board was found in use at site, informed HSE supervisor AJC.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActElectricalAt tank #56, A 5" grinder electrical inspection tag was found damaged: informed HSE supervisor AJC.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActPPEAt tank #56, A worker’s safety shoes were found damaged which was immediately replaced after informing HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActProcedureAt tank #56, A 200 KVA generator spark arrestor found installed with unapproved spark arrestor Informing HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActProcedureAt tank #56, The ambulance spark found installed with unapproved spark arrestor. Informing HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActElectricalAt tank #56, Electrical cable of extension box was found damaged; informed HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActElectricalAt tank #56, Electrical cables were found lying on a wet surface at the workplace; informed HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActProcedureAt tank #56, During crane operation lifting of MS plate, a 3-ton sling wire was found damaged, immediately removed from the site.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-19Unsafe ActProcedureAt tank #56, During hot work activity a fire extinguisher was not available. Informed HSE supervisor.KTTank #56StationaryCONTRACTORAJCRoutineKemari TerminalClosed2026-07-17
2026-01-25Unsafe ActPPEAt tank # 35, during civil work, workers were found not wearing face masks. Informed to the HSE Supervisor.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-06-28
2026-01-22Unsafe ActProcedureAt tank # 35, unsafe manual hammering observed during steel cutting.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-06-28
2026-01-22Unsafe ActEquipmentAt tank # 35, generator shade not installed at office area.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-06-28
2026-01-12Unsafe ActProcedureAt tank # 56, the operator was not present on the running 200 KV generator. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2026-01-12Unsafe ActProcedureAt tank # 56, paramedic was not present on site. Informed to HSE lead AJC.Tank FarmTank # 56StationaryCONTRACTORAJCRoutineKemari TerminalteamClosed2026-01-11
2026-01-12Unsafe ActWork at HeightAt tank # 62, the expiry date on inspection tag of scaffolding was not available.Tank FarmTank # 62CivilPRLRoutineKemari TerminalteamClosed2026-01-11
2026-01-16Unsafe ActWork at HeightAt tank # 62, reflective tape was missing on scaffolding installed along the roadside, posing a risk of vehicle colliding with the scaffolding (AKS).KTTank #62CivilCONTRACTORAKSRoutineKemari TerminalteamClosed2026-01-18
2026-01-06Unsafe ConditionVehicleDuring excavation work at Tank #35, the excavator being used by M/s IIW was found without a PRL-approved spark arrester and was reported to the HSE In-Charge.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionHousekeepingAt tank#35,during excavation work, found some materials not barricaded at work site. Informed to HSE supervisor IIW using materials barricaded immediately.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionHousekeepingAt tank#35,during excavation work, found full  diesel dram were present at tank yard. Informed to HSE in charge immediately remove diesel dram.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionProcedureAt tank#04 ,during removing IFR materials not barricaded informed site supervisor and immediately barricading area.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionLack of SupervisionAt tank#04,during confined space activities, not present HSE person ,informed site supervisors.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionLack of SupervisionAt tank#11 ATL, W/S, during crane operation involved riggers 3rd party certification missing. Informed HSE in charge.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionHousekeepingAt tank#11,during safety round I observe pipe line materials not barricaded, informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-17
2026-01-06Unsafe ConditionProcedureHandrail installed at walkway need to be fixed located at road no. 2 opposite foam skid generator.  KTKTCivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedurePermanent Chain pole needs to be installed as barrication over underground pipelines at road # 1 near VFD Crude Pump.  KTKTCivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedureWalkway is required for easily access the foam header at road # 1.  KTKTCivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedureTank 57 west side (walkway) handrails need to be fixed and walkway at road # 1 need to be repaired.KTTank #57CivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedureThe access staircase to the fire hydrant no. 16 need to be realigned from road side at road # 1.     KTFire Hydrant no. 16CivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedureWalkway platform is required for Tank # 58 foam manifold at road # 1.KTTank # 58CivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-06Unsafe ConditionProcedureRotary miller machine found at road # 1 need to be removed.  KTRoad #1CivilPRLRoutineKemari TerminalClosed2026-07-17
2026-01-05Unsafe ConditionPPEAt tank 04 yard, during scaffolding materials sifting not wearing a safety gloves, , informed to site supervisor and consoling done.Tank FarmTank #04ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-06
2026-01-05Unsafe ConditionProcedureAt tank#35,during excavation work use one dumper not fitted revers alarm, informed to HSE person and immediately fitted revers alarm.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-06
2026-01-05Unsafe ConditionLack of SupervisionAt tank#35, during excavation work use one dumper move on rood.16 without flagman. Informed to HSE supervisor and consoling done.Tank FarmTank #35ConstructionCONTRACTORIIWRoutineKorangi RefineryteamClosed2026-01-06
2025-12-24Unsafe ActProcedureAt tank # 04, Al Hadeed, workers engaged in sludge removal inside the tank were found wearing coveralls that were neither reflective tape nor PRL-approvedTank FarmTank # 04CivilCONTRACTORAl HadeedRoutineKorangi RefineryClosed2026-07-19
2025-12-24Unsafe ActPPEAt tank# 35, during excavation workers were found without dust mask. Informed to HSE supervisor to use proper PPEs.Tank FarmTank # 35ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-24Unsafe ActPPEAt tank # 35, IIW Ambulance equipped with spark arrester (metallic grating), it should be replaced with proper spark arrestor.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActElectricalAt tank# 11, electrical inspection tag was found expired of ventilation fan, informed to HSE supervisor, and immediately removed from the site for reinspection and retagging.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActProcedureAt tank # 5 & 35, shifting scaffolding material through crossing the dike wall instead of using the proper passage.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActProcedureAt tank # 35, IIW two workers were observed working in close proximity to the excavator.Tank FarmTank # 35ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActWork at HeightAt tank # 20, the toe board was found missing on the lifting platform being used by the UE for painting work, creating a potential risk of paint cans and materials falling from height. Furthermore, the lifting rope was found damage.Tank FarmTank # 20CivilCONTRACTORUERoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActWork at HeightAt tank # 04, an air hose pipe and electrical cable were found lying on the walkway, creating a trip hazard. The issue was immediately reported to the HSE personnel from SWIFT Civil, and the walkway was promptly cleared.Tank FarmTank #04CivilCONTRACTORSWIFTRoutineKorangi RefineryClosed2026-07-19
2025-12-19Unsafe ActProcedureATL workers were observed crossing the Tank-05 dyke wall, which is unsafe. The ATL HSE Supervisor was informed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-19Unsafe ActHousekeepingDuring a round of the Tank-05 yard, poor housekeeping was observed. The HSE Supervisor of ATL was informed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-19Unsafe ActWork at HeightOutside the Tank 36 yard, along the road, scaffolding pipes were found laid in a disorganized manner. The HSE Officer of IIW was informed.Tank FarmTank #36ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-19Unsafe ActProcedureA rest shed is not available at Tank 36. The matter was informed to the IIW HSE Officer.Tank FarmTank #36ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-17Unsafe ConditionProcedureAt Tank #11, during mechanical work inside the tank, the ventilation system was not in use. The site supervisor was informed and the ventilation fan was started immediately.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-17Unsafe ConditionHousekeepingAt ATL W/S, during crane operations, the safety person was not available at the site. The rigging supervisor and construction representative were informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-16Unsafe ActProcedureAt Tank #11, during fabrication work, the I-beam and U-clamps in use were not secured with chains. The HSE supervisor and site supervisor were informed and chains were installed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActProcedureAt Tank #11, the gap between the shell and the scaffolding platform was not covered. The construction representative and HSE supervisor were informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActProcedureAt Tank #11, the ATL fire extinguisher was found lying at the site in very poor condition. The HSE supervisor was informed, and the fire extinguisher was replaced.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActProcedureAt Tank #11, the safety sign on the waste disposal dustbin was found torn and needs to be replaced.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActProcedureAt Tank #05, during civil work on the boundary wall, the walkway was found unsafe and obstructed. The HSE supervisor was informed, and the access was cleared and made safe immediately.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActProcedureAt Tank #05, during civil work on the boundary wall, a proper platform was not provided, and workers were working under unsafe conditions. The HSE lead was informed, and a safe scaffolding platform was provided immediately.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-16Unsafe ActWork at HeightAt Tank #11, during tools inspection, two tool ties were found damaged. The HSE supervisor was informed, and the tool ties were replaced immediately to ensure safe work.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-19
2025-12-15Unsafe ConditionElectricalAt Tank #11, during fabrication work, one electrical extension board was found with an expired inspection tag. The HSE supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionElectricalAt Tank #05, during civil work, the access was not clear. The HSE supervisor was informed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionElectricalAt Tank #11, during safety harness inspection, one lanyard hook was found not working. The HSE supervisor was informed, and the safety harness was replaced.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionFalling ObjectAt the Gantry Substation, railings have been installed at the roof edge for fall protection; however, there are significant gaps in the railings and edge, posing a risk of falling.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionWork at HeightAt the Gantry Substation, no lifeline has been installed on the roof to which a safety harness can be hooked.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionWork at HeightAt the Gantry Substation, on the scaffolding platform, workers from QK Builders are moving around but are not hooking their safety harnesses.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionWork at HeightAt Road 1 near the M/s ATL fabrication yard, a person from M/s Pak Impex was found wearing a coverall without reflective tape and was not wearing safety goggles. Counseling doneTank FarmGantry SubstationConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ConditionWork at HeightAt Road 2, M/s RE generator was found parked without wheel chocks.Tank FarmRoad # 2StationaryCONTRACTORRERoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ActProcedureAt road #16, M/s IIW staff were found sitting on road due to unavailability of rest shed. Counseling done.Tank FarmRoad # 16ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-15Unsafe ActPPEAt Road #16, a person from M/s IIW was found wearing safety shoes that were not PRL-approved. Counseling done.Tank FarmRoad # 16ConstructionCONTRACTORIIWRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionEnvironmentAt Tank #05, diesel cans were found kept near the generator. The HSE Supervisor was informed, and the diesel cans were immediately removed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionHousekeepingAt Tank #05, during civil work on the boundary wall, workers were passing materials over it and the access was not clear. Mr. Irfan was informed and the access was cleared immediately.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionHousekeepingAt Tank #11, during fabrication work, the gap between the shell and the platform was not covered to prevent falling objects. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-14Unsafe ConditionEnvironmentAt Tank #11, during fabrication work, I-clamps and U-clamps were found tied with binding wire instead of using chains. The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionProcedureAt Tank #11, no operator was present while the generator was in use at the ATL office (25 kV). The HSE Supervisor was informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionVehicleAt Tank #11, a loaded boom truck developed a mechanical fault; the clutch and gear system were not functioning properly. The HSE Lead and Project CM were informed. The boom truck was immediately stopped and isolated, and the operator was instructed to park the vehicle in a safe area. The issue was reported to the mechanical/maintenance team for inspection and repair. The boom truck will remain out of service until the fault is rectified and verified as safe for operation.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionVehicleAt Tank #11, a loaded boom truck developed a mechanical fault; the clutch and gear system were not functioning properly. The HSE Lead and Project CM were informed. The boom truck was immediately stopped and isolated, and the operator was instructed to park the vehicle in a safe area. The issue was reported to the mechanical/maintenance team for inspection and repair. The boom truck will remain out of service until the fault is rectified and verified as safe for operation.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionVehicleAt Tank #11, an ATL worker was lifting and dragging a steel bar weighing more than 50 kg, which is against manual handling rules and safe lifting limits. The HSE Supervisor was informed, and counselling was conducted.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionVehicleAt Tank #11, two grinder operators were using grinders without maintaining a safe distance, causing sparks to hit each other during operation. The HSE Supervisor was informed, and counselling was conducted.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-12Unsafe ConditionVehicleAt Tanks #11 and #05, some ATL workers were not using safety gloves regularly. The HSE Supervisor and Site Supervisor were repeatedly informed.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActEquipmentAt Tank #11, a grinder stand was available. However, the grinder was placed on the floor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActWork at HeightAt Tank #11, parallel activities (fabrication work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActWork at HeightAt Tank #11, M/s ATL worker was found walking on scaffolding platform without hooking his harness hook.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActHousekeepingAt outside area of tank #5. Leftover material needs to be removed.Tank FarmTank #5ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActEnvironmentOil leakage was observed from M/s ATL’s generator, which is used for the office area.Tank FarmATL YardConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ActWork at HeightAt Tank #11, a tool used for reinforcement was found with a gripping handle.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-11Unsafe ActPPEAt Tank #11, workers inside the tank were using black goggles during mechanical work. The HSE Supervisor was informed, and the workers were instructed to replace the black goggles with clear safety goggles suitable for inside-tank work.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-11Unsafe ActPPEAt Tank #11, the grinder man inside the tank was not using earplugs during grinding work. The HSE Supervisor was informed, and counselling was provided.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-11Unsafe ActHousekeepingAt Tank #11, poor housekeeping was observed in the tank yard, including scattered tools, materials, and debris. The HSE Supervisor was informed, and the workplace was immediately cleaned.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-11Unsafe ActPPEAt Tank #11, some ATL workers were not using safety gloves regularly. The HSE Supervisor was informed, and the Site Supervisor was instructed to immediately provide the required PPE.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-11Unsafe ActPPEAt Tank #05, during civil work for backfilling the bund wall, ATL workers were not using dust masks. The HSE Supervisor was informed, and counselling was provided.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ConditionProcedureNear the gantry sub-station, construction materials (cement mixer, trolley, etc.) were found placed on the road without proper barrication.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineKorangi RefineryClosed2026-07-19
2025-12-09Unsafe ConditionProcedureAt gantry sub-station, M/s QK Builders workers were found working below area of expired green tag scaffolding structure.Tank FarmGantry SubstationCivilCONTRACTORQKRoutineKorangi RefineryClosed2026-07-19
2025-12-05Unsafe ConditionHousekeepingAt backside of lab, cylinder trolley was placed on walkway, needs to be removed.KOR RefineryLABCivilPRLRoutineKorangi RefineryClosed2026-07-19
2025-09-07Unsafe ActProcedureAt tank# 05, spark were falling directly on the gas cylinder while using the grinder. Informed to HSE supervisor and immediately remove gas cylinder remove this place.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-08
2025-09-07Unsafe ActProcedureAt tank # 05, D-door was hold by the workers instead of hold by the chain block while its installing and welding.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-08
2025-09-04Unsafe ActWork at HeightAt 103E, 104E, and 102E, during scaffolding dismantling, one AKS scaffolder was found not using tool tie.Plant Area103E, 104E, and 102ECivilCONTRACTORAKSRoutineKorangi RefineryClosed2025-09-05
2025-09-04Unsafe ActWork at HeightAt tank 05, a wroker found without wearing rigging gloves while rigging activity of pipes. Informed to HSE supervisor and counseling .Plant AreaTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-05
2025-09-11Unsafe ActPPEPermit was issued but not available at the site, and scaffolding work was in progress. Informed to HSE lead.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2025-09-11Unsafe ActProcedureAt tank # 05, nearby main D .Door  scattered material was present. Informed to HSE supervisor and immediately remove these materials.Tank FarmAt Tank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-12
2025-09-13Unsafe ActElectricalAt tank#11, during the tool inspection, it was observed that the electrical inspection tags of 2 LED lights were found expired. Informed to HSE supervisor and immediately electrical inspection tag install.Tank FarmTank #11ElectricalCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-13Unsafe ActPPEAt tank # 11, while working on chain block, the impact gloves of rigger was found damaged, informed to HSE supervisor and immediately replace gloves.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-13Unsafe ActPPEAt tank # 05, during handing of MS plate, the scaffolders were found without wearing impact gloves, informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-13Unsafe ActProcedureAt tank # 05, during the painting work, the electrical inspection tag of mixture machine was found expired. Informed to HSE supervisor and Electrician immediately inspection and tag install.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-13Unsafe ActPPEAt tank #05, one worker was using a drill machine without wearing safety gloves. Informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-13Unsafe ActPPEAt tank #11, one fitter was lifting and shifting a Garder without wearing rigging gloves. Informed to HSE supervisor during lifting /shifting activities to avoid hand injuries.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-14
2025-09-14Unsafe ActElectricalAt tank # 05, Main Electrical DB was tripping repeatedly and the electrician was not present. Informed to HSE supervisor maintenance team to arrange an alternate electrician and ensure proper inspection of the Main Electrical DB.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-15
2025-09-14Unsafe ActProcedureAt tank # 05, some workers entered the tank whose names were not included in the SBM medical list .(Nizam sb, Usman sb, Mr. Nasir, Mr. Irfan, Mr. Kaim visitor and Mr. Shahid Lodhi ATL) informed to HSE supervisor ensure only medically cleared workers are allowed the tank to verify medical fitness before assigning confined space.Tank FarmAt Tank # 05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-15
2025-09-18Unsafe ActElectricalThe handle of the CO2 fire Extinguisher was damaged placed near the electrical generator. Informed to HSE supervisor and immediately replace CO2 fire Extinguisher.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-19
2025-09-19Unsafe ConditionPPEAt tank # 05,(Mr. shahid Lodhi) during the visit found without wearing safety gloves while handling the electrical bord and LED light.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-09-16
2025-09-19Unsafe ConditionPPEAt tank # 05, a worker during the grinding activity found without earplug, informed to HSE supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-09-16
2025-09-19Unsafe ConditionPPEAt tank # 11,during the material shifting 02 nos ATL workers were lifting an H-beam without wearing safety impact gloves. Informed to HSE supervisor and safety gloves wearing.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2025-09-16
2025-09-21Unsafe ActProcedureAt ATL workshop the operator was not present with generator. Informed to HSE supervisor.KOR RefineryATL WorkshopConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-09-21Unsafe ActProcedureAt tank # 05, gas cylinder was placed very close to the work area. Informed to HSE supervisor and gas cylinder shifted to a safe distance form hot work area.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-09-21Unsafe ActProcedureAt tank # 05, while changing the disc of grinder the plug was connected (energized). Informed to HSE supervisor.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-09-21Unsafe ActProcedureAt tank # 05, some person entered the tank whose names were not included in the SBM medical list,(Mr. Khalid Anwar, Mr. Majeed sb.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-09-21Unsafe ActProcedureAt tank # 05, after replacement of the breaker and switch in the generator , the electrical tag was not re-tagged. Informed to HSE supervisor.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-10-03Unsafe ActPPEAt tank #11, during fabrication work, one fabricator was not wearing a safety glove. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-10-03Unsafe ActLine of FireAt tank # 11, sparks from the grinder were hitting to another worker. Informed to HSE lead.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-10-03Unsafe ActWork at HeightAt tank # 11, during the scaffolding modification one scaffolder safety harness’s lanyard was not hooked. Informed to HSE supervisor and counseling doneTank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-10-03Unsafe ActLine of FireAt tank # 05, during the crane operation, 01 worker was crossing the barricaded area. Informed to HSE supervisor and counseling done.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-10-07Unsafe ActProcedureAt tank#05,during the crane operation ,An MS plate buried under the ground was being pulled out using a mobile crane by applying excessive force. Informed to HSE supervisor and Rigging Supervisor.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2025-10-10Unsafe ConditionElectricalAt tank # 11, the cap of the three- phase receptacle (Female) connected to the main electrical panel was found broken.Tank FarmTank # 11ElectricalCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-11-29Unsafe ActProcedureAt road 18, while M/s UE team were performing hot work activity fire extinguisher was not available at site. Informed to site supervisorKOR RefineryRoad # 18StationaryCONTRACTORUERoutineKorangi RefineryClosed2026-07-19
2025-11-29Unsafe ActProcedureAt road 18, grinder operator and generator operator were found without wearing ear plugs. Counseling done.KOR RefineryRoad # 18StationaryCONTRACTORUERoutineKorangi RefineryClosed2026-07-19
2025-11-29Unsafe ActProcedureAt road 18, unavailability of grinder stand was observed. Informed to site supervisorKOR RefineryRoad # 18StationaryCONTRACTORUERoutineKorangi RefineryClosed2026-07-19
2025-12-04Unsafe ConditionProcedureAt Tank #11, parallel activities (grinding work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-04Unsafe ConditionProcedureAt Tank #11, parallel activities (grinding work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-04Unsafe ConditionProcedureAt Tank #11, parallel activities (grinding work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-04Unsafe ActProcedureAt Tank #11, parallel activities (grinding work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-04Unsafe ActProcedureAt Tank #11, parallel activities (grinding work) were observed in 5th and 5th shell.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-23Unsafe ActElectricalAt tank # 11, grinder was found placed on surface instead of stand while it is not in use. Informed to HSE supervisor.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-12-17Unsafe ConditionProcedureAt Tank #11, during mechanical work inside and outside the tank, loose materials were found. The site supervisor was informed for removal of the loose materials.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-19
2025-11-30Unsafe ActProcedureWild bushes need to be remove in tank # 54, 55, 58, & 57 yard.KTKTCivilPRLRoutineKemari TerminalClosed2026-07-20
2025-11-30Unsafe ActProcedurehydrant # B-10, tank # 55 yard, minor seepage in foam line T-joint.KTKTStationaryPRLRoutineKemari TerminalClosed2026-07-20
2025-11-26Unsafe ActPPEAt Tank #11, while working at height M/s ATL supervisor was found without wearing helmet chin guard. Counseling done.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-07-09
2025-11-27Unsafe ActProcedureAt Tank #11, M/s ATL worker was found wearing torn safety gloves. Counseling done.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-24Unsafe ConditionProcedureAt Tank #05, while welding miller was in operation, but operator was not available at nearby area.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-24Unsafe ConditionProcedureAt Tank #05, no rest shed was available.KOR RefineryTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-09-19Unsafe ConditionProcedureLow water pressure found on EEWS number 25 at gantry.Tank FarmTank #05CivilPRLRoutineKorangi RefineryClosed2026-07-20
2025-09-19Unsafe ConditionHousekeepingConcrete waste material placed on different location of road-4.Tank FarmRoad # 4CivilPRLRoutineKorangi RefineryClosed2026-07-20
2025-09-19Unsafe ConditionProcedureAt road-01 hydrant Number 27 concrete support required.Tank FarmRoad # 01CivilPRLRoutineKorangi RefineryClosed2026-07-20
2025-09-19Unsafe ConditionProcedureWeather protection shed required on fire alarm Number 56 block-2, FA-9 stationary workshop, FA-54 instrument workshop and FA-52 AC workshop.Tank FarmRoad # 01ElectricalPRLRoutineKorangi RefineryClosed2026-07-20
2025-09-15Unsafe ConditionProcedureAt tank#05, no mechanical work supervision from ATL was present. Informed to HSE lead.Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2025-09-15Unsafe ConditionPPEAt tank#05, 1 fitter was observed without safety gloves while using the grinder, informed to HSE supervisor and inshore use PPEs .Tank FarmTank#05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2025-09-15Unsafe ConditionPPEAt tank#11, 2 ATL workers were found wearing black googles during working inside the tank. Informed to HSE supervisor and change safety goggles.Tank FarmTank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2025-09-16
2025-10-17Unsafe ConditionPPEAt tank #11,the portable air compressor was connected with an electrical plug while activity was stopped. Informed to HSE supervisor and immediately disconnect plug.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-17Unsafe ConditionPPEAt tank #11,during sand blasting activities, workers were not wearing face masks.(N.95)informed to HSE supervisor and wearing a face mask.Tank FarmTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-10-21Unsafe ActEquipmentAt tank#15, during the hot work activities found the fire Extinguisher were not available near the generator, informed to HSE person.Tank FarmTank #15ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-04-05
2025-11-05Unsafe ActPPEAt tank#11,One worker was not wearing gloves during hammering activity, which increases the risk of hand injury. Informed to HSE supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-05Unsafe ActElectricalAt tank#11,The electrical tag on the indicator was expired, indicating that the equipment’s inspection was overdue. Informed to HSE  supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-05Unsafe ActPPEAt tank#11,Observation: During housekeeping activity, the worker was not wearing an N95 mask, which can lead to dust inhalation and respiratory issues. Informed to HSE supervisor.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-05Unsafe ActProcedureAt tank #05, during the dismantling of scaffolding  materials not barricaded in tank site. Informed to HSE supervisor and immediately all materials barricaded.Tank FarmAt Tank#11ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-06-24
2025-11-13Unsafe ActPPEAt tank # 05, SGS inspector found wearing low ankle shoes inside tank yard. Informed to HSE Lead.Tank FarmTank #05ConstructionCONTRACTORATLRoutineKorangi RefineryClosed2026-07-13
2025-11-14Unsafe ActProcedureAt tank # 05, A safety person and construction representative were not present during the crane operation. Informed to HSE Lead.KOR RefineryTANK# 05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-14Unsafe ActHousekeepingAt tank # 11, during the safety round poor housekeeping was observed at the back side of the tank. Informed to HSE supervisor.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-14Unsafe ActHousekeepingAt tank #11, the fan installed in the ventilation system was not operating. Informed to HSE supervisor.KOR RefineryTANK# 11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-16Unsafe ConditionElectricalAt tank # 11,during the hot work, welding cables was found damaged. Informed to HSE supervisor and replace the welding cables.Tank FarmTank #11ConstructionCONTRACTORATLRoutineKorangi RefineryteamClosed2026-06-24
2025-11-19Unsafe ConditionEquipmentAt Tank #11, operating handle of fire extinguisher was found damaged. HSE supervisor was informed.KOR RefineryTank #11ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09
2025-11-21Unsafe ActProcedureAt Tank #05, the confined space access area was not clear. The HSE supervisor was informed.Tank FarmTank #05ConstructionCONTRACTORATLRoutineN/AKorangi RefineryteamClosed2026-09-09