Safety Observations — All Years

1483
Total
9
Open
1474
Closed
Open: 9, Closed: 1474.
Open Closed
Unsafe Act: 609, Unsafe Condition: 874, Near Miss: 0, Positive: 0.
Unsafe Act Unsafe Cond.
PPE: 271. Work at Height: 208. Housekeeping: 149. Lack of Supervision: 144. Slip/Trip/Fall: 124. Electrical: 121. Equipment: 91. Procedure: 88. Line of Fire: 63. Vehicle: 52. Falling Object: 52. Environment: 44. Fire: 21. Health: 17. Emergency Response: 17. PTW: 12. SIMOP: 5. Pressure: 3. Ergonomics: 1.
PRL: 112, Contractor: 1371.
PRL Contractor

By Department

Construction: 835. Stationary: 475. Civil: 119. Logistic: 13. Electrical: 12. Operation: 7. OM KT: 6. A&S: 4. Rotary: 3. Warehouse: 2.

By Contractor

DEL: 459. ATL: 337. IIW: 234. AJC: 202. UE: 31. RE: 25. AKS: 15. SWIFT: 14. WMS: 10. Afzal: 9.

Monthly Trend

Jul 2025: 61. Aug 2025: 304. Sep 2025: 77. Oct 2025: 74. Nov 2025: 81. Dec 2025: 74. Jan 2026: 116. Feb 2026: 93. Mar 2026: 97. Apr 2026: 207. May 2026: 70. Jun 2026: 107. Jul 2026: 120. Aug 2026: 2.
Observations List 1483 records
No Date Type Department Description Assigned To Status Closed Date Actions
483 28 Oct 2025 Unsafe Act Construction At tank#05,during the safety round, four fitters were manual … team Closed 12 Jul 2026
482 28 Oct 2025 Unsafe Condition Construction At tank #11, during safety round, the ventilation fan instal … team Closed 05 Apr 2026
481 28 Oct 2025 Unsafe Condition Construction At tank #11, during the safety, round and Electrical tool in … team Closed 05 Apr 2026
480 28 Oct 2025 Unsafe Condition Construction At At tank# ATL yard, the ambulance driver was driving other … team Closed 05 Apr 2026
479 28 Oct 2025 Unsafe Act Construction At tank#05,during work at height activities ,one hammer and … team Closed 05 Apr 2026
478 28 Oct 2025 Unsafe Condition Construction At tank#05, during safety round different loose materials we … team Closed 05 Apr 2026
477 28 Oct 2025 Unsafe Condition Construction At tank #11,during the safety round, one 3-phase female sock … team Closed 05 Apr 2026
476 28 Oct 2025 Unsafe Act Construction At tank #11,during the material shifting one fitter was lift … team Closed 05 Apr 2026
475 28 Oct 2025 Unsafe Condition Construction At temporary M/s DEL fabrication yard, poor housekeeping was … team Closed 05 Apr 2026
474 24 Oct 2025 Unsafe Condition Civil At multiple locations (Near Kachra Kundi Road 4, access to t … team Closed 05 Apr 2026
473 22 Oct 2025 Unsafe Condition Logistic At tank #05,different types of materials were lying scattere … team Closed 05 Apr 2026
472 22 Oct 2025 Unsafe Condition Construction At tank#11,the Air compressor tire was sent yesterday for pu … team Closed 05 Apr 2026
471 22 Oct 2025 Unsafe Condition Construction At tank#05 , during the fabrication work the crude line spoo … team Closed 05 Apr 2026
470 22 Oct 2025 Unsafe Act Construction At ATL yard during MS plate shifting and cleaning 1 worker n … team Closed 05 Apr 2026
469 21 Oct 2025 Unsafe Act Construction At tank#15, during the hot work activities found the fire Ex … team Closed 05 Apr 2026
468 21 Oct 2025 Unsafe Condition Construction At tank#05, during grinding work, no support was provided to … team Closed 05 Apr 2026
467 21 Oct 2025 Unsafe Act Construction At tank #11, an ATL staff member was observed working on a h … team Closed 05 Apr 2026
466 21 Oct 2025 Unsafe Condition Construction At tank#15, during the hot work activities found the fire Ex … team Closed 05 Apr 2026
465 17 Oct 2025 Unsafe Condition Construction At tank #11,during sand blasting activities, workers were no … team Closed 05 Apr 2026
464 17 Oct 2025 Unsafe Condition Construction At tank #11,the portable air compressor was connected with a … team Closed 05 Apr 2026