arrow_back Back
Date21 Sep 2025
CategoryProcedure
FacilityKorangi Refinery
AreaKOR Refinery
Exact LocationTank #05
DepartmentConstruction
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameATL
StatusClosed
Assigned To
Target Date
Closed Date19 Jul 2026
Observation Summary

At tank # 05, while changing the disc of grinder the plug was connected (energized). Informed to HSE supervisor.