Safety Observations — All Years

1483
Total
9
Open
1474
Closed
Open: 9, Closed: 1474.
Open Closed
Unsafe Act: 609, Unsafe Condition: 874, Near Miss: 0, Positive: 0.
Unsafe Act Unsafe Cond.
PPE: 271. Work at Height: 208. Housekeeping: 149. Lack of Supervision: 144. Slip/Trip/Fall: 124. Electrical: 121. Equipment: 91. Procedure: 88. Line of Fire: 63. Vehicle: 52. Falling Object: 52. Environment: 44. Fire: 21. Health: 17. Emergency Response: 17. PTW: 12. SIMOP: 5. Pressure: 3. Ergonomics: 1.
PRL: 112, Contractor: 1371.
PRL Contractor

By Department

Construction: 835. Stationary: 475. Civil: 119. Logistic: 13. Electrical: 12. Operation: 7. OM KT: 6. A&S: 4. Rotary: 3. Tank Farm: 2.

By Contractor

DEL: 459. ATL: 337. IIW: 234. AJC: 202. UE: 31. RE: 25. AKS: 15. SWIFT: 14. WMS: 10. Afzal: 9.

Monthly Trend

Jul 2025: 61. Aug 2025: 304. Sep 2025: 77. Oct 2025: 74. Nov 2025: 81. Dec 2025: 74. Jan 2026: 116. Feb 2026: 93. Mar 2026: 97. Apr 2026: 207. May 2026: 70. Jun 2026: 107. Jul 2026: 120. Aug 2026: 2.
Observations List 1483 records
No Date Type Department Description Assigned To Status Closed Date Actions
403 14 Sep 2025 Unsafe Act Construction At tank # 05, Main Electrical DB was tripping repeatedly and … Closed 15 Sep 2025
402 14 Sep 2025 Unsafe Condition Construction At tank # 11, the HSE lead and HSE supervisor were not prese … Closed 15 Sep 2025
401 14 Sep 2025 Unsafe Condition Construction At tank # 05,the scaffolding team and fabrication team were … team Closed 15 Sep 2025
400 14 Sep 2025 Unsafe Condition Construction At tank # 11 and at tank #05, two generators were used despi … Closed 14 Sep 2025
399 14 Sep 2025 Unsafe Act Construction At tank # 05 ,one fitter during the power brushing not weari … Closed 15 Sep 2025
398 13 Sep 2025 Unsafe Act Construction At tank #11, one fitter was lifting and shifting a Garder wi … Closed 14 Sep 2025
397 13 Sep 2025 Unsafe Act Construction At tank #05, one worker was using a drill machine without we … Closed 14 Sep 2025
396 13 Sep 2025 Unsafe Act Construction At tank # 05, during the painting work, the electrical inspe … Closed 14 Sep 2025
395 13 Sep 2025 Unsafe Act Construction At tank # 05, during handing of MS plate, the scaffolders we … Closed 14 Sep 2025
394 13 Sep 2025 Unsafe Act Construction At tank # 11, while working on chain block, the impact glove … Closed 14 Sep 2025
393 13 Sep 2025 Unsafe Act Electrical At tank#11, during the tool inspection, it was observed that … Closed 14 Sep 2025
392 13 Sep 2025 Unsafe Act Construction At tank # 05, Mr. Shahid Lodhi CM use scaffolding ladders wi … Closed 14 Sep 2025
391 11 Sep 2025 Unsafe Act Construction At tank # 05, nearby main D .Door  scattered material was pr … team Closed 12 Sep 2025
390 11 Sep 2025 Unsafe Act Construction Permit was issued but not available at the site, and scaffol … Closed 12 Sep 2025
389 11 Sep 2025 Unsafe Act Construction At tank #05,  ATL 3 workers were found in confined space wit … Closed 12 Sep 2025
388 11 Sep 2025 Unsafe Act Construction At tank#05, ATL 1 fitter during the main D. Door MS  plate f … Closed 12 Sep 2025
387 11 Sep 2025 Unsafe Act Construction At tank #05, during the IFR work use Hammar workers not wear … Closed 11 Sep 2025
386 11 Sep 2025 Unsafe Act Construction At tank #05, during the cutting work use grinder worker not … Closed 12 Sep 2025
385 07 Sep 2025 Unsafe Act Construction At tank # 05, D-door was hold by the workers instead of hol … team Closed 08 Sep 2025
384 07 Sep 2025 Unsafe Act Construction At tank# 05, spark were falling directly on the gas cylinde … team Closed 09 Sep 2025