| 1373 |
12 Jun 2026 |
Unsafe Condition |
Construction |
At tank #30, grinder of M/s DEL was found without a functio … |
team |
Closed |
09 Sep 2026 |
|
| 1372 |
12 Jun 2026 |
Unsafe Condition |
Construction |
At Road No. 01, diesel was being filled into the generator w … |
team |
Closed |
09 Sep 2026 |
|
| 1371 |
12 Jun 2026 |
Unsafe Condition |
Construction |
At Road No. 01, during work in a temperature of 34°C, worker … |
team |
Closed |
09 Sep 2026 |
|
| 1370 |
12 Jun 2026 |
Unsafe Condition |
Construction |
At Tank #30, during the inspection of the crane and lifting … |
team |
Closed |
09 Sep 2026 |
|
| 1369 |
12 Jun 2026 |
Unsafe Act |
Construction |
At tank #30, M/s DEL workers were observed crossing over pip … |
— |
Closed |
24 Jun 2026 |
|
| 1368 |
12 Jun 2026 |
Unsafe Condition |
Construction |
At tank #30, during crane operations, gas cylinder of M/s DE … |
team |
Closed |
09 Sep 2026 |
|
| 1367 |
12 Jun 2026 |
Unsafe Act |
Construction |
At road #4, during crane activity, M/s DEL workers were obse … |
team |
Closed |
09 Sep 2026 |
|
| 1366 |
11 Jun 2026 |
Unsafe Act |
Construction |
At tank #30: A welder was performing welding work without we … |
team |
Closed |
09 Sep 2026 |
|
| 1365 |
11 Jun 2026 |
Unsafe Act |
Construction |
At tank #21: M/s DEL worker was observed wearing damaged rig … |
team |
Closed |
09 Sep 2026 |
|
| 1364 |
11 Jun 2026 |
Unsafe Condition |
Construction |
At tank #04: while holding a C-channel, M/s IIW worker was o … |
team |
Closed |
09 Sep 2026 |
|
| 1363 |
11 Jun 2026 |
Unsafe Condition |
Construction |
At tank #04: During gas cutting activity, M/s IIW rigger was … |
team |
Closed |
09 Sep 2026 |
|
| 1362 |
11 Jun 2026 |
Unsafe Act |
Construction |
At tank #04: A mobile scaffold was relocated with an M/s IIW … |
team |
Closed |
09 Sep 2026 |
|
| 1361 |
08 Jun 2026 |
Unsafe Act |
Construction |
At the DEL Yard, welder was performing welding work without … |
team |
Closed |
09 Sep 2026 |
|
| 1360 |
08 Jun 2026 |
Unsafe Act |
Construction |
At tank#35, the potable stair being used to cross the ring w … |
team |
Closed |
09 Sep 2026 |
|
| 1359 |
08 Jun 2026 |
Unsafe Condition |
Construction |
At tank#35, diesel-filled jerry cans were found stored outsi … |
team |
Closed |
09 Sep 2026 |
|
| 1358 |
08 Jun 2026 |
Unsafe Act |
Construction |
At Tank #04, some workers of M/s IIW were using damaged rigg … |
team |
Closed |
09 Sep 2026 |
|
| 1357 |
08 Jun 2026 |
Unsafe Act |
Construction |
At the DEL Yard, during grinding work, a worker was observed … |
team |
Closed |
09 Sep 2026 |
|
| 1356 |
06 Jun 2026 |
Unsafe Condition |
Stationary |
M/s AJC, gas cylinders were not properly secured with chains … |
team |
Closed |
09 Sep 2026 |
|
| 1355 |
06 Jun 2026 |
Unsafe Condition |
Stationary |
At Tank #56, M/s AJC, during crane operations, electrical fa … |
team |
Closed |
09 Sep 2026 |
|
| 1354 |
06 Jun 2026 |
Unsafe Condition |
Stationary |
At Tank #56, M/s AJC, during hot work activities, the area o … |
team |
Closed |
09 Sep 2026 |
|