arrow_back Back
Date17 Mar 2026
CategoryPPE
FacilityKorangi Refinery
AreaTank Farm
Exact LocationTank #30
DepartmentRotary
CompanyCONTRACTOR
Routine / ShutdownRoutine
Contractor NameDEL
StatusClosed
Assigned Toteam
Target Date
Closed Date25 Mar 2026
Observation Summary

At Tank #30, A critical unsafe act was observed involving the Rotary team manually handling an electrical pump (approx. 100 kg) from the tank yard to the road. The task was performed without proper lifting equipment or appropriate rigging gloves.

Action Taken / Required

N/A