arrow_back Back
Date22 Jan 2026
CategoryLine of Fire
FacilityKemari Terminal
AreaKT
Exact LocationTank # 56
DepartmentStationary
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameAJC
StatusClosed
Assigned Toteam
Target Date
Closed Date25 Jun 2026
Observation Summary

At Tank#56, AJC grinder men was grinding near crane operation, while the safety supervisor were at other side for site works.