arrow_back Back
Date26 Mar 2026
CategoryProcedure
FacilityKorangi Refinery
AreaPlant Area
Exact LocationTank#11
DepartmentConstruction
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameATL
StatusClosed
Assigned Toteam
Target Date
Closed Date30 Mar 2026
Observation Summary

At Tank#11: The area needs to be properly barricaded as no work is currently in progress at the tank.

Action Taken / Required

N/A