| 24 Oct 2025 |
2025-26 · Q1 |
Korangi Refinery |
Process & Utilities Plant Area |
Around new CW diesel engine pump foundation, redundant material was fo … |
Stationary |
— |
Closed |
— |
|
| 24 Oct 2025 |
2025-26 · Q1 |
Korangi Refinery |
Process & Utilities Plant Area |
Stagnant water was observed in new CW diesel engine pump foundation. |
Civil |
— |
Closed |
— |
|
| 24 Oct 2025 |
2025-26 · Q1 |
Korangi Refinery |
Process & Utilities Plant Area |
Plant and Utilities area , catchment basins along with grating cleanin … |
Civil |
— |
Closed |
— |
|
| 24 Oct 2025 |
2025-26 · Q1 |
Korangi Refinery |
Process & Utilities Plant Area |
Plant Area spit bins was found in pathatic condition, need to be remov … |
A&S |
— |