arrow_back Back
Date20 Aug 2025
CategoryLine of Fire
FacilityKorangi Refinery
AreaPlant Area
Exact LocationAt Plant Center
DepartmentStationary
CompanyCONTRACTOR
Routine / ShutdownShutdown
Contractor NameDEL
StatusClosed
Assigned Toteam
Target Date
Closed Date21 Aug 2025
Observation Summary

At plant center, bundle puller was slightly hit with steam line below the 107-F while lifting by the crane and the DEL workers were standing below the suspended load. Counseled the team.