Date10 Feb 2026
CategoryWork at Height
FacilityKorangi Refinery
AreaPlant Area
Exact LocationBoiler No. 4
DepartmentCivil
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameAKS
StatusClosed
Assigned Toteam
Target Date
Closed Date20 Feb 2026
Observation Summary

At the Heat Exchanger area, scaffolding pipes were placed on the walkway without barrication.

Action Taken / Required

N/A