Observation Details
Date30 Dec 2025
CategoryWork at Height
FacilityKorangi Refinery
AreaTank Farm
Exact LocationTank # 05
DepartmentConstruction
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameIIW
StatusClosed
Assigned Toteam
Target Date—
Closed Date01 Jan 2026
Observation Summary
At tank # 36, inside tank yard an iron hammer was being used to straight the scaffolding pipe very close to adjacent flanges. Informed to IIW HSE person & project manager.
