Observation Details
Date18 Nov 2025
CategoryPPE
FacilityKorangi Refinery
AreaKOR Refinery
Exact LocationTANK# 11
DepartmentConstruction
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameATL
StatusClosed
Assigned Toteam
Target Date—
Closed Date09 Sep 2026
Observation Summary
At tank 11, parallel activity was observed, welding work on above area and scaffolding modification in below area. Immediately stopped the activity and counseling of team was done at site.
Action Taken / Required
N/A