| 813 |
28 Jan 2026 |
Unsafe Condition |
Stationary |
Tank #11: During sand blasting activity, workers were expose … |
team |
Closed |
30 Jan 2026 |
|
| 812 |
28 Jan 2026 |
Unsafe Condition |
Stationary |
Tank # 56: During lux monitoring, inadequate lighting was ob … |
team |
Closed |
30 Jan 2026 |
|
| 811 |
25 Jan 2026 |
Unsafe Act |
Construction |
At tank # 35, during civil work, workers were found not wear … |
team |
Closed |
28 Jun 2026 |
|
| 810 |
25 Jan 2026 |
Unsafe Act |
Construction |
At tank # 11, during sandblasting, nearby some workers were … |
team |
Closed |
28 Jun 2026 |
|
| 809 |
25 Jan 2026 |
Unsafe Act |
Construction |
At tank # 11, during hot work activities, the platform gap w … |
team |
Closed |
28 Jun 2026 |
|
| 808 |
24 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, M/s AJC workers were not wearing gloves and gog … |
— |
Closed |
17 Jul 2026 |
|
| 807 |
24 Jan 2026 |
Unsafe Condition |
Stationary |
At tank #56, Grinder #02 was found on site without electric … |
— |
Closed |
17 Jul 2026 |
|
| 806 |
24 Jan 2026 |
Unsafe Condition |
Stationary |
At tank #56, three electrical board was found withou proper … |
— |
Closed |
17 Jul 2026 |
|
| 805 |
23 Jan 2026 |
Unsafe Act |
Construction |
At tank #56, AJC electrician was working on electric DP with … |
team |
Closed |
26 Jan 2026 |
|
| 804 |
23 Jan 2026 |
Unsafe Act |
Construction |
At tank #56, One Grinder was found without safety guard on s … |
team |
Closed |
26 Jan 2026 |
|
| 803 |
23 Jan 2026 |
Unsafe Act |
Construction |
At tank #56, M/s AJC DB (WP-01) was found without inspection … |
team |
Closed |
26 Jan 2026 |
|
| 802 |
22 Jan 2026 |
Unsafe Act |
Construction |
At tank # 35, generator shade not installed at office area. |
team |
Closed |
28 Jun 2026 |
|
| 801 |
22 Jan 2026 |
Unsafe Act |
Construction |
At tank # 35, unsafe manual hammering observed during steel … |
team |
Closed |
28 Jun 2026 |
|
| 800 |
22 Jan 2026 |
Unsafe Act |
Stationary |
At Tank#56, AJC grinder men was grinding near crane operatio … |
team |
Closed |
25 Jun 2026 |
|
| 799 |
22 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, Safety harness SH-5 lan-yard hook was damaged a … |
team |
Closed |
30 Jan 2026 |
|
| 798 |
22 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, During crane operation AJC welder and worker mo … |
team |
Closed |
30 Jan 2026 |
|
| 797 |
22 Jan 2026 |
Unsafe Act |
Construction |
At tank # 11, loose material was found on scaffolding platfo … |
team |
Closed |
28 Jun 2026 |
|
| 796 |
22 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, M/s AJC worker working with binding wire withou … |
team |
Closed |
25 Jun 2026 |
|
| 795 |
19 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, During hot work activity a fire extinguisher wa … |
— |
Closed |
17 Jul 2026 |
|
| 794 |
19 Jan 2026 |
Unsafe Act |
Stationary |
At tank #56, During crane operation lifting of MS plate, a 3 … |
— |
Closed |
17 Jul 2026 |
|